Fixed-price contract
A fixed-price contract is a contract for work in which the parties agree one total price for a defined scope of work.
What is a fixed-price contract?
A fixed-price contract is a contract for work (zmluva o dielo) with one agreed total price for a defined scope of work. Slovak practice calls the price pevná cena diela. Neither the Civil Code nor the Commercial Code uses this phrase. The Civil Code speaks of a price agreed as a fixed sum (pevnou sumou). If the parties cannot agree a fixed sum, the price needs at least an estimate (§ 636 ods. 1). The Commercial Code requires a price or a method to determine it (§ 536 ods. 3).
The label does not decide the price. The contract text decides it. A "fixed price" with a vague scope can still lead to a dispute about what the price covers.
How does a fixed price differ from a unit-price contract?
A fixed price names one total before work starts. A unit-price contract names a price for each unit of an item, so the total follows the quantities that the parties measure. Neither code uses "unit-price contract" as a name. The table describes the two models as parties usually define them in the contract.
| Feature | Fixed-price contract | Unit-price contract |
|---|---|---|
| How the price is set | One total for the defined scope | A price per unit of each item, multiplied by the quantity |
| When the total is known | At signing, for the agreed scope | After the quantities are measured |
The bill of quantities lists the items and quantities that a unit-price contract multiplies. Both codes say the contractor performs the work at its own risk (Civil Code § 631, Commercial Code § 537 ods. 1). The sections read do not say who carries the risk of a wrong quantity, so the contract has to say.
Which code governs a fixed-price contract?
The Commercial Code governs obligations between entrepreneurs when the obligation clearly relates to their business activity (§ 261 ods. 1). The parties can also choose it in writing for a relation that § 261 does not cover (§ 262 ods. 1 and 2). A private person who builds a house for own use is a consumer when the contractor acts in business. The Civil Code then applies first (§ 52 ods. 2 and 4). The contract-for-work article explains how the codes are chosen.
Under the Civil Code, the client pays after the contractor finishes the work, unless the parties agreed otherwise. If the contractor works in parts or the work costs a lot, the contractor can ask for reasonable advances (§ 634 ods. 2). Under the Commercial Code, the client pays at the agreed time (§ 548 ods. 1).
What happens to a fixed price when something changes?
A fixed price covers the scope written in the contract, its drawings and the specified quality. It does not by itself cover work that the contract does not describe. The table shows what each code says in the sections read for this page. Where a cell says "no matching rule", the contract has to settle the point.
| Event | Commercial Code (businesses) | Civil Code (private client) |
|---|---|---|
| The parties agree to extend the work and not the price effect | The client pays a proportionally higher price (§ 549 ods. 1) | No matching rule for a fixed sum. A price agreed by budget allows work outside the budget only after written approval or a written order (§ 635 ods. 1) |
| The parties agree to reduce the work and not the price effect | The client pays a proportionally lower price (§ 549 ods. 1) | No matching rule |
| A hidden obstacle at the item under repair or at the site makes the agreed way of work impossible | The contractor tells the client without delay and proposes a change. The contractor may pause the work. If the parties do not agree in a reasonable time, either may withdraw (§ 552 ods. 1) | No matching rule |
| The client causes a delay or prevents the work | The contractor withdraws for the client's delay. The contractor then receives the contract price less the saving. This does not apply if a § 374 circumstance caused the delay (§ 548 ods. 2) | The contractor was ready, and circumstances on the client's side prevented the work. The contractor receives the agreed price less savings, other earnings and earnings that the contractor deliberately missed (§ 641 ods. 1) |
How are extra works and scope changes priced?
Viacpráce, or extra works, often cause disputes under a fixed price. The Civil Code rule on a budget-based price is strict. The contractor can charge work outside the budget only in two cases. The client approved it in writing, or ordered it in writing later (§ 635 ods. 1). A written order that states the price, made before work starts, gives both parties the best proof.
Under the Commercial Code, the parties can change the work and not agree the price effect. The price then rises or falls with the difference in the needed activity and the reasonable costs of the changed work (§ 549 ods. 2). A written change order that states the new price avoids this default rule.
When can a contractor ask for a higher price?
For a price based on a budget, the Commercial Code says the budget does not by itself change the price (§ 547 ods. 1). There is an exception. The contract can say that the budget is not guaranteed complete. The contractor can then claim a reasonable increase for activities outside the budget. No one could foresee them at signing (§ 547 ods. 2). The contractor loses the claim if the contractor does not report the need and the amount without delay (§ 547 ods. 6).
If the claimed increase is more than 10 % above the budget price, the client can withdraw without delay. The client must then pay for the part already done (§ 547 ods. 5). If the client does not agree to an increase, a court sets it on the contractor's petition (§ 547 ods. 4).
The Civil Code rule applies to an estimate. The contractor can find that the estimated price must rise substantially. The contractor must then warn the client in writing without delay and state the new price. Without that warning, the contractor has no right to the difference (§ 636 ods. 1). After the warning, the client can withdraw (§ 636 ods. 2).
Can the client leave a fixed-price contract?
Under the Civil Code, the client can withdraw until the work is done. The client then pays for the work already done, unless the contractor can use the result elsewhere. The client also repays the costs that the contractor incurred for the purpose (§ 642 ods. 1). The client can also withdraw if it is clear that the work will not be ready in time or will not be done properly. The contractor must first fail to put this right in a reasonable time that the client allows (§ 642 ods. 2). A fixed price does not lock the client in.
How is a fixed price different from a budget-based price?
A fixed price names one total. A budget-based price follows a list of expected costs. The codes treat the two differently. For a budget-based price, the Civil Code bars an increase without the client's consent (§ 635 ods. 1). The Commercial Code allows a claim only in the cases in § 547 ods. 2 and 3. Ask whether the budget is a guarantee or an estimate, because the answer decides which of these rules can apply. The construction budget entry explains the budget itself.
What should the contract say about a fixed price?
Check four things before signing. First, the scope, listed by drawing and specification. Second, the procedure and price for extra works, with a written order. Third, the way the contract handles a hidden condition on site. Fourth, the time of payments, including advances. The progress payment entry covers payment by completed stage. The retention money entry covers the amount that the client holds back until the contractor removes defects. A clause that circumvents the consumer rules is invalid for a consumer client (§ 52 ods. 2).
Frequently asked questions
- Does a fixed price mean the final bill can never change?
- No. A fixed price covers the agreed scope and quality. A change that both parties agree can change the price (Commercial Code § 549). The contract should say how each change is priced and approved in writing.
- Can a contractor charge for extra works after the contract is signed?
- Under the Civil Code, a price agreed by budget allows work outside the budget in two cases. The client approved it in writing, or ordered it in writing later (§ 635 ods. 1). An oral instruction does not meet this rule.
- Is a fixed price a term in Slovak law?
- No. The Civil Code speaks of a price agreed as a fixed sum (pevnou sumou). Without one, the price needs at least an estimate (§ 636 ods. 1). The Commercial Code requires a price or a method to determine it (§ 536 ods. 3).
- Which code governs a fixed-price contract with a building firm?
- Between entrepreneurs acting in business, the Commercial Code applies (§ 261 ods. 1). A private person who is a consumer gets the Civil Code first (§ 52 ods. 2). The contract for work article explains the choice.
- What happens if the contractor finds a hidden problem on site?
- Under the Commercial Code, the contractor must notify the client and propose a change. The contractor may pause the work until the parties agree (§ 552 ods. 1). The Civil Code sections read for this page set no such procedure, so the contract should define it.
- Can the client withdraw from a fixed-price contract?
- Under the Civil Code, yes, until the work is done. The client pays for the work already done, unless the contractor can use the result elsewhere. The client also repays the costs that the contractor incurred for the purpose (§ 642 ods. 1).
Sources
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 52, § 631, § 634, § 635, § 636, § 641, § 642
- Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261, § 262, § 536, § 537, § 546 to § 549, § 552