Environmental impact assessment (EIA)

An environmental impact assessment (EIA) is a procedure that evaluates the effects of a planned activity on the environment before it is permitted.

What is an environmental impact assessment?

An environmental impact assessment (EIA) is a procedure that evaluates the effects of a planned activity on the environment before it is permitted.

In Slovakia it is regulated by Act 24/2006 on environmental impact assessment. For a planned activity the procedure has five parts (§ 3 písm. d). The proposer (navrhovateľ) prepares an assessment report. The authorities, the municipalities and the public are consulted. The competent authority reviews the report. It then states reasoned conclusions on the significant effects. These conclusions are built into the permits for the activity.

The act defines the environment broadly. It includes people's health, plants and animals, biodiversity, soil, climate, air and water. It also includes landscape (see landscape character), natural sites, material assets and cultural heritage (§ 3 písm. a). A related step is screening (zisťovacie konanie). It checks whether an activity may have a significant adverse effect. Its result is a binding opinion from screening. That opinion says whether a full EIA is needed (§ 3 písm. c).

When is an EIA required?

An EIA is required for every activity listed in Part A of Annex 8 of the act (§ 18 ods. 1 písm. a). Annex 8 gives activity types by chapter, with thresholds. Part B activities go to screening (§ 18 ods. 2 písm. b). They need an EIA only if the binding opinion from screening says so (§ 18 ods. 1 písm. c).

Two more routes exist. An EIA is also required for an unlisted activity. The nature protection authority must expect a significant effect on the network of protected areas (§ 18 ods. 1 písm. g). A proposer may also ask for an EIA for a Part B activity (§ 18 ods. 1 písm. i).

An activity may be below the threshold in Annex 8. The competent authority can still decide that it must be assessed. It decides on an initiative (podnet, § 19 ods. 1). Anyone may file a reasoned written initiative (§ 19 ods. 2).

Does a family house or a housing development need an EIA?

A single family house is not an activity type named in the chapter of Annex 8 that this page read. That chapter is chapter 13, infrastructure. Its item 1, municipal development projects, is a Part B item. It sets these screening thresholds:

  • Preparing land for later construction from 10 000 m² of total land take.
  • Buildings or sets of buildings not listed in other items. The threshold is 10 000 m² of gross floor area, above and below ground, inside the built-up area. Outside the built-up area it is 1 000 m².

The same chapter lists parking areas from 200 parking spaces for motor vehicles (item 2). It also lists sports or recreation centres, including hotel complexes and permanent campsites (item 8). Item 2 is in Part B. Item 8 is in Part A in protected areas. Elsewhere it is in Part B from 10 000 m² of land take inside the built-up area or 5 000 m² outside it. Compare your project with these figures and with the rest of Annex 8, which has other chapters for farms, mines and roads. A developer should ask the district office early if the project is near a threshold.

Part B means screening, not an automatic EIA. If the project is in or near a protected area, see environmental binding opinion.

What are the steps of the EIA procedure?

  1. Screening, where it applies. The proposer delivers a plan of the activity (zámer, Annex 9). The authority forwards it within 20 days. The affected authorities, the permitting authority and the municipality send opinions within 21 days. After an oral hearing the authority issues the binding opinion from screening. It has 15 days from the hearing and at most 60 days from delivery. In especially complex cases it may extend the limit to 90 days (§ 29 ods. 4, 5, 12).
  2. Information on the activity. Before the permitting procedure starts, the proposer delivers an information document with a zero variant and at least one variant of the activity. A linear building needs at least two variants (§ 22 ods. 1, 2).
  3. Scope of assessment. The authority sets the scope within 15 days of the oral hearing and at the latest within 60 days of delivery. The limit may extend to 90 days (§ 23 ods. 4). The scope is valid for three years. The authority may extend it by two years, repeatedly, up to seven years in total (§ 23 ods. 6).
  4. Assessment report. The proposer delivers the report. The authority checks it for completeness within 30 days (§ 31 ods. 5). Within 40 days of delivery it announces the start of the procedure and publishes the report (§ 33 ods. 1).
  5. Opinions. Authorities and the municipality send opinions within 30 days of delivery of the report. The public may send an opinion within 30 days of publication (§ 35 ods. 1, 2).
  6. Expert opinion. A person determined by the authority writes it (§ 36 ods. 1, 2).
  7. Final opinion. The authority issues the final opinion (záverečné stanovisko) within 60 days of the expert opinion. The last date is six months from delivery of the report (§ 37 ods. 2). It is valid for three years unless the authority sets otherwise. Extension by two years at a time is possible up to seven years in total (§ 37 ods. 8).

Who runs the procedure and who pays?

The competent authority depends on the case. It is the Ministry of Environment, the district office in the regional seat, or the district office (§ 3 písm. l, § 54 to 56). The proposer pays the cost of the assessment. This includes the public hearing and the expert opinion. Each state authority, municipality and member of the public pays its own cost of taking part (§ 59 ods. 1, 3).

The information on the activity needs an author with a second-degree university education in a field that matches the activity (§ 22 ods. 6).

How does the EIA connect to the building procedure?

The permitting body must not decide without the final opinion or the binding opinion from screening. This applies if the activity is subject to the act (24/2006 § 38 ods. 3). If screening rules out an EIA, the proposer may file for the permit once that opinion is final (§ 29 ods. 16). The final opinion is binding for the later permitting procedure (§ 37 ods. 1).

Under Act 25/2025 the building office checks that the building work conforms to the decision of the EIA body (§ 57 ods. 2 písm. b). It rejects an application that conflicts with it (§ 59 ods. 1 písm. a). Where an EIA preceded the procedure, the decision on the building intent is announced by public notice (§ 61 ods. 3). During works, the person who carries out the activity must comply with the final opinion and its conditions. An assessed activity also needs a post-project analysis (24/2006 § 39 ods. 1, 2).

How can the public take part?

The public may deliver a reasoned written opinion on the assessment report within 30 days of its publication (§ 35 ods. 2). The concerned public becomes a party if it files that opinion. It is then a party in the EIA and in the later permitting procedure (§ 24 ods. 2, 3). A civic initiative is at least three natural persons older than 18 who sign a joint opinion (§ 24 ods. 5). Against the binding opinion from screening, the proposer, the concerned public and the municipality may appeal within 15 days (§ 30 ods. 1, 2). See party to proceedings.

How is an EIA different from an environmental binding opinion?

An EIA tests the activity as a whole under its own act and ends in a final opinion. An environmental binding opinion comes from one authority, such as nature protection or water, in one building procedure. The two meet. The nature protection authority issues a binding opinion on the screening decision and on the final opinion (543/2002 § 9 ods. 1 písm. w). The EIA body is an affected authority in the later permitting if it issued a final opinion (24/2006 § 38 ods. 4). See binding opinion.

Frequently asked questions

What is an EIA?
An EIA (posudzovanie vplyvov na životné prostredie) is a procedure under Act 24/2006. It evaluates a planned activity before permitting. It ends in a final opinion that binds the later permitting (§ 37 ods. 1).
When is an EIA required?
For every activity in Part A of Annex 8 of Act 24/2006 (§ 18 ods. 1 písm. a). Part B activities need an EIA only if screening says so. An activity below a threshold can be assessed after an initiative (§ 19).
Does a family house need an EIA?
A single house is not an activity type in chapter 13 of Annex 8, the chapter read for this page. Its municipal development item has a screening threshold of 1 000 m² of gross floor area outside the built-up area and 10 000 m² inside. The rest of Annex 8 has other chapters.
What is screening?
Screening (zisťovacie konanie) checks whether an activity may have a significant adverse effect on the environment. It ends in a binding opinion that says whether an EIA is needed (§ 3 písm. c, § 29 ods. 11).
How long does the procedure take?
The law sets limits per step. The screening opinion is due within 60 days of delivery, or 90 in especially complex cases (§ 29 ods. 12). The final opinion is due at the latest six months after delivery of the report (§ 37 ods. 2).
Who pays for an EIA?
The proposer pays the cost of the assessment, including the public hearing and the expert opinion. Other bodies and the public pay their own cost of taking part (§ 59 ods. 1, 3).

Sources

  1. Zákon č. 24/2006 Z. z. o posudzovaní vplyvov na životné prostredie a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 3 písm. a, c, d, l, § 18, § 19, § 22, § 23, § 24, § 29, § 30, § 31 ods. 5, § 33, § 35, § 36, § 37, § 38, § 39, § 54 až 56, § 59, Príloha č. 8 kap. 13 položky 1, 2 a 8, Príloha č. 9
  2. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 57 ods. 2 písm. b, § 59 ods. 1 písm. a, § 61 ods. 3
  3. Zákon č. 543/2002 Z. z. o ochrane prírody a krajiny · Národná rada Slovenskej republiky, via Slov-Lex · § 9 ods. 1 písm. w