Surplus Electricity Feed-In
Surplus electricity feed-in is the delivery of PV electricity that the building does not use to the grid, within the reserved capacity of the connection.
What is surplus electricity feed-in?
Surplus electricity feed-in is the delivery of PV electricity that the building does not use to the grid, within the reserved capacity of the connection. The Slovak name is dodávka prebytkov elektriny do siete. This phrase is not a defined term in the acts. Act 309/2009 describes the same thing in plain words: electricity from the source that the metering point does not consume (Sections 4a(13) and 4b(12)). The share the building keeps is its self-consumption. The source is usually a photovoltaic panel array.
What may a small or local source deliver to the grid?
The owner of a small source may deliver unused electricity within the maximum reserved capacity of the source (Act 309/2009, Section 4a(13)). The owner of a local source has the same right (Section 4b(12)). If the connection conditions do not allow a reserved capacity equal to the installed power, the parties agree a lower value (Sections 4a(12) and 4b(12)). A small source is a device of up to 10.8 kW (Section 2(1)(l)). A local source supplies its own metering point (Section 2(1)(o)).
What are the steps to connect a small source?
The steps for a small source follow Section 4a of Act 309/2009:
| Step | Time limit | Source |
|---|---|---|
| Ask the DSO for an opinion on reserved capacity | The DSO replies within 10 working days. The opinion is valid for 6 months. | Section 4a(3) |
| Sign a connection contract under the DSO operating rules | None stated | Section 4a(2)(c) |
| Tell the DSO the start date | At least 2 days before start of operation | Section 4a(5) |
| Send the notice of operation | Within 5 working days after start, and before the opinion expires | Section 4a(6) |
| The DSO connects the source and installs the meter | Within 5 working days after you meet the conditions | Section 4a(4) |
If the DSO does not reply within 10 working days, the applicant may start operation after the notice in Section 4a(5). The installed power must not exceed the value that the 16 A fuse on one phase secures (Section 4a(2)(a)).
What are the steps to connect a local source?
| Item | Small source (Section 4a) | Local source (Section 4b) |
|---|---|---|
| Power definition | Up to 10.8 kW (Section 2(1)(l)) | Not above the reserved capacity of the metering point (Section 2(1)(o)) |
| DSO reply to the capacity request | 10 working days, valid 6 months | 15 working days, valid 12 months |
| ÚRSO confirmation | Not mentioned in Section 4a | Within 30 days of a complete application |
| Support forms in Section 3(1) | Lost if state-budget programme support is given (Section 4a(8)) | Do not apply (Section 4b(4)) |
A local source follows Section 4b. The DSO must reply to the request for an opinion within 15 working days. The opinion is valid for 12 months (Section 4b(5)). The producer must deliver a complete notice of operation before the opinion expires (Section 4b(3)(c)). ÚRSO then issues a confirmation of generation within 30 days after a complete application (Section 4b(7)). A local source of up to 100 kW needs no DSO opinion. This holds only if the applicant ensures technically that no electricity reaches the grid (Section 4b(21)).
What happens if a local source exports more than its reserved capacity?
The DSO may disconnect a local source that exceeds its maximum reserved capacity in two consecutive quarter-hours. The DSO owes no compensation for damage (Act 309/2009, Section 4b(15)). The DSO must tell the producer the reason at least 5 working days before the disconnection (Section 4b(16)). The producer cannot reduce the reserved capacity of the metering point below the installed power while the source operates (Section 4b(14)).
Who pays for the surplus, and is the price regulated?
The acts checked for this page do not set a purchase price for the surplus of a household PV system. A local source may sell electricity to a customer under a renewable power purchase agreement or by peer-to-peer trading (Act 309/2009, Section 4b(13)). A producer that delivers electricity to the grid has the rights and duties of an electricity producer under a special act (Section 4b(13)). See the term power purchase agreement. For support schemes, see green bonus electricity.
The state purchase price in Section 3(1)(b) covers only the sources listed in Section 3(3), and solar is not among them. This page gives no price per kWh. A price needs a dated ÚRSO or act source, and the offer of a supplier is not such a source.
Do I need a licence to sell surplus electricity?
Not for a small system. Generation in a device of up to 11 kW is not energy business. The producer must not claim the doplatok support (Act 251/2012, Section 4(4)). For an active customer, generation up to 1 MW, storage up to 1 MW and the supply of electricity are not energy business (Section 4(5)). A household customer who generates, stores or shares electricity is always an active customer (Section 4(6)). The 11 kW limit differs from the 10.8 kW small-source limit, because the two acts use separate definitions.
Do I need a special meter?
Yes, a metering device that records both directions. For a small source, the DSO installs a determined meter free of charge. It counts generated and delivered electricity between phases in real time (Act 309/2009, Section 4a(1)(b)). For a local source, the DSO exchanges the meter free of charge. The new meter records electricity taken from the grid and delivered to it (Section 4b(2)(b)). The cited texts name the function of the meter and not the term smart meter.
What are the alternatives to exporting the surplus?
- Use more of it on site, for example in a heat pump, or store it in a home battery. Operating a storage device at the handover point does not affect the right to support under Section 3 (Act 309/2009, Section 4(14)).
- Share it with other active customers in a sharing group (Act 251/2012, Section 35b). See net metering for how sharing works.
- Install the source with no export. A local source of up to 100 kW then needs no DSO opinion on reserved capacity (Section 4b(21)).
What does EU law say about selling surplus electricity?
Member States must let active customers sell self-generated electricity, including through power purchase agreements (Directive (EU) 2019/944, Article 15(2)(b)). They must let renewables self-consumers sell excess production through suppliers, power purchase agreements and peer-to-peer trading (Directive (EU) 2018/2001, Article 21(2)(a)). Self-consumers have the right to remuneration that reflects the market value of the electricity they feed into the grid (Article 21(2)(d)).
Frequently asked questions
- Can I sell the surplus from my solar panels in Slovakia?
- Yes. A small or local source may deliver unused electricity to the distribution system, within the maximum reserved capacity (Act 309/2009, Sections 4a(13) and 4b(12)). You sell it under a contract, for example with a supplier.
- Is there a state purchase price for PV surplus?
- No. The purchase price in Section 3 of Act 309/2009 applies to the sources listed in Section 3(3), and solar is not among them. The price you get depends on your contract.
- Do I need a licence to sell surplus electricity?
- Not for a system of up to 11 kW without doplatok support (Act 251/2012, Section 4(4)). An active customer may also generate up to 1 MW and supply electricity without it counting as energy business (Section 4(5)).
- What size is a small source in Slovakia?
- A small source has a total installed power of up to 10.8 kW (Act 309/2009, Section 2(1)(l)). Its power must also stay within what the 16 A fuse on one phase secures to get the free connection rights (Section 4a(2)(a)).
- What happens if I export more than my reserved capacity?
- The DSO may disconnect a local source that exceeds the limit in two consecutive quarter-hours (Section 4b(15)). The DSO must announce the reason at least 5 working days before (Section 4b(16)).
- How is surplus feed-in different from net metering?
- Surplus feed-in delivers the unused electricity to the grid under a sales contract. Net metering would net import against export on one meter. Slovak acts do not contain such a scheme.
Sources
- Zákon č. 309/2009 Z. z. o podpore obnoviteľných zdrojov energie a vysoko účinnej kombinovanej výroby a o zmene a doplnení niektorých zákonov · Slov-Lex, consolidated version in force from 1 September 2026 · § 2 ods. 1 písm. l) a o), § 3 ods. 1 až 5, § 4 ods. 14, § 4a, § 4b
- Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Slov-Lex, consolidated version in force from 1 July 2026 (the version from 1 January 2027 keeps the cited wording) · § 2 písm. b) bod 19 a 20, § 4 ods. 4 až 6, § 34 ods. 2 písm. ac) a ad), § 35 ods. 4, § 35b
- Directive (EU) 2019/944 of the European Parliament and of the Council of 5 June 2019 on common rules for the internal market for electricity and amending Directive 2012/27/EU · European Union, Official Journal text (later amendments not checked) · Article 15(1), (2), (4)
- Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources · European Union, Official Journal text (RED II) · Article 2(14), Article 21(1) to (4)