Extra works
Extra works are works beyond the scope agreed in a contract for work, which the contractor can charge only under that contract's price rules.
What are extra works (viacpráce)?
Extra works (viacpráce) are works that go beyond the scope that the parties agreed in a contract for work. The opposite case is menejpráce, work that the parties agree to drop. Neither the Civil Code nor the Commercial Code uses these two words. They are practice terms. Both codes deal with the same situations under their rules on the price and on a change of the work.
Extra works change the amount that the client owes. The sections below show which rule decides whether the contractor can charge for them.
Which price rules apply to extra works?
The answer depends on the code that governs the contract and on how the parties set the price. The Commercial Code (Obchodný zákonník, 513/1991 Zb.) governs obligations between entrepreneurs when the obligation clearly relates to their business (§ 261 ods. 1). Otherwise the Civil Code (Občiansky zákonník, 40/1964 Zb.) applies. A consumer, such as a private person who builds a house for own use, gets the Civil Code first (§ 52 ods. 2 and 4).
Under the Civil Code, a price agreed by budget may not rise without the client's consent. Work outside the budget is chargeable only if the client approved it in writing or ordered it in writing later. Under the Commercial Code, the contractor has more room to claim an increase, but must report it without delay. The table sets out the main points.
| Point | Civil Code | Commercial Code |
|---|---|---|
| Price set by a budget | § 635 ods. 1: no increase without the client's consent. Work outside the budget is chargeable only if approved in writing or ordered in writing later | § 547 ods. 1: a budget that is part of the contract does not by itself change the price |
| Budget not guaranteed complete | No matching rule in § 635 and § 636 | § 547 ods. 2: the contractor can claim a reasonable increase for activities outside the budget that no one could foresee at signing |
| Budget not binding under the contract | No matching rule in § 635 and § 636 | § 547 ods. 3: the contractor can ask to set an increase by the amount that the necessary, reasonable costs exceed the budget costs |
| Price set by an estimate | § 636 ods. 1: the contractor must warn the client in writing without delay if the estimate will rise substantially, or lose the right to the difference | No matching rule for an estimate in § 546 to § 549 |
| Time limit for the contractor | § 636 ods. 1: in writing and without delay | § 547 ods. 6: the claim lapses if the contractor does not report the need and the amount without delay |
| Client exit right | § 636 ods. 2: the client can withdraw after the new price is announced | § 547 ods. 5: the client can withdraw without delay if the claimed increase is more than 10 % above the budget price |
The Civil Code rule is stricter for the contractor. Under the Commercial Code, an increase that the client does not accept can go to a court. The court sets the increase on the contractor's petition (§ 547 ods. 4).
Does the client have to approve extra works in writing before the work starts?
For a price agreed by budget under the Civil Code, yes in effect. Section 635 ods. 1 limits what the contractor can charge for work outside the budget. The client must have approved it in writing, or ordered the work in writing later. The text sets no deadline for the writing. A spoken instruction on site does not meet the rule, because the law requires writing.
Advice, not a legal requirement: sign the written change agreement before the extra work starts. Name what changes, the price of the change, and the effect on the completion date. An agreement that names only the work and leaves the price open can lead to a dispute about the amount.
How are extra works priced?
Neither code sets a formula for extra works. Both codes give a default for the price that the parties did not set. Under the Civil Code the client pays a reasonable price if the contract and the regulations do not set one (§ 634 ods. 1). Under the Commercial Code a contract can be valid with no price. The client then pays the price that is usual for a comparable work (§ 546 ods. 1).
For a change that both parties agree, the Commercial Code gives a more specific default. The parties can extend or limit the work and not agree the effect on the price. The client then pays a proportionally higher or lower price (§ 549 ods. 1). If the parties change the work and do not agree the effect on the price, the price rises or falls. It follows the difference in the needed activity and the reasonable costs of the changed work (§ 549 ods. 2).
A contract can also state the price of extras in advance. For example, it can say that each extra item is priced at the unit prices from the contractor's offer, applied to the changed quantity. This is a drafting choice, not a legal requirement. It works only if the offer lists unit prices, so ask for them before signing. The quantities come from the bill of quantities, and the prices come from the priced construction budget.
Does a fixed price rule out extra works?
No. A fixed-price contract covers the scope written in the contract. Work outside that scope is a change of the work. Under the Commercial Code, the parties can agree the change and its price (§ 549). The Civil Code sections read set no rule for work outside a fixed sum. The contract has to say how the parties order and price it.
What risk do extra works carry for the client?
Extra works change the amount that the client owes, and the way of approval decides how much room for dispute remains. A verbal approval, or a signed approval with no price, leaves the amount to the rules above. Under the Commercial Code the contractor can ask a court to set an increase (§ 547 ods. 4).
- Ask the contractor to state in the contract whether the budget is complete. Under Commercial Code § 547 ods. 2 and 3 the answer decides whether and how the contractor can claim an increase.
- Keep every written change agreement with the contract, because it proves what the client approved.
- Do not sign an approval that leaves the price open.
- Compare the running total of approved extras with the budget at regular intervals.
Under the Civil Code rule for a price agreed by budget, the contractor cannot add unapproved work to the bill. The cost of that protection is the paperwork.
How should a client handle a request for extra works?
Handle each request in the same order. This is advice, not a legal procedure. The aim is that the approval is in writing and the price is known before the work starts.
- The contractor describes the extra work and states the quantity, using the same item list as the bill of quantities.
- The contractor prices the change, ideally with the offer's unit prices, and states the effect on the completion date.
- The client reviews the price and the schedule effect, and asks for a correction if a line is unclear.
- Both parties sign the written change agreement. Only then does the work start.
| Document | What it records |
|---|---|
| Change agreement | The work added or removed, its price, and any change to the completion date |
| Updated budget | The original budget with each approved change added, so the running total stays visible |
| Site record | The date of the work and the people who confirmed it |
What if the parties reduce the work (menejpráce)?
Under Commercial Code § 549 ods. 1, the parties can agree to limit the scope and not agree the price effect. The client then pays only a proportionally lower price. The Civil Code sections read set no matching reduction rule, so write the price effect into the agreement.
Frequently asked questions
- What is the difference between viacpráce and menejpráce?
- Viacpráce are works added beyond the agreed scope. Menejpráce are works dropped from it. Neither code uses these words. Under Commercial Code § 549 ods. 1, an agreed extension or limit changes the price in proportion. This applies if the parties did not agree the price effect.
- Can a contractor charge for extra works without written approval?
- Under the Civil Code, a price agreed by budget limits what the contractor can charge. The client must have approved the work in writing, or ordered it in writing later (§ 635 ods. 1). An oral instruction does not meet that rule.
- Can a contractor claim more money for unforeseen work under the Commercial Code?
- Yes, if the contract says that the budget is not guaranteed complete. The contractor can then claim a reasonable increase for activities that no one could foresee at signing (§ 547 ods. 2). The claim lapses if the contractor does not report the need and the amount without delay (§ 547 ods. 6).
- When can a client withdraw because of extra works?
- Under Commercial Code § 547 ods. 5, the client can withdraw without delay. This applies if the claimed increase is more than 10 % above the budget price. Under the Civil Code, the client can withdraw after the contractor announces a new price for an estimate that rises substantially (§ 636 ods. 2).
- How are extra works priced?
- Neither code sets a formula. Suppose the parties agree a change and not its price effect. The Commercial Code then adjusts the price by the difference in needed activity and reasonable costs (§ 549 ods. 2). A contract can also fix the unit prices for extras in advance.