Electricity meter cabinet

An electricity meter cabinet is the enclosure that holds the meter at the metering point, placed where distributor staff can reach it.

What is an electricity meter cabinet?

An electricity meter cabinet (elektromerový rozvádzač) is the enclosure that holds the electricity meter at the metering point. The distributors' rules abbreviate it as RE or ER. It also holds the accessories that belong to the metering. The ZSD and VSD rules allow only accessories used exclusively for metering, remote communication and data blocking control. The SSD rules list the permitted elements one by one.

The cabinet belongs to the customer, who must keep it in the condition that the technical requirements demand (ZSD and VSD, section 3.4). The meters and the communication units of the billing metering belong to the distributor (ZSD and VSD, section 3.8).

Where does the cabinet go?

For a family house the three distributors give three different rules. ZSD and VSD put the cabinet on the plot boundary with the public space, in the fence or in front of it. SSD depends on whether the house adjoins the public road. Each text applies in the distribution area of its own distributor.

SituationDistributor and clauseWhat the text says
Family house, holiday house or similarZSD and VSD, section 3.7Cabinet on the plot boundary with the public space, in the fence or in front of it
Same, with no fence now and none plannedZSD and VSD, section 3.7Cabinet may stand on the outer side of the building
Detached house adjoining a public roadSSD, section 15.1(5)Cabinet on the outer face of the building that faces the road
Detached house not adjoining a public roadSSD, section 15.1(6)Cabinet on the plot boundary that adjoins the public road
Centre of the meter dialsZSD and VSD, section 3.71 000 to 1 700 mm above fixed ground after all building work, cabinet upright
Cabinet in a fence pier or a shared cabinetZSD and VSD, section 3.7700 to 1 700 mm above the floor
Centre of the dial or displaySSD, section 15(3)1 000 to 1 700 mm, with seal covers at least 600 mm above the finished surface in front
Free space in frontZSD and VSD section 3.7, SSD section 15(4)At least 800 mm, so that the door opens fully. SSD gives 800 mm in depth and width

SSD also states that the cabinet must not stand on a stair flight (section 15(4)). The free surface in front must be level and fixed. Other boundary services, such as a water meter shaft, raise the same access question.

How far can the cabinet sit from the connection point?

The SSD rules set distance limits. The general principle is to keep the unmetered supply as short as possible. It must run along the outside of the building, not through the inside (section 15.1(1)). The other limits are in the table. The ZSD and VSD texts read for this page give no comparable figures.

Distance ruleLimitSource
From a transformer station or SSD support pointAt least 2 mSSD, section 15.1(3)
From the connection cabinet, cable distributionAt least 1 mSSD, section 15.1(3)
Supply cable length, direct meteringAt most 50 mSSD, section 15.1(4)
Supply cable cross-section, direct meteringAt most 35 mm2SSD, section 15.1(4)

Near a transformer station or support point, the cabinet must also respect existing energy equipment and must not damage the earthing (section 15.1(3)).

What may go inside the cabinet?

Only metering equipment and its accessories. For a new direct-metering cabinet, ZSD names the meter, the main breaker, the reverse-voltage disconnecting breaker and the earth-neutral (PEN) terminal. An isolating module is added if the customer wants direct data from the meter (section 3.4.2.1).

The SSD rules list the permitted elements for the metering part (section 14.1(1)):

  • the main breaker before the meter and the meter
  • the reverse-voltage disconnecting element
  • a control element and a communication device
  • an antenna, a PEN terminal or busbar, an isolating member for pulse output and a relay for switching appliances

SSD also requires metering points to be in the TN-C system. A change to TN-S is allowed only after the metering part, in the unsealed part of the cabinet (section 14(1)).

Because the cabinet holds only metering equipment, the circuits of the house belong in a separate enclosure, the distribution board. This follows from the content limits above.

What does the cabinet itself have to be like?

ZSD and VSD recommend a plastic cabinet for new and rebuilt metering points (section 3.4.1). A new metal cabinet needs one side made of plastic, or a grommet with an 8 mm opening for the communication antenna. The cabinet needs a manufacturer's declaration of conformity and a CSK or CE mark.

The ZSD text adds rules for the door. The lock takes a 6 x 6 mm mandrel key or a similar mechanical lock used in the power sector. The door must not take an individual lock, and it must not have a reading window. A single-line diagram of the connection must be inside the cabinet.

Who may reach the meter, and who approves the place?

All three texts put the meter in a publicly accessible place. Distributor staff must reach it when the customer is away (ZSD and VSD section 3.7, SSD section 15(1)). ZSD and VSD allow a departure only in justified cases. They name a statement from a heritage office as the usual proof.

For new and rebuilt buildings, SSD makes the placement subject to approval by the distribution system operator (PDS in its text, section 15.1(2)). ZSD and VSD make the connection of a new or rebuilt metering point subject to approval by the metering manager. If the customer ignores the conditions, the distributor need not install the meter or start the supply (section 3.8 of ZSD and VSD).

Can the surge protection go in the cabinet?

Only in limited cases. SSD prefers the customer's surge protection device in the measured part, after the meter. In the cabinet, it needs a cabinet that the manufacturer approved for it (SSD section 13(2)). ZSD and VSD allow surge protection before the meter in residential buildings with several floors and flats, after approval by the metering manager.

Where do the rules come from, and which version applies?

The duty rests on the energy act, zákon 251/2012 Z. z. o energetike. Under § 19 ods. 1 and 2, the distribution system operator sets technical conditions for access and connection. Under § 19 ods. 4, those conditions are binding for electricity market participants. The distributors publish their own versions. Whether a given metering document is such a technical condition was not checked.

The versions read for this page are:

  • ZSD, Podmienky merania elektriny, version 4, effective 1 January 2025. ZSD still publishes an older edition dated 28 May 2018 on its site, with different section numbers.
  • VSD, Podmienky merania elektriny, dated 1 October 2024.
  • SSD, Zásady a podmienky montáže a prevádzkovania merania elektriny. The file is titled as valid from 1 June 2026, but its closing clause gives 1 February 2026. Ask SSD which date applies.

Check the distributor's current text before design.

Frequently asked questions

Is an electricity meter cabinet the same as a distribution board?
No. The cabinet holds the meter and metering accessories, and the distributor sets its rules. The distribution board feeds the circuits of the house and sits in a separate enclosure.
Can the meter cabinet go inside a detached house?
ZSD and VSD put it on the plot boundary. They allow the outer side of the building only if the plot has no fence and will have none. SSD puts it on the outer face of the building or on the boundary.
Who approves where the cabinet goes?
For new and rebuilt buildings, SSD makes the placement subject to approval by the distributor. ZSD and VSD make the connection of the metering point subject to approval by the metering manager.
How close can the cabinet be to a transformer station?
The SSD rules require at least 2 m from a transformer station or an SSD support point. For direct metering, the supply cable may be at most 50 m long and no thicker than 35 mm2.
Which distributor's rules apply to my plot?
The rules of the distributor of your distribution area apply. This page read the texts of ZSD, SSD and VSD. Check the current text of your distributor before design.
How high does the meter go?
ZSD and VSD put the centre of the meter dials 1 000 to 1 700 mm above fixed ground. In a fence pier or shared cabinet the range is 700 to 1 700 mm above the floor.

Sources

  1. Zákon č. 251/2012 Z. z. o energetike · Národná rada SR, Slov-Lex · § 19 ods. 1, 2 and 4
  2. Podmienky merania elektriny (Postup č. D6.ELM.01, verzia 4, účinnosť 1. 1. 2025), part of Pravidlá pre prevádzkovanie a montáž merania elektrickej energie · Západoslovenská distribučná, a.s. (ZSD) · 2, 3.1, 3.4, 3.4.1, 3.4.2.1, 3.5, 3.7, 3.8
  3. Podmienky merania elektriny, Východoslovenská distribučná, a.s., Košice, 1.10.2024 · Východoslovenská distribučná, a.s. (VSD) · 2, 3.4, 3.4.1, 3.5, 3.7, 3.8
  4. Zásady a podmienky montáže a prevádzkovania merania elektriny, Príloha č. 2 · Stredoslovenská distribučná, a.s. (SSD) · 2, 13, 14, 14.1, 15, 15.1