Self-Consumption (PV)

Self-consumption is the share of the electricity from a photovoltaic system that the building uses on site instead of exporting it to the grid.

What is PV self-consumption?

Self-consumption is the share of the electricity from a photovoltaic (PV) system that the building uses on site instead of exporting it to the grid. The rest is surplus. The surplus either goes to the grid, as described under surplus electricity feed-in, or charges a home battery. EU law calls the owner a renewables self-consumer. This is a final customer who generates renewable electricity for its own use and may store or sell it (Directive (EU) 2018/2001, Article 2(14)). Slovak law uses the terms active customer, small source and local source, which this page explains.

How do you calculate the self-consumption share?

Divide the electricity the building uses from its own PV system by the total electricity the PV system generates over the same period. This is the definition used on this page. The result is a percentage. Use a full year, because the share changes with the season.

A second figure often appears next to it: self-sufficiency. Divide the electricity the building uses from its own PV system by the total electricity the building consumes. The two figures answer different questions. The first shows how much of the PV output stays on site. The second shows how much of the demand the PV system covers.

Arithmetic example, not a measured value: a system generates 100 kWh and the building uses 40 kWh of it at the time of generation. The self-consumption share is 40 %. If the building consumes 200 kWh in total, self-sufficiency is 20 %.

What decides how much PV electricity the building uses itself?

The overlap in time between generation and demand decides it. A PV system generates most around midday and in summer. A household that is empty during the day, or that heats mainly in winter, uses a smaller share of its own output. This page gives no typical percentage, because the sources checked for this page do not give a Slovak figure.

Four measures raise the share without a change of the PV array:

  • Move flexible loads, such as a washing machine or a hot-water tank, to the hours of generation.
  • Run a heat pump or an electric vehicle charger on PV electricity when the sun shines.
  • Add a home battery to keep midday surplus for the evening.
  • Choose a smaller array. A smaller array exports less, so the share rises, but the total output falls.

An energy management system can automate the first three measures.

What is a small source (malý zdroj) in Slovak law?

A small source is a renewable electricity device with a total installed power of up to 10.8 kW (Act 309/2009, Section 2(1)(l)). The act gives the owner of a small source rights, if the generation is not a business under a special act. The distribution system operator (DSO) must connect it at the existing metering point and install a metering device. Both are free of charge (Section 4a(1)). The DSO must do both within 5 working days after the conditions are met (Section 4a(4)).

The owner must meet these conditions (Section 4a(2) and (6)):

  • The total installed power does not exceed the value that the 16 A fuse on one phase secures.
  • The owner has a connection contract under the DSO operating rules.
  • The owner sends the DSO a notice of operation within 5 working days after start of operation.

If the owner does not send the notice, the DSO may disconnect the source (Section 4a(6)). A functional test is not required, unless the DSO asks for one for a reason in Section 4a(9). The owner may deliver unused electricity to the distribution system, within the maximum reserved capacity (Section 4a(13)).

What is a local source (lokálny zdroj) and why does it matter?

A local source is a renewable electricity device that supplies the metering point at its own handover point. Its installed power does not exceed the maximum reserved capacity of that metering point (Act 309/2009, Section 2(1)(o)). The producer is the customer at that metering point who has a connection contract for the local source (Section 4b(1)). Section 4a does not apply to a local source (Section 4b(18)).

A local source has these rights and limits:

  • The owner has the right to free connection, free exchange of the metering device and priority connection (Section 4b(2)).
  • The Úrad pre reguláciu sieťových odvetví (ÚRSO) keeps a list of local sources. It issues a confirmation of generation within 30 days after a complete application (Section 4b(6) and (7)).
  • The support forms in Section 3(1) do not apply to a local source (Section 4b(4)).
  • If the source exceeds its maximum reserved capacity in two consecutive quarter-hours, the DSO may disconnect it (Section 4b(15)).

The main financial effect is in Section 4b(19). The system-operation tariff (tarifa za prevádzkovanie systému) is not charged on electricity that a local source generates and the metering point consumes. The limit is 1,000 MWh per year. It starts in the month after ÚRSO issues the confirmation. The exemption does not apply to a company in difficulty or to a company that must repay unlawful state aid. If local sources reach 8 % of the installed generation capacity in Slovakia, ÚRSO may suspend new confirmations for one calendar year. It needs a published cost-benefit analysis first (Section 4b(20)). This page gives no tariff amount, because it needs a dated ÚRSO decision.

Which size limits apply to a household PV system in Slovakia?

Several limits exist. They come from different acts and mean different things. Do not read one of them as the limit of another.

LimitWhat it governsSource
10.8 kWDefinition of a small sourceAct 309/2009, Section 2(1)(l)
16 A fuse on one phaseInstalled power for the free connection rights of a small sourceAct 309/2009, Section 4a(2)(a)
10 kWSection 4a also applies to a group of small sources up to this total powerAct 309/2009, Section 4a(11)
11 kWGeneration is not energy business, if the producer does not claim the doplatok supportAct 251/2012, Section 4(4)
100 kWNo DSO opinion on reserved capacity for a local source without exportAct 309/2009, Section 4b(21)
1 MWActive customer: generation, storage or supply of electricity is not energy businessAct 251/2012, Section 4(5)
10.8 kWLargest electricity source eligible in the Zelená domácnostiam programme, as of November 2026SIEA programme page

The 10.8 kW in the programme page matches the small-source definition. It is a subsidy rule and not a legal limit on a larger system.

Does Slovakia pay a feed-in tariff for household PV?

The text of Act 309/2009 does not list solar power among the sources that get a guaranteed purchase price or a doplatok. Section 3 sets these forms of support and their scope:

Support form (Section 3(1))Scope in the act
Purchase by the výkupca elektriny and balancing responsibility taken over by the výkupcaUp to 250 kW: high-efficiency cogeneration, hydro, geothermal, biogas, landfill gas, sewage gas (Section 3(3))
DoplatokHydro, geothermal and gas sources up to 500 kW, and cogeneration up to 1 MW (Section 3(4))
Príplatok10 kW to 50 MW, chosen in a tender under Section 5c (Section 3(5))

Slovakia has no scheme that nets import against export. See net metering for the details.

For a household, the value of self-consumption is therefore the retail electricity purchase that the building avoids. This page gives no price per kWh, because a price needs a dated ÚRSO or act source.

Can a household combine a subsidy with a small source?

A subsidy may change the support rights. The owner of a small source loses the right to support under Section 3(1)(b) and (c) of Act 309/2009. This happens if a programme financed from the state budget gave support (Section 4a(8)). The Zelená domácnostiam programme of SIEA supports a PV panel in a family house. As of November 2026, the base rate is 500 EUR per kW with a cap of 1,000 EUR. With the 15 % increase it is 575 EUR per kW with a cap of 1,150 EUR. The household must operate the device for at least 5 years. Read the current programme page before you apply, because the rates change.

Can neighbours share the electricity from one PV system?

Yes, under electricity sharing in Act 251/2012. An active customer or an energy community may share electricity directly or through a sharing organiser (Section 35b(1)). Sharing needs a registration of the metering points in a sharing group with the short-term market operator (Section 35b(9)). A household customer who generates, stores or shares electricity is always an active customer (Section 4(6)).

Frequently asked questions

What is self-consumption in a PV system?
Self-consumption is the share of the electricity from a PV system that the building uses on site instead of exporting it to the grid. You calculate it as on-site use divided by total generation over the same period, ideally one year.
Is there a Slovak feed-in tariff for household solar panels?
No feed-in tariff for solar power appears in Section 3 of Act 309/2009. The purchase price and the doplatok apply to the sources listed in Section 3(3) and (4), which do not include solar. The príplatok applies only to installations of 10 kW to 50 MW that win a tender.
What is the system-operation tariff exemption for a local source?
The system-operation tariff is not charged on electricity that a local source generates and its metering point consumes. The limit is 1,000 MWh per year (Act 309/2009, Section 4b(19)). It starts in the month after ÚRSO issues the confirmation of generation.
What is the difference between a small source and a local source?
A small source has an installed power of up to 10.8 kW (Section 2(1)(l)). A local source generates for its own metering point and its installed power does not exceed the maximum reserved capacity of that point (Section 2(1)(o)). A local source loses the support forms in Section 3(1) (Section 4b(4)).
Does the 10.8 kW in Zelená domácnostiam limit what I may install?
No. The 10.8 kW is the size limit for a device that gets the subsidy, as of November 2026. It is the same figure as the small-source definition, but it does not forbid a larger system.
How can I raise my self-consumption?
Move flexible loads to the hours of generation, run a heat pump or vehicle charger on PV electricity, or add a home battery. A smaller array also raises the share, but it lowers the total output.

Sources

  1. Zákon č. 309/2009 Z. z. o podpore obnoviteľných zdrojov energie a vysoko účinnej kombinovanej výroby a o zmene a doplnení niektorých zákonov · Slov-Lex, consolidated version in force from 1 September 2026 · § 2 ods. 1 písm. l) a o), § 3 ods. 1 až 5, § 4 ods. 14, § 4a, § 4b
  2. Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Slov-Lex, consolidated version in force from 1 July 2026 (the version from 1 January 2027 keeps the cited wording) · § 2 písm. b) bod 19 a 20, § 4 ods. 4 až 6, § 34 ods. 2 písm. ac) a ad), § 35 ods. 4, § 35b
  3. Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources · European Union, Official Journal text (RED II) · Article 2(14), Article 21(1) to (4)
  4. Zelená domácnostiam: Podmienky podpory (Základné podmienky podpory pre rodinné domy) · SIEA, Slovenská inovačná a energetická agentúra