Utility Room in a Family House

8 min read
Illustration: a compact plant room in a new family house with a white hot water cylinder, a wall-mounted heating manifold with brass valves, a blue cartridge water filter on the incoming pipe, a floor drain grate in a grey tiled floor and a closed grey distribution board on the wall

What has to fit in a utility room?

In a new family house, the utility room is where the services and equipment of the whole house meet. A typical brief lists a heat source or the indoor unit of a heat pump, an indirect hot water cylinder and a buffer tank. It also lists a heat recovery ventilation unit and the water entry with a filter and a softener. Add the house distribution board, a data cabinet and, with solar panels, an inverter and a battery.

Decree No. 532/2002 Coll. sets no floor area for a utility room. It does set requirements for individual pieces of equipment:

EquipmentWhat Decree 532/2002 requiresProvision
Boiler or other fuel applianceSupply of combustion and ventilation air, discharge of flue gas and condensate without risk to health or surroundings§ 41(2)
Ventilation unitExhaust air outlet at least 1.5 m from the outdoor air intake. Where the air carries a lot of water vapour and condensation is a risk, a watertight duct laid to a fall, drained and insulated§ 40(2) and (3)
Water entryMain stop valve before the water meter, accessible, visibly and permanently marked. Cold and hot water pipes thermally insulated§ 35(3) and (5)
ElectricityRoom for the entry of power and telecom cables and for the distribution cabinet. A permanently accessible, visibly marked main switch§ 37(4) and (5)
Equipment that causes noise and vibrationPlaced and installed so that transfer of noise and vibration into the structure is limited§ 20(5)
FloorA floor gully where the floor is wet-cleaned or where a fixture is not connected to the drainage§ 36(5)

The decree does not ask for a drain in every utility room, only where the floor is wet-cleaned or a fixture is not connected. Water does come out of the installations during servicing and after a fault, so a floor drain is worth adding in every case.

Where should the utility room go in the floor plan?

Position matters more than area. Four things are worth checking:

  • Short hot water runs. Bathrooms and a kitchen close to the cylinder shorten the pipes and often make recirculation unnecessary. The background is in the post on hot water in a family house.
  • Short ducts. The heat recovery unit should sit at the external wall through which it takes in and expels air, and also close to the ventilated rooms. Duct design is covered in Heat recovery ventilation in practice.
  • Noise. The utility room does not belong behind a bedroom wall or under a bedroom. The decree requires protection of acoustically protected rooms against noise from the building services (§ 20(2)(d)). It also requires limits on the transfer of noise and vibration from built-in equipment into the structure (§ 20(5)).
  • Access. A service technician should reach the room without walking through the living room, ideally from the hall, the entrance lobby or the garage.

How the utility room fits between the day and night zones is shown in Day and night zones: the logic of the floor plan.

How big should the utility room be?

Big enough for the equipment, the space to operate it and a route to replace it. The method is simple:

  1. List all the equipment, including items that will come later, such as a battery for solar panels.
  2. For each item, take the dimensions and service clearances from the manufacturer's manual.
  3. Lay the equipment out on a scaled plan and leave free space in front of doors, filters and valves.
  4. Check the way out. The largest item, usually the cylinder or the buffer tank, must pass through the door and the corridor years later when it is replaced.

Meter cabinet at the boundary or distribution board in the house?

These are two different cabinets. The electricity meter cabinet holds the meter, and the distribution company approves where it goes. The house distribution board with breakers and residual current devices is part of the internal wiring. It belongs in the house, often in the utility room.

Each distributor has its own rules for the meter cabinet. Two distributors publish their rules. Stredoslovenská distribučná (SSD) has rules in force from 1 February 2026. Západoslovenská distribučná (ZSD) has metering conditions version 4 of 1 January 2025. Both require a place that their staff can reach even when the customer is absent (SSD Art. 15(1), ZSD point 3.7). For a detached family house directly next to a public road, SSD puts the cabinet on the outside of the house facing the road. If the house is not next to the road, it goes on the plot boundary by the road (Art. 15.1(5) and (6)). ZSD puts it on the plot boundary with the public space, in the fence or in front of it. It goes on the outside wall of the house only when the property is not fenced (point 3.7). The cabinet door must not take an individual lock (point 3.4.1). Under SSD, the unmetered supply must not run through the inside of the building (Art. 15.1(1)).

AspectMeter cabinetHouse distribution board
WherePublicly accessible place. For a detached house, SSD: the facade facing the road or the plot boundary, ZSD: the plot boundary, or the house wall if the property is not fenced (SSD Art. 15.1(5) and (6), ZSD point 3.7)In the house, location chosen by the electrical designer
Who decidesThe distributor approves the location in a new building (SSD Art. 15.1(2))The designer. The building must allow the distribution cabinet to be placed (532/2002 § 37(4))
Height and spaceCentre of the meter display at 1,000 to 1,700 mm, free space in front at least 800 mm deep and wide (SSD Art. 15(3) and (4), ZSD point 3.7)Per design
CostsThe distributor pays for fitting the meter, the customer for the adjustments to place it (Act 251/2012 § 40(5), SSD Art. 5.3(5))The builder
Solar and batteryA mandatory back-voltage disconnecting switch (SSD Art. 11(4))Per design

How are surge protection and bonding handled?

The electrical designer plans surge protection and bonding. The architect has to give the designer space and routes. The ÚNMS SR standards catalogue lists these standards for the topic:

  • STN 33 2000-4-443 specifies protection of electrical installations against transient overvoltages of atmospheric origin transmitted by the supply network and against switching overvoltages. It does not cover protection against a direct lightning strike to the building or near it. This is the field of the surge protection device.
  • STN 33 2000-5-54 covers earthing arrangements and protective conductors, including protective bonding conductors.
  • STN EN 62305-4 covers protection of electrical and electronic systems within structures against the lightning electromagnetic impulse. It gives information for design, installation, inspection and testing. The catalogue lists its withdrawal date as 31 October 2027 and the replacing standard as STN EN IEC 62305-4:2025-02.

The decree requires lightning protection where lightning could, for example, endanger life or health or cause an explosion. It also requires it where the building stands on a hilltop or rises above its surroundings (§ 38). The designer judges whether the house needs it. SSD may ask the system user for a valid report on the professional inspection and testing of the electrical installation (Art. 5.2(3)).

SSD puts the customer's surge protection preferably in the house distribution board. It belongs in the meter cabinet only with the cabinet maker's approval. It belongs in the unmetered part only when the lightning protection concept needs it and the distributor agrees (Art. 13(1) to (3)).

Water meter in a meter pit or in the house?

Under the act on public water supply, the meter on the water connection is usually in a water meter pit. The pit must meet the technical requirements of the owner or operator of the water supply. It must be protected against ingress of water, gases and dirt, and be drainable, ventilated and safely accessible. The meter is an accessory of the public water supply (Act 442/2002 § 4(10)). Your water company therefore sets the technical requirements. Two of them publish the following:

RequirementTAVOS (Trnava water company)VVS (East Slovak water company)
PositionAt most 1.0 m behind the plot boundary or at most 10 m from the connection to the main, or per the approved designThe leaflet does not state a position
Concrete pit for one DN25 or DN32 meter assemblyInternal dimensions 900 × 1,200 × 1,800 mmThe leaflet does not describe one
Plastic pitInternal size DN1200, internal height outside the entry at least 1,600 mmInternal width 1,000 mm, internal height 1,200 mm, total height 1,600 mm
EntryOpening at least 600 × 600 mm with a cast-iron cover and a ladderEntry riser 600 mm in diameter, plastic lid and step irons

Under the TAVOS rules, the owner of the connected property builds the water meter shaft at their own cost. The owner must protect it against freezing and mechanical damage. In justified cases and with the operator's consent, the pit can be omitted.

In the house, the main stop valve of the internal water supply goes before the meter (532/2002 § 35(3)). The internal water supply must be protected against back-siphonage of contaminated water (§ 35(6)). The filter usually follows and, depending on water hardness, a softener.

How should risers run through a service shaft?

In a two-storey house, water, drainage, ventilation and electrical runs go up from the utility room. A vertical service shaft gathers them in one place. The decree has these rules for it:

  • The cladding and insulation of a service shaft must have the required fire performance (§ 34(5) and (7)).
  • No service line may be placed in a ventilation flue, and a ventilation duct must not be connected to a chimney (§ 34(5)).
  • The vent pipe of the internal drainage must not connect to a service shaft or a chimney. It must run above the roof (§ 36(4)).

Run the shaft from the utility room straight to the bathrooms above it. At valves and manifolds it needs access panels, otherwise the tiles come off at the first fault.

Gas and batteries: what to consider in the design?

If gas heats the house, the distributor builds the gas installation up to the boundary of the customer's plot or building. This includes the main gas valve (Act 251/2012 § 72(1)). The main valve must be in a permanently accessible and ventilated place. It must not be, for example, in a boiler room, bathroom, laundry, garage or shaft (532/2002 § 39(4)).

A home battery for solar panels fits well in the utility room, where the distribution board and the inverter are. Decree 532/2002 does not state requirements for its position, clearances, ventilation or ambient temperature. The manufacturer's manual sets them and, for larger systems, the fire safety designer. It is sensible to keep the battery out of bedrooms and off escape routes.

Which utility room mistakes are worth avoiding?

  • A room designed as leftover space. The equipment fits, but the technician cannot reach the filter or the valve.
  • No floor drain. Water from servicing or a fault runs across the floor into the corridor.
  • A door narrower than the largest piece of equipment. Replacing the cylinder becomes building work.
  • A meter cabinet behind the gate, where the distributor's staff cannot reach it without you.
  • No spare space. A battery, an electric car charger or a softener arrive later and have nowhere to go.

Frequently asked questions

Can the utility room be in the garage?
Under Decree No. 532/2002 Coll., the main gas valve must not be in a garage (§ 39(4)). For other equipment, the design decides. A garage also has its own fire safety requirements, which the fire safety designer assesses.
Who pays for the adjustments to place the electricity meter?
The distribution system operator fits the meter at its own cost. The final customer makes the adjustments needed to place the meter at its own cost (Act No. 251/2012 Coll. § 40(5)). SSD adds that the customer pays for the adjustments and placement of the meter cabinet. The cabinet is part of the customer's supply point (Art. 5.3(5)).
Can the water meter be in the house instead of a meter pit?
Act No. 442/2002 Coll. says the meter is usually in a water meter pit (§ 4(10)), so not always. The TAVOS rules allow the pit to be omitted in justified cases and with the operator's consent. Your water company decides, so ask it before the connection is designed.
Where does a water softener go?
In practice, in the utility room after the main stop valve, the meter and the filter. A water softener needs space for operation and refilling. The manufacturer's manual sets its connection to drainage and electricity. If you plan to add one later, leave space for it by the drain now.
Does solar with a battery require changes to the meter cabinet?
With SSD, yes. A back-voltage disconnecting switch is mandatory in every meter cabinet of a supply point to which a new generating or storage device is connected. It must be near the meter or the main breaker, outside the row of circuit breakers, and labelled “MAIN SWITCH AFTER THE METER” (Art. 11(3) and (4)). More on batteries is in the entry home battery storage.
Where should the main electrical switch be?
Every building must have a permanently accessible and visibly marked main switch for electricity (Decree No. 532/2002 Coll. § 37(5)). The electrical designer proposes the exact place.
Does Decree 532/2002 still apply under the new building act?
Yes, for a transition period. Act No. 25/2025 Coll. keeps it in force until new implementing regulations take effect, at the latest until 31 March 2027 (§ 84(23)(b)). For a project that will be finished after that date, it pays to watch what replaces it.

Sources

  1. Vyhláška Ministerstva životného prostredia Slovenskej republiky č. 532/2002 Z. z., ktorou sa ustanovujú podrobnosti o všeobecných technických požiadavkách na výstavbu a o všeobecných technických požiadavkách na stavby užívané osobami s obmedzenou schopnosťou pohybu a orientácie · Slov-Lex, Ministerstvo spravodlivosti SR · § 20 ods. 2 písm. d) a ods. 5, § 34 ods. 5 a 7, § 35 ods. 3, 5 a 6, § 36 ods. 4 a 5, § 37 ods. 4 a 5, § 38, § 39 ods. 4, § 40 ods. 2 a 3, § 41 ods. 2
  2. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov · Slov-Lex, Ministerstvo spravodlivosti SR · § 84 ods. 23 písm. b)
  3. Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách · Slov-Lex, Ministerstvo spravodlivosti SR · § 4 ods. 10
  4. Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Slov-Lex, Ministerstvo spravodlivosti SR · § 40 ods. 5, § 72 ods. 1
  5. Zásady a podmienky montáže a prevádzkovania merania elektriny, účinnosť od 1. 2. 2026 (Príloha č. 2) · Stredoslovenská distribučná, a.s. · čl. 5.2 ods. 3, čl. 5.3 ods. 4 a 5, čl. 11 ods. 3 a 4, čl. 13 ods. 1 až 3, čl. 15 ods. 1, 3 a 4, čl. 15.1 ods. 1, 2, 5 a 6, čl. 21 ods. 11
  6. Podmienky merania elektriny (Pravidlá pre prevádzkovanie a montáž merania elektrickej energie), verzia 4 · Západoslovenská distribučná, a.s. (ZSD) · 3.4.1, 3.7
  7. Interná smernica IS-P10-1_1: Podmienky pripojenia na verejný vodovod a verejnú kanalizáciu · Trnavská vodárenská spoločnosť, a. s. (dokument zverejnený obcou Podolie) · Pojmy písm. o), kap. 2 písm. m), kap. 3.1 písm. a) a b)
  8. Plastová vodomerná šachta (leták, 2024) · Východoslovenská vodárenská spoločnosť, a.s. · Whole leaflet
  9. STN 33 2000-5-54 Elektrické inštalácie nízkeho napätia. Časť 5-54: Výber a stavba elektrických zariadení. Uzemňovacie sústavy a ochranné vodiče · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR · Catalogue entry: title and Predmet normy
  10. STN 33 2000-4-443 Elektrické inštalácie nízkeho napätia. Časť 4-44: Zaistenie bezpečnosti. Ochrana pred rušivými napätiami a elektromagnetickým rušením. Oddiel 443: Ochrana pred prechodnými prepätiami atmosférického pôvodu alebo pred spínacími prepätiami · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR · Catalogue entry: title and Predmet normy
  11. STN EN 62305-4 Ochrana pred bleskom. Časť 4: Elektrické a elektronické systémy v stavbách · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR · Catalogue entry: title, withdrawal date, replacing standard, Predmet normy

Topic

  • Design and layout