Demolition of a structure

Demolition of a structure (odstránenie stavby) is covered by the building intent decision since 1 April 2025, and the former demolition permit is gone.

What does demolishing a structure require now?

Demolition of a structure (odstránenie stavby) is covered by the building intent decision since 1 April 2025, and the former demolition permit is gone. Removal means works that take a structure down in whole or in part, including the handling of the waste (§ 2 ods. 11). The old Building Act, zákon č. 50/1976 Zb., had a separate demolition permit (povolenie na odstránenie stavby). People still search for that name. The act in force since 1 April 2025 replaced it with a decision on the building intent (rozhodnutie o stavebnom zámere). A verified project follows. A building office decides. A notification replaces both steps in some cases (§ 18 ods. 2, § 25). Zákon č. 25/2025 Z. z. still uses the old name in § 84 ods. 12, for nuclear installations.

When is a decision required to demolish a building?

Removal (odstraňovanie stavby) means works that take a structure down in whole or in part. It includes handling the waste (§ 2 ods. 11). Section 18 ods. 2 requires a decision for every removal, unless the act names an exception.

CaseWhat the act requiresSource
A house or another structure that needs a decisionA decision on the building intent that covers the removal, then a verified project§ 9 ods. 2, § 18 ods. 2, § 25
A structure built on a notification, an information structure or an assembled productThe owner notifies the building office of the deadline for the removal§ 63 ods. 11
Works done without a verified projectThe inspectorate orders the removal in a separate order§ 28 ods. 1, § 78
Proceedings that the office began by 31 March 2025The old rules apply§ 84 ods. 4

For a small structure, read § 18 ods. 3 and 5. Section 18 ods. 3 písm. c names the removal of a numbered structure among the cases that need a notification. The act does not require kolaudácia after a demolition. Section 66 ods. 1 lists new structures, changes of completed structures and terrain works.

How does the procedure work?

The procedure is the one for any building intent. The building intent contains the removal of the structure (§ 9 ods. 2). The owner files the application electronically on the prescribed form, with documentation from an authorised person (§ 50 ods. 1 and 2).

  1. A designer prepares the building intent and the demolition project. The office rejects an intent that a designer did not prepare (§ 59 ods. 1 písm. b).
  2. The owner asks the spatial planning authority and the affected authorities for binding opinions. They have 30 days, or 60 days for a complex structure (§ 20 ods. 1 and § 21 ods. 9).
  3. The municipal building office decides within 30 days. It has 60 days with a hearing or inspection and 90 days in the cases of § 58 ods. 2.
  4. The office verifies the project. It can do this in the same step when the owner files positive compliance declarations (§ 57 ods. 3 and § 65).

The decision lasts 2 years from the day it becomes final. The office may set a longer period (§ 61 ods. 1). Compare the building permit and the decision on the building intent.

How much does a demolition decision cost?

The state fee for removing a structure is 25% of the fee for the decision on that type of structure (položka 59 písm. a bod 14 of zákon 145/1995). Verifying a demolition project costs 10% of that same rate (písm. b bod 3). For a single-flat or two-flat building the rate is 300 euro, so the fees calculate to 75 euro and 30 euro. This calculation is ours, the schedule prints only the percentages. The schedule is the version from 01.11.2026 to 30.11.2026.

Do I need other approvals before demolition?

Sometimes. If the structure is in a heritage zone or its protection zone, the regional monuments office (krajský pamiatkový úrad) takes part in the proceedings. It acts as an affected authority (§ 32 ods. 12 of zákon 49/2002). The building office asks for its opinion even when the owner only files a notification. Section 18 ods. 3 písm. f and g list works on a monument and in a heritage zone among the cases that need a notification.

What waste rules apply to a demolition?

When a firm demolishes for a private owner, the firm is the waste producer (§ 77 ods. 2 of zákon 79/2015). The producer has these duties (§ 77 ods. 3).

  • Demolish selectively, by the method that a decree sets, so that materials can be reused and recycled.
  • Recover and recycle at least 70% by weight of the construction and demolition waste on structures with a built-up area over 300 m2.
  • Sign a contract for the physical handling of the waste before the waste arises.
  • Notify the waste authority in writing at least three working days before the demolition. The notice gives the method, the types and the expected quantity of waste.
  • Report the result of the selective demolition to the same authority within 90 days after the works end.

See construction and demolition waste.

What happens if I demolish without a decision?

Removing a structure without a verified project is an offence. Amendment 243/2026 changes § 79 and § 80 from 1 January 2027, so read the new text then.

WhoFineSource
A natural person30 to 30,000 euro§ 79 ods. 4 písm. c and ods. 6 písm. d
A business or a legal person1,000 to 25,000 euro§ 80 ods. 3 písm. c

The reverse case is a structure built without a verified project. Such works count as unauthorised (§ 28 ods. 1). The inspectorate then orders the removal, sets a deadline and may demand a security for the cost (§ 78 ods. 1). The owner pays. If the owner does not remove the structure, the inspectorate does it (§ 78 ods. 2).

Owners of completed buildings without a permit can still ask for a review of fitness for use or for retrospective approval by 31 March 2029. The conditions of the old act must be met (§ 84 ods. 7). See the Building Act.

Frequently asked questions

What does demolishing a structure require now?
Since 1 April 2025 a decision on the building intent covers the removal, then a verified project (§ 18 ods. 2 and § 25 of zákon 25/2025). The separate demolition permit of the old Act 50/1976 Zb. no longer exists.
What permit do I need to demolish a house?
You need a decision on the building intent that covers the removal, then a verified project (§ 9 ods. 2, § 18 ods. 2 and § 25 of zákon 25/2025). A designer prepares the documents. The municipal building office decides.
Do I need a decision to remove a small structure?
Not always. A structure built on a notification needs only a notice of the removal deadline (§ 63 ods. 11 of zákon 25/2025). For other small structures, § 18 ods. 3 and 5 say whether you must file a notification.
How long and how much is a demolition decision?
The office decides within 30, 60 or 90 days (§ 58 of zákon 25/2025). The fee is 25% of the rate for the structure type. Verifying the project costs 10% of that rate (položka 59 of zákon 145/1995, version 01.11.2026).
What happens if you demolish without a decision?
It is an offence. A natural person faces a fine of 30 to 30,000 euro and a business 1,000 to 25,000 euro (§ 79 ods. 4 písm. c, § 80 ods. 3 písm. c of zákon 25/2025, version to 31.12.2026).
What waste rules apply to a demolition?
The person who demolishes must demolish selectively and notify the waste authority at least three working days before. On structures over 300 m2 built-up area at least 70% by weight must be recovered (§ 77 ods. 3 of zákon 79/2015).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2, 9, 18, 20, 21, 25, 28, 50, 57, 58, 59, 61, 63, 65, 66, 78, 79, 80, 84
  2. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59
  3. Zákon č. 79/2015 Z. z. o odpadoch a o zmene a doplnení niektorých zákonov · Slov-Lex · § 77, príloha č. 3 časť VI
  4. Zákon č. 49/2002 Z. z. o ochrane pamiatkového fondu · Slov-Lex · § 32 ods. 12
  5. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex