Retention money

Retention money is a part of the contract price that a client holds back as security until defects are fixed or the warranty ends.

What is retention money in a construction contract?

Retention money (zádržné) is a part of the price that the client keeps back from the contractor as security for defects. The contract decides how much the client holds and when it pays the money out.

Retention is not a separate type of contract. It is a clause inside the contract for work (zmluva o dielo). The parties write its share, its release events and its conditions into that clause. Neither code names it as a contract term.

Why does the client hold back part of the price?

A building is rarely perfect on the day of handover. Between businesses, the contractor is liable for defects the work has at handover (Commercial Code § 560 ods. 2). A private client under the Civil Code has the same protection (Civil Code § 646 ods. 1). The Civil Code also covers defects that appear later. For a building the warranty period is three years from the day the client should take it over (§ 646 ods. 3). A regulation may set a shorter period for some parts of a building, but never below eighteen months.

Retention gives the client a sum to draw on while defects are still open. A contractor who already has the full price has less reason to return for a small crack or a faulty door.

Can the client withhold money without a retention clause?

Between businesses, partly. The Commercial Code applies its rules on defects in goods to a work, with the necessary changes (§ 564). One of them says the client need not pay the part of the price that matches its claim for a price reduction until the defects are fixed (§ 439 ods. 4). The Civil Code sections on the contract for work (§ 631 to 656) contain no such rule. A private client who wants to hold back money therefore needs a retention clause.

Is there a legal percentage for retention in Slovakia?

No. The Commercial Code and the Civil Code (versions from 17 August 2026 and 31 July 2026) set no retention rate. They use the word zádržné only for a lien (zádržné právo) over a thing, for example in storage and carriage. A lien is a different tool. The percentage, the amount at each stage and the release conditions are a matter of agreement. Treat a fixed percentage quoted as "the law" with suspicion, and ask for the section it cites.

When is retention money released?

Release follows the events in the contract. The table lists the events that the codes define. Dates are fixed by law only where the contract does not fix them.

EventWhat the code saysBasis
HandoverThe contractor finishes the work properly and hands it over at the agreed place. A handover protocol is drawn up if either party asks.Commercial Code § 554 ods. 1 and 6
Inspection and defect noticeThe client must inspect the work as soon as possible after handover. A court does not grant rights from defects that the client did not report without undue delay. Later defects must be reported at the latest two years after handover, or five years for buildings. Where a warranty applies, the warranty period replaces that limit.Commercial Code § 562 ods. 1 and 2
Warranty periodThe warranty period for a work starts at handover. A warranty exists where the contract or a declaration gives it. A private client under the Civil Code has three years for a building.Commercial Code § 563 ods. 1, § 429 ods. 2. Civil Code § 646 ods. 3
Final releaseThe last part of the retained sum is paid when the contract says so.Set by the contract

Many contracts tie the final release to two conditions, the end of the warranty and a closed defects list. That is a drafting choice, not a rule of the codes.

How does retention money differ from a bank guarantee?

Both give the client security against a contractor that does not finish or fix the work. They differ in where the security sits. Retention money stays with the client, held back from the price. A bank guarantee is a written promise by a bank to pay the client up to a stated sum (Commercial Code § 313).

FeatureRetention moneyBank guarantee
Who holds the securityThe client, from the priceThe bank, under the guarantee letter
How the client gets the moneyBy keeping the sum under the contractBy a written call on the bank (§ 319)
BasisA clause in the contractA written declaration by the bank (§ 313)

The codes do not say that a guarantee replaces retention. The parties can agree it, and the contract should then say when the guarantee takes over.

How is retention money different from a contractual penalty?

A contractual penalty is a sum that the parties agree for a breach of the contract. The party in breach must pay it even if the breach caused no damage. The agreement must be in writing and must state the amount or how to work it out (Civil Code § 544 ods. 1 and 2). Retention money is price the contractor has already earned. The client holds it as security against a defect that may appear later. The two can sit in one contract, so each clause should name the risk it covers.

What should a retention clause state?

These points are worth writing down. They come from the gaps above, because the codes set none of them:

  • the share, and whether it applies to the whole price or to each interim invoice,
  • the event that triggers each payment out, linked to the handover protocol and the defects list,
  • how long the client has to decide on a reported defect before the sum is released,
  • whether a bank guarantee may replace the retained sum.

Retention works with progress payments. If the contract holds back a share of each interim payment, read the two clauses together.

What are common misconceptions about retention money?

First, retention is not a penalty. It is a part of earned money that the client holds as security. Second, the client may not keep it for ever. The contract sets the release, and a hold with no end date invites a dispute. Third, the sum is only as large as the amount held. If a defect costs more, the client claims the rest under its rights from defects (Commercial Code § 564 with § 436 to 441, Civil Code § 646). Fourth, retention does not replace the handover protocol. The Commercial Code requires a protocol only on request (§ 554 ods. 6).

Frequently asked questions

What is retention money in a construction contract?
Retention money (zádržné) is a part of the contract price that the client keeps back as security for defects. The contract sets how much and when the client pays it out.
Is there a legal percentage for retention in Slovakia?
No. The Commercial Code and the Civil Code set no retention rate. The parties agree the share in the contract, so the clause itself is the text to check.
When does the warranty period start for a building?
Under the Commercial Code it starts at handover (§ 563 ods. 1), where the contract or a declaration gives a warranty. For a private client, the Civil Code sets three years from the day the client should take the building over (§ 646 ods. 3).
Can the client withhold money without a retention clause?
Between businesses, the client need not pay the part of the price that matches a price-reduction claim until defects are fixed (Commercial Code § 564 with § 439 ods. 4). The Civil Code sections on the contract for work have no such rule.
Can a bank guarantee replace retention money?
The parties can agree that it does. The codes do not require it. The contract should say when the guarantee takes over the security role.
Is retention money the same as a contractual penalty?
No. A contractual penalty is owed for a breach, even without damage (Civil Code § 544 ods. 1). Retention is earned money that the client holds as security against a later defect.

Sources

  1. Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261, § 313, § 319, § 429 ods. 2, § 439 ods. 4, § 536, § 554 ods. 1 and 6, § 560 ods. 2, § 562 ods. 1 and 2, § 563 ods. 1 and 2, § 564
  2. Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 544 ods. 1 and 2, § 631 to 656, § 646 ods. 1 and 3