Demolition project documentation

Demolition project documentation is the project a designer prepares to show how a structure will be removed, and the building office verifies it.

What is demolition project documentation?

Demolition project documentation is the project that shows how a structure will be removed. In Slovak it is often called projekt búracích prác. Act 25/2025 Z. z. (Stavebný zákon) has no document with that name. It speaks of the projekt stavby, which can express the design of "odstránenie stavby" in text and graphics (§ 9 ods. 3).

The act also lets the building intent (stavebný zámer) cover the removal of a structure (§ 9 ods. 2). Removal means construction work that takes down a structure in whole or in part. It includes the handling of construction and demolition waste. Removal of the whole structure means demolition of all structural elements (§ 2 ods. 11).

Which procedure applies to removing a structure?

The default is a decision on the building intent (rozhodnutie o stavebnom zámere). Section 18 ods. 2 requires it for every removal of a structure, unless the act says otherwise. Work may follow only a project that the office verified in that procedure, or a notification (§ 25).

CaseWhat the act requiresSource
A structure that needs a decisionA decision on the building intent, then a verified project§ 18 ods. 2, § 25, § 65
A structure built on a notification, an information structure or an assembled productThe owner tells the building office the deadline for the removal§ 63 ods. 11
An unauthorised information structureA notification of the removal§ 64
An emergency such as a natural disaster or an accidentDemolition work may start without a prior building intent, to prevent danger to people, the environment or serious damage. The person who organises it must tell the building office at once§ 47 ods. 1
A structure built by unauthorised workThe building inspectorate orders the removal in an order§ 78 ods. 1

Section 18 ods. 3 and 5 set exceptions for minor structures and building alterations. Ask the building office which case applies before you plan the work.

Is there still a demolition permit?

No. The old name povolenie na odstránenie stavby belonged to the old building act. The act of 2025 uses it only for nuclear installations in a transitional rule (§ 84 ods. 12). The demolition permit page explains the old name.

Proceedings that began by 31 March 2025 follow the rules in force until that date (§ 84 ods. 4).

Who prepares the project?

An authorised designer (projektant). Project work is a reserved activity (§ 34 ods. 2 písm. a), and only an authorised person may be a designer (§ 35 ods. 4). The designer prepares the project according to the decision on the building intent (§ 35 ods. 6 písm. b).

If the documentation needs several designers who depend on each other, the builder must engage a general designer (§ 30 ods. 2 písm. d). A designer without authorisation for one part must engage a person who has it (§ 35 ods. 2). A structural engineer prepares the structural part, with a checkable structural calculation (§ 35 ods. 8). See structural engineer and structural assessment.

What does the project contain?

The act says the project is a text and graphic expression of the removal (§ 9 ods. 3). Decree 60/2025 Z. z. sets the content of the project in annex 17 (§ 6 ods. 4). If the removal is the subject of the project, the summary data name the structure to remove and its owner (§ 16 písm. e).

The decision on the building intent carries similar data about the removed structure (§ 14 písm. e). The act does not list utility disconnections, hazardous materials or neighbour notices as parts of the project. Treat them as questions for the designer and the office.

How long does the procedure take?

The act sets deadlines for the office, not for the demolition.

StepDeadlineSource
Decision on the building intent without an oral hearing30 days from a complete application§ 58 ods. 1
Decision that needs a hearing or an inspection60 days§ 58 ods. 1
A reserved structure, a linear structure, many parties or an expert opinion90 days§ 58 ods. 2
Verification of the project30 days§ 65 ods. 2
Verification clause stays valid if work starts withintwo years§ 65 ods. 6

The time does not run while the office lacks an expert opinion (§ 58 ods. 2). The time for delivery of the notice of the start does not count (§ 58 ods. 3).

What does the work itself require?

Demolition work is construction work (§ 27 ods. 1), and the rules for the contractor apply to removal (§ 26 ods. 5). The builder must use an authorised contractor, unless the act allows self-build (§ 26 ods. 2).

The decision may set a control inspection before a stage of the removal. The site manager (stavbyvedúci) must tell the office, the builder, the designer and the person in charge of construction supervision the date (§ 43 ods. 1).

What waste duties apply to a demolition?

The waste act, zákon č. 79/2015 Z. z., sets the duties in § 77. They apply to the originator of the waste. For work done for a private person, the originator is the person who does the work (§ 77 ods. 2).

  • The originator must run selective demolition by the method that the implementing rules set (§ 77 ods. 3 písm. b). Selective demolition sets the order of the work so that materials can be separated and sorted (§ 77 ods. 1 písm. b).
  • The originator must have a proven contract for the physical handling of the waste before the waste arises (§ 77 ods. 3 písm. d).
  • The originator must notify the state waste authority in writing at least three working days before the demolition (§ 77 ods. 3 písm. e).
  • The originator must report the result of the selective demolition within 90 days after the work ends (§ 77 ods. 3 písm. f).
  • For structures above 300 m2 of built-up area, the originator must reach the recovery and recycling targets of annex 3 (§ 77 ods. 3 písm. a). Annex 3 part VI sets a minimum of 70 % of the weight of the waste.

The 300 m2 limit applies to the recovery target, not to selective demolition. See construction and demolition waste.

What if a structure was built without a permit?

The inspectorate sets a deadline and conditions in an order. The owner must remove the structure at the owner's own cost (§ 78 ods. 1 and 2). If the owner does not, the inspectorate carries out the order. Some older structures can still get a review of fitness for use under the old rules. The owner must apply by 31 March 2029 (§ 84 ods. 7 písm. a). See review of fitness for occupancy.

What happens to the project after the demolition?

A new building on the cleared plot needs its own decision on the building intent. The building intent can express both the new building and the removal of an existing structure (§ 9 ods. 2).

Frequently asked questions

What is a demolition project?
A demolition project (projekt búracích prác) is the project that shows how a structure will be removed. Act 25/2025 Z. z. calls the document projekt stavby and lets it express the removal of a structure (§ 9 ods. 3).
Do I need a permit to demolish a house in Slovakia?
You need a decision on the building intent, not a separate demolition permit. Section 18 ods. 2 of act 25/2025 Z. z. requires it for every removal unless the act says otherwise. Work follows a verified project (§ 25).
Who prepares a demolition project?
An authorised designer prepares it. Project work is a reserved activity (§ 34 ods. 2 písm. a of act 25/2025 Z. z.), and only an authorised person may be a designer (§ 35 ods. 4).
When is a notification enough to remove a structure?
A notification is enough for a structure built on a notification, an information structure or an assembled product. The owner tells the building office the deadline for the removal (§ 63 ods. 11 of act 25/2025 Z. z.).
What waste duties apply to demolition?
The originator of the waste must run selective demolition and have a contract for the waste. The originator must notify the waste authority three working days before the work and report within 90 days after it (§ 77 ods. 3 of act 79/2015 Z. z.).
Does the 70 % recovery target apply to every demolition?
No. The recovery and recycling target applies to structures above 300 m2 of built-up area (§ 77 ods. 3 písm. a of act 79/2015 Z. z.). Annex 3 part VI sets at least 70 % of the weight of the waste.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 11, § 9, § 18 ods. 2, 3 a 5, § 25, § 26, § 27, § 30, § 34, § 35, § 43, § 47, § 58, § 63 ods. 11, § 64, § 65, § 78, § 84
  2. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby (č. 60/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu Slovenskej republiky, via Slov-Lex · § 6 ods. 4, § 14 písm. e, § 16 písm. e
  3. Zákon č. 79/2015 Z. z. o odpadoch a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 77 ods. 1 až 3, príloha č. 3 časť VI