Energy Community (Citizen and Renewable Energy Community)

An energy community is a non-profit legal entity that produces, shares or supplies energy for its members. Slovak law also defines a renewable one.

What is an energy community in Slovak law?

An energy community (energetické spoločenstvo) is a legal entity founded to meet the energy needs of its members for community benefit and not for profit. § 11a ods. 1 of Act No. 251/2012 Z. z. defines it. It may produce, supply, share or store electricity, act as an aggregator, distribute electricity or run a charging station.

The act sets four conditions. The entity is not founded to make a profit (písm. b). People can join and leave by their own decision (písm. c). Only some members can control it (písm. d). They are natural persons, small enterprises, and certain municipal bodies and municipalities in the same higher territorial unit as the community. The purpose is environmental, economic or social benefit for the members (písm. a).

What is a renewable energy community in Slovak law?

A renewable energy community (komunita vyrábajúca energiu z obnoviteľných zdrojov) is a legal entity founded to produce electricity from renewable sources or biomethane. § 11a ods. 2 defines it. It has the same non-profit and open-membership conditions as an energy community. It may also supply, share, store and aggregate. Its members are only natural persons, small and medium enterprises, and certain municipal bodies.

The controlling members must live or have their seat in the higher territorial unit where the community's plant stands (§ 11a ods. 2 písm. e). A renewable energy community counts as an energy community too, unless the act says otherwise (§ 11a ods. 3).

How do the Slovak terms map to the EU terms?

Slovak law has two terms and EU law has two, and they are not the same pair. The EU terms are the citizen energy community (Directive (EU) 2019/944, Art. 2 point 11 and Art. 16) and the renewable energy community (Directive (EU) 2018/2001, Art. 2 point 16 and Art. 22). The list of EU acts transposed by Act 251/2012 includes both directives.

Slovak termClosest EU termWhat differs in the texts
energetické spoločenstvo (§ 11a ods. 1)citizen energy community (Directive 2019/944)May engage in generation "including from renewable sources". Members or shareholders control it, with no proximity condition in the EU definition.
komunita vyrábajúca energiu z OZE (§ 11a ods. 2)renewable energy community (RED II)Renewable energy only. The EU text requires control by members "located in the proximity" of the projects. The Slovak text states this as the same higher territorial unit.

The mapping is a reading of the two texts. The act does not name the matching EU term in § 11a.

Does an energy community need to register?

An energy community or a renewable energy community proves its status to other market participants with a certificate (osvedčenie). The regulatory office (úrad) issues and cancels it (§ 11a ods. 5). The office issues the certificate within 30 days of a written request from a person who shows that the conditions are met (§ 11a ods. 6).

The office keeps a record of the certificates and publishes a list of communities on its website (§ 11a ods. 11). If a community stops meeting a condition, it must tell the office without delay (§ 11a ods. 8). The office cancels the certificate if the community does not fix the problem in the set time. It also cancels it if the community obtained the certificate with false data (§ 11a ods. 10). The EU texts also expect fair, proportionate and transparent registration and licensing procedures (Directive 2019/944 Art. 16 ods. 1 písm. e, RED II Art. 22 ods. 4 písm. d). This page does not check whether a specific activity, such as supply, needs a separate authorisation.

What may an energy community do?

§ 35a ods. 1 of Act 251/2012 gives an energy community the right to do the following.

  • Buy electricity at its own metering point.
  • Produce electricity in a plant connected at its metering point or elsewhere.
  • Store electricity.
  • Supply its members with electricity from its own plant or storage, or electricity bought on the market.
  • Share electricity with its members, other active customers and other energy communities.
  • Aggregate for its members and run a charging station.

An energy community must have a contract on balancing settlement with the settlement body, including a financial security (§ 35a ods. 2). The duty does not apply if it passed balancing responsibility to another market participant by contract (§ 15 ods. 9). An energy community may share directly or through a sharing organiser (§ 35b ods. 1).

Can a household in a new house join an energy community?

A natural person can be a member under § 11a ods. 1 písm. d) and ods. 2 písm. d). Membership is optional, and a member can leave under § 11a ods. 1 písm. c). EU law says members keep their rights as household customers (Directive 2019/944 Art. 16 ods. 1 písm. c). The community itself does not have the rights of a household customer under § 35a ods. 3.

A house with its own photovoltaic array does not need a community to use its own electricity. See self-consumption, net metering and renewable energy source. Battery storage may belong to the community under § 35a ods. 1 písm. c).

Can an energy community pay out profit?

A community may pay out a share of profit, within a limit. Its activities still count as non-profit under this act (§ 11a ods. 4). The condition is that its founding document or statutes let members divide at most 50 % of the profit. The "50 %" is a ceiling for the share paid to members.

Frequently asked questions

What is an energy community in Slovakia?
An energy community is a legal entity that works for the energy needs of its members and not for profit. § 11a ods. 1 of Act 251/2012 Z. z. defines it. Members can join and leave freely.
What is the difference between an energy community and a renewable energy community in Slovakia?
A renewable energy community produces electricity from renewable sources or biomethane and has stricter member and location rules (§ 11a ods. 2). It counts as an energy community too (§ 11a ods. 3). The wider energy community is not limited to renewable energy.
How do the Slovak terms map to EU law?
The energy community is close to the EU citizen energy community of Directive 2019/944 Art. 16. The community producing energy from renewable sources is close to the renewable energy community of RED II Art. 22. They are two separate EU concepts.
Does an energy community need a certificate in Slovakia?
It needs a certificate from the regulatory office to prove its status to other market participants (§ 11a ods. 5). The office decides within 30 days of a written request (§ 11a ods. 6) and keeps a public list (§ 11a ods. 11).
Who can be a member of an energy community in Slovakia?
Natural persons, small enterprises and certain municipal bodies and municipalities can control an energy community (§ 11a ods. 1 písm. d). A renewable energy community has natural persons, small and medium enterprises and municipal bodies (§ 11a ods. 2 písm. d).
Can an energy community share electricity?
Yes. An energy community may share electricity from its own plant or storage with its members, other active customers and other energy communities (§ 35a ods. 1 písm. e). It may share directly or through a sharing organiser (§ 35b ods. 1).

Sources

  1. Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Slov-Lex · § 11a ods. 1 až 11
  2. Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Slov-Lex · § 35a ods. 1 až 3, § 35b ods. 1
  3. Smernica Európskeho parlamentu a Rady (EÚ) 2019/944 z 5. júna 2019 o spoločných pravidlách pre vnútorný trh s elektrinou (Directive (EU) 2019/944 on common rules for the internal market for electricity) · Official Journal of the European Union · Art. 2 point 11, Art. 16
  4. Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources · Official Journal of the European Union · Art. 2 point 16, Art. 22