Population equivalent
Population equivalent (ekvivalentný obyvateľ, 1 EO) is a unit of organic pollution equal to 60 g of BOD5 per day that sizes wastewater plants.
What is a population equivalent?
A population equivalent (ekvivalentný obyvateľ, 1 EO) is a unit of organic pollution load. It is not a count of people. In the Slovak Water Act (364/2004 Z. z.), 1 EO is the biodegradable organic pollution of one inhabitant in one day. The act expresses it as five-day biochemical oxygen demand (BOD5). It sets the value at 60 g of BOD5 per day (§ 2 písm. s).
The unit lets an engineer or an authority compare a house, a restaurant and a village on one scale. A domestic wastewater treatment plant is sized and permitted by its size in EO.
Where does the 60 g BOD5 figure come from?
The figure is a reference value in the law. It is not a measurement of one household. Government decree 269/2010 repeats it in the explanations of annex 6. There, 1 EO is the load that equals the pollution of one inhabitant, that is 60 g of BOD5 per day. The decree measures BOD5 with nitrification suppressed (the abbreviation BSK5 ATM in Slovak).
The unit is a mass per day, not a concentration. A concentration in mg/l depends on how much water carries the load. Two sources with the same load in EO can have very different concentrations.
How is population equivalent different from the number of residents or the water volume?
Population equivalent counts organic load. A resident count counts people. The Water Act uses both in one definition. A small plant has a size up to 50 EO and an inflow below 10 m3 a day (§ 36 ods. 18). The two limits are separate because load and volume are different quantities.
| Measure | What it counts | Unit |
|---|---|---|
| Residents | People | Persons |
| Population equivalent | Organic load, with 1 EO as the reference value | 60 g of BOD5 per day |
| Wastewater volume | Water that leaves the building | m3 per day |
Which Slovak rules use population equivalents?
Several rules use EO as a threshold. The table lists the ones that matter for a house or for the area around it.
| Threshold | What changes | Source |
|---|---|---|
| Up to 50 EO and inflow below 10 m3 a day | The facility is a small wastewater treatment plant, with its own limit values and inspection | Water Act § 36 ods. 18, § 53 ods. 2 |
| Agglomeration above 2 000 EO | Wastewater must go through a public sewer only, unless a public sewer brings no environmental benefit or costs too much | Water Act § 36 ods. 2 |
| Agglomeration below 2 000 EO without a public sewer | Individual systems are possible, such as watertight cesspits and, in sparsely populated areas, small plants | Water Act § 36 ods. 3 |
| Planned capacity of a public sewer: below 2 000 EO, 2 000 to 25 000 EO, above 25 000 EO | Category III, II or I. The category decides which operator qualification certificate is needed | Sewerage Act 442/2002 Z. z., § 6 ods. 2 and 5 |
Most single houses are not public sewers. The category table matters mainly to municipalities and operators. For a house, the question is whether the building connects to a public sewer or needs its own plant. See sewer connection.
How do the limit values depend on the size in EO?
Decree 269/2010 sets limit values for wastewater that goes to surface water by size of the source. The tables in annex 6 name a source above 50 EO an agglomeration. For sources up to 50 EO, the decree has separate limits by plant category. The table shows the first three size classes. The value p applies to a composite sample over a period. The value m is the maximum in a spot sample.
| Size of source | COD (p / m), mg/l | BOD5 (p / m), mg/l | Suspended solids (p / m), mg/l |
|---|---|---|---|
| 51 to 500 EO | 150 / 220 | 40 / 70 | 50 / 80 |
| 501 to 2 000 EO | 135 / 170 | 30 / 60 | 30 / 60 |
| 2 001 to 10 000 EO | 120 / 170 | 25 / 45 | 25 / 50 |
The decree states how to work out the load for these tables. The load in EO comes from the highest weekly average load at the inflow to the plant in the last calendar year. Unusual events, such as a cloudburst or sudden snow melt, do not count (decree 269/2010, annex 6, explanations).
What are common misconceptions about population equivalent?
One misconception is that one EO equals one litre of water. It does not, because the unit is a mass of BOD5 per day. Another misconception is that EO counts the residents of a house. The law defines the unit by a reference load. It does not say how many EO one resident or one guest room adds.
The sources read for this page give no value of EO per person for a house design. Ask the designer of the treatment plant which design value applies. Then write it into the design brief, next to the expected use of the building.
Frequently asked questions
- What does 1 EO mean?
- One EO, or population equivalent, is the amount of biodegradable organic pollution that equals the pollution of one inhabitant in one day. The Water Act sets it at 60 g of BOD5 per day (§ 2 písm. s). It is a load unit, not a count of people in a building.
- Is the 60 g BOD5 figure a measured value?
- No. It is a reference load that the Water Act fixes in the definition. Government decree 269/2010 repeats it. Real households differ, so the designer of a plant checks the figure against the expected use of the building.
- Does population equivalent tell me how much water a house uses?
- No. EO measures organic pollution as a mass per day. Water volume is a separate quantity in m3 per day. The Water Act limits both for a small plant (§ 36 ods. 18).
- How many EO is a family house?
- The Water Act and decree 269/2010 give no number of EO per resident. The law defines 1 EO by the reference load of 60 g of BOD5 per day. The designer of the treatment plant states the design load.
- When does a treatment plant count as a small plant in Slovakia?
- Under the Water Act, a small plant serves up to 50 EO and has an inflow below 10 m3 a day (§ 36 ods. 18). Small plants have inspection duties and category limits in decree 269/2010. A larger source gets limits by size or individual limits.
- Which law defines population equivalent in Slovakia?
- The Water Act, zákon č. 364/2004 Z. z. o vodách, defines it in § 2 písm. s. The sewer categories by EO are in § 6 ods. 5 of the Sewerage Act, zákon č. 442/2002 Z. z.
Sources
- Zákon č. 364/2004 Z. z. o vodách a o zmene zákona Slovenskej národnej rady č. 372/1990 Zb. o priestupkoch (vodný zákon) · Slov-Lex (Ministry of Justice of the Slovak Republic) · § 2 písm. k, m, s; § 36 ods. 2, 3, 18; § 53 ods. 2
- Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách · Slov-Lex (Ministry of Justice of the Slovak Republic) · § 6 ods. 2 and 5
- Nariadenie vlády Slovenskej republiky č. 269/2010 Z. z., ktorým sa ustanovujú požiadavky na dosiahnutie dobrého stavu vôd · Slov-Lex (Ministry of Justice of the Slovak Republic) · Annex 6 parts A.1, A.1.1, A.2 and explanations