Surge protection device
A surge protection device (SPD) is a device that protects AC low-voltage circuits and equipment against lightning and other transient overvoltages.
What is a surge protection device?
A surge protection device (SPD) is a device that protects AC low-voltage circuits and equipment against lightning and other transient overvoltages. The Slovak term is prepäťová ochrana. The IEC writes "surge protective device".
The IEC abstract of IEC 61643-11:2025 describes devices for surge protection against the indirect and direct effects of lightning. They connect to AC power circuits and equipment rated up to 1 000 V RMS. The preferred frequencies are 50 and 60 Hz.
Which Slovak standards apply to surge protection devices?
The standards office (ÚNMS) lists all four standards in the table as valid. The Slovak edition of Part 11 adopts EN IEC 61643-11:2025 and IEC 61643-11:2025 without change.
| Standard | Released | Official Journal | Replaces |
|---|---|---|---|
| STN EN IEC 61643-11 (SPDs for AC low-voltage circuits) | 1 April 2026 | 03/26 | STN EN 61643-11:2013-08 |
| STN EN IEC 61643-11/Zmena A11 (change sheet) | 1 April 2026 | 03/26 | Not listed |
| STN EN IEC 62305-1 (lightning protection, general principles) | 1 February 2025 | 01/25 | STN EN 62305-1:2012-04 |
| STN EN IEC 62305-4 (lightning protection, electrical and electronic systems in structures) | 1 July 2026 | 06/26 | STN EN IEC 62305-4:2025-02 |
The catalogue note for A11 says the April 2026 standard may be used without this change until 30 November 2028. The project documentation should name the exact version and amendment that the engineer applied.
The catalogue entry for STN EN IEC 62305-1 says the English text is available and a Slovak translation is in preparation. Part 4 covers the design, installation, inspection, maintenance and testing of surge protection measures for electrical and electronic systems in structures. The catalogue note says the 2013 edition of Part 4 may be used in parallel until 31 October 2027. Parts 2 and 3 were not read here, except that Part 3 has a 2026 edition, as the equipotential bonding page notes.
What changed in the 2025 edition of IEC 61643-11?
IEC published edition 2.0 on 18 June 2025, and the IEC page carries a corrected version of October 2026. The abstract lists these technical changes:
- The specific requirements for AC applications are now in this document.
- The voltage protection level is also measured on combined modes of protection.
- There is an extra duty test for T1 and T2 SPDs with follow current.
- The short-circuit current test requirements are modified, to cover current internal disconnector technologies.
- The dielectric test requirements for the main circuits are improved.
- There are extra clearance requirements for electrically separated circuits.
The change list names T1 and T2 SPDs. These are the standard's own names for two types.
How do Type 1, Type 2 and Type 3 differ?
The sources read for this page name only some of the types. The IEC change list names T1 and T2. The SSD rules name the combined type T1 + T2, which they also write as B+C. No source read for this page defines Type 3.
Designers choose a type by the location and the expected duty. This page did not read the clauses that assign types to places in the installation. The engineer applies those clauses and states the choice in the project.
Where do the distributors allow a surge protection device?
The distributors' metering rules deal with the place of the device. The texts say:
| Distributor and clause | What the text says |
|---|---|
| SSD, section 13(2) | The customer's SPD goes preferably in the measured part of the installation, which is the part after the meter |
| SSD, section 13(1) | The customer discusses any placement in the unmetered part with the distributor before the electrical work starts, in the design stage |
| SSD, section 13(3) | An SPD in the unmetered part is possible only if the overall lightning protection concept needs it |
| SSD, section 13(4) | In the unmetered part only a T1 + T2 (B+C) device with fuse protection, in the first entry board, with a sealable cover |
| SSD, sections 13(5) and 13(6) | Replaceable modules cannot be pulled out and changed without breaking the seal. A single-line diagram of the unmetered SPD stays in the cabinet |
| ZSD and VSD, section 3.5 | After approval by the metering manager, an SPD in a residential building with several floors and flats may connect before the meter, for protection against the effects of lightning |
In the electricity meter cabinet, SSD allows an SPD only in a cabinet that the manufacturer approved for it. SSD calls the first board after the entry the prvý vstupný rozvádzač. It does not use the name distribution board.
How does an SPD relate to lightning protection?
An SPD is not a lightning conductor. STN EN IEC 62305-1 covers the protection of structures against lightning, including their installations, contents and people. It excludes, among others, railway systems, vehicles and power lines outside structures.
The SSD rule in section 13(3) links the two. An SPD in the unmetered part is allowed only when the overall lightning protection concept needs it. Related connections are in equipotential bonding.
What do architects decide about SPDs at design stage?
Architects rarely size an SPD. The sources above support two early steps:
- Ask the electrical designer whether an SPD goes in the unmetered part. If so, raise it with the distributor in the design stage (SSD section 13(1)).
- Name the edition of the standards in the documentation, including the A11 change sheet and its transition date.
Frequently asked questions
- Is an SPD the same as a lightning conductor?
- No. STN EN IEC 62305-1 covers the protection of structures against lightning. An SPD is a device for AC circuits and equipment, covered by STN EN IEC 61643-11.
- Where may an SPD be installed relative to the meter?
- SSD prefers the measured part, after the meter. An unmetered placement needs the distributor's agreement, a T1 + T2 device with fuse protection, and a sealable cover.
- Which standard applies to SPDs in Slovakia?
- The Slovak edition is STN EN IEC 61643-11, released on 1 April 2026 and identical to IEC 61643-11:2025. A change sheet A11 exists, and the 2026 release may be used without it until 30 November 2028.
- Does an architect need to specify an SPD?
- Architects usually leave the device choice to the electrical engineer. They can ask whether an SPD goes in the unmetered part and name the standard edition in the documentation.
- What do T1 and T2 mean?
- They are the type names used in the IEC 61643-11 change list. SSD names the combined type T1 + T2, also written B+C. The clauses that assign types to places were not read.
Sources
- IEC 61643-11:2025 Low-voltage surge protective devices - Part 11: Surge protective devices connected to AC low-voltage power systems - Requirements and test methods · IEC Webstore · Abstract and list of significant technical changes
- STN EN IEC 61643-11, Nízkonapäťové prepäťové ochranné prístroje, Časť 11: Prepäťové ochranné prístroje zapojené v sieťach nízkeho napätia striedavého prúdu. Požiadavky a skúšobné metódy (catalogue entry) · ÚNMS SR, normy.normoff.gov.sk · Catalogue entry
- STN EN IEC 61643-11/Zmena A11 (catalogue entry) · ÚNMS SR, normy.normoff.gov.sk · Catalogue entry
- STN EN IEC 62305-1, Ochrana pred bleskom, Časť 1: Všeobecné princípy (catalogue entry) · ÚNMS SR, normy.normoff.gov.sk · Catalogue entry
- STN EN IEC 62305-4, Ochrana pred bleskom. Časť 4: Elektrické a elektronické systémy v stavbách (edition 2026-07, catalogue entry) · ÚNMS SR, normy.normoff.gov.sk · Catalogue entry
- Zásady a podmienky montáže a prevádzkovania merania elektriny, Príloha č. 2 · Stredoslovenská distribučná, a.s. (SSD) · 13(1) to (6), 14.1
- Podmienky merania elektriny (Postup č. D6.ELM.01, verzia 4, účinnosť 1. 1. 2025), part of Pravidlá pre prevádzkovanie a montáž merania elektrickej energie · Západoslovenská distribučná, a.s. (ZSD) · 3.5