Progress payment

A progress payment is a part of the contract price that a client pays when an agreed stage of the work is finished, not in advance.

What is a progress payment in a construction contract?

A progress payment (čiastková fakturácia) is a part of the contract price that the client pays when an agreed stage of the work is finished. The client pays as the building goes up, not the whole price at the end or at the start. It is a payment term, not a separate type of contract. It sits inside a contract for work (zmluva o dielo), often with a fixed-price contract, where a schedule lists each stage and its share of the price.

Neither the Civil Code nor the Commercial Code uses the term progress payment. The Civil Code speaks of advances (preddavky) during work done in parts. The stage schedule is therefore a contract term that the parties write.

When is the price due if the contract says nothing about stages?

The Civil Code sets the default for a private client. Under § 634 ods. 2 the price is paid after the work is finished, unless the parties agree otherwise. The same paragraph adds that when the work is done in parts, or needs considerable costs, the contractor may ask the client for reasonable advances while the work is under way.

The Commercial Code governs contracts between businesses. There the client must pay the price at the time agreed in the contract (§ 548 ods. 1). If the contract and the act say nothing else, the right to the price arises when the work is performed. A stage payment therefore exists only where the contract creates it.

How does a progress payment differ from an advance payment?

A progress payment pays for work already done. An advance (preddavok, often issued as a zálohová faktúra) pays before the work is done. The Commercial Code says that agreeing and paying advances does not affect § 548 and 549 (§ 546 ods. 2). Those sections set when the right to the price arises and how the price changes after a change of scope.

FeatureProgress paymentAdvance payment
What it pays forWork already done at a stageWork not yet done
Basis in the codesPayment time agreed in the contract (Commercial Code § 548 ods. 1)Agreed advances (Commercial Code § 546 ods. 2). For a private client, reasonable advances on request where work is done in parts or is costly (Civil Code § 634 ods. 2)
Evidence the contract can requireSigned stage protocol, site diary entry, invoice for the stageAdvance invoice and a rule for setting it off against the final price

What evidence should support each stage payment?

The codes tie a payment to no specific record, so the contract has to name the proof. Three items work well: a written description of the stage, a record that the stage is done, and an invoice that matches the schedule.

The site diary is the natural record. Under the Stavebný zákon (Act 25/2025 Z. z.), the stavebný denník is the documentary record of construction progress from taking over the site to handing over the building (§ 10 ods. 2). The stavbyvedúci (site manager) must keep it. It is available for entries and checks from the first day the site is set up until the building is handed over (§ 39 ods. 1). A diary entry shows that work took place. It does not accept the work for payment, so the contract should require a signed stage protocol as well.

The table shows an example schedule. It is a drafting example, not a requirement of any act. The contract should name the real stages of each project.

StageAccepted whenEvidence to attach
Foundations and slabThe slab is complete and matches the verified projectSigned stage protocol, diary entry, photographs
Shell and roofThe structure is closed and the roof is watertightSigned stage protocol, diary entry
Services rough-inPipes and cables are in place and the agreed tests are recordedTest records, stage protocol, diary entry
Finishes and fittingsRooms are finished and the client has accepted themProtocol signed by both parties
Final stageThe building is handed overHandover protocol (see building handover)

How does a progress payment relate to retention money?

A progress payment and retention money (zádržné) both change when the client pays, but in opposite directions. A progress payment brings a payment forward as a stage ends. Retention holds back part of a payment as security for defects that may appear later. A contract can combine them. The schedule sets what falls due at each stage, and a retention clause says how much of each payment the client holds and when it releases it. The codes set no figure for either, because both are contract terms.

How do progress payments fit with a fixed price and with changes?

A fixed price fixes the total, while a progress payment fixes the timing. Under the Civil Code, a price agreed by budget may not rise without the client's consent. Work and costs outside the budget can be charged only if the client approved them in writing, or ordered them in writing afterwards (§ 635 ods. 1).

Between businesses, the Commercial Code has its own rules on a budget price. The contractor may claim an increase only in the cases the act names, and must report the need without undue delay (§ 547 ods. 2, 3 and 6). The client may withdraw if the increase is more than 10 % above the budget price (§ 547 ods. 5). If the parties agree a change after signing and say nothing about the price, the price rises or falls with the change in work and cost (§ 549 ods. 2). In both codes, agree an extra stage or change in writing before billing it.

What mistakes should clients and architects avoid with progress payments?

Most disputes over stage payments come from a few gaps. The list below is drafting advice, not a legal rule.

  • Paying a stage on the invoice date instead of on the signed protocol.
  • A schedule whose stage shares do not add up to the contract price.
  • Vague stage descriptions such as "structure done", which invite argument about what the client accepted.
  • Treating a stage payment as final acceptance of the whole building.
  • Agreeing extra work by phone or on site without a written change order.

Frequently asked questions

What does progress payment mean in a Slovak building contract?
It means the client pays a share of the price when each agreed stage is finished, as the contract sets out. The codes do not use the term. For a private client the default is payment after completion, with reasonable advances allowed for work done in parts (Civil Code § 634 ods. 2).
Is a progress payment the same as a preddavok?
No. A preddavok, or advance, is paid before the work is done. A progress payment is paid when a stage is finished. Both can appear in one contract.
When is the price due if the contract is silent?
For a private client under the Civil Code, the price is due after the work is finished (§ 634 ods. 2). Between two businesses, the Commercial Code uses the payment time agreed in the contract (§ 548 ods. 1).
Does the stavebný denník decide when a stage is paid?
No. The site diary records progress, and the site manager must keep it (§ 39 ods. 1 of Act 25/2025). The payment trigger comes from the contract and the signed stage protocol.
Can the client hold back money from a stage payment?
Only where the contract provides for it, for example as retention money. The codes set no percentage or release rule, so the clause itself decides.
Can the contractor add a stage to the price later?
For a budget price under the Civil Code, only with the client's written approval or written order (§ 635 ods. 1). Between businesses, the Commercial Code allows an increase only in the cases it names (§ 547).

Sources

  1. Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 631, § 634 ods. 2, § 635 ods. 1
  2. Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 536, § 546 ods. 2, § 547 ods. 2, 3, 5 and 6, § 548 ods. 1, § 549 ods. 2
  3. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 10 ods. 2, § 39 ods. 1