Sewer connection

A sewer connection is the pipe that carries wastewater from a plot or building to the public sewer. The property owner owns it and pays for it.

What is a sewer connection?

A sewer connection (kanalizačná prípojka) is the pipe section that carries wastewater from a plot to the junction with the public sewer. It can also start at the outlet of a building's internal drains. The sewerage act 442/2002 Z. z. defines it this way (§ 4 ods. 2). The junction (zaústenie) is the branch from the public sewer pipe. It is part of the public sewer, but the connection pipe is not (§ 3 ods. 5 písm. h). The utility connections entry explains the wider family of links to the network.

Who owns and maintains the sewer connection?

The owner is the person who built the connection at their own cost, in the way the sewer operator set (§ 4 ods. 6). If the owner of the property owns the connection, it passes to the new owner when the property changes hands (§ 4 ods. 6). The owner of the connection must meet three duties (§ 4 ods. 8):

  • keep the connection watertight and build it to the technical requirements of the sewer owner or operator (písm. a),
  • pay for its repair and maintenance (písm. b),
  • remove the link to the junction at their own cost if the operator decides so (písm. c).
PartWhat the act saysBasis
Internal drains of the buildingThe connection starts at their outlet. They are not part of the connection§ 4 ods. 2
Connection pipeOwned by the person who built it. The owner pays for repair and maintenance§ 4 ods. 6 and 8
Junction (zaústenie)Part of the public sewer. The sewer owner bears the cost of setting it up, unless the applicant agrees to pay§ 4 ods. 2 and 11

A junction in a public space has a branch fitting on the sewer pipe and a pipe that usually ends in an inspection shaft. This pipe runs from the fitting to the property boundary and is at most 10 m long. Its diameter must suit the future connection (§ 4 ods. 2). On other land the junction is only the branch fitting. A producer may build a junction at their own cost. If this happened after 1 January 2023, the sewer owner must take it over into ownership and operation. This applies if the producer met the build conditions set by the operator or owner (§ 4 ods. 12).

Is connecting to the public sewer mandatory?

Yes, where the municipality has a public sewer. The owner of a building or plot where wastewater arises must connect it. The owner must also meet the technical conditions for the place and method of connection. The owner must sign a connection contract with the sewer owner (§ 23 ods. 2). The municipality imposes this duty on the owner (§ 4 ods. 14). The duty has limits.

SituationPosition under the act
The municipality has a public sewer and the owner has no other permitThe duty to connect applies (§ 23 ods. 2)
The water authority gave the owner a permit for another way to handle wastewaterThe duty does not apply while the permit holds (§ 23 ods. 2)
The plot has a permitted holding tank (žumpa)The owner must connect if this is technically possible and does not need unreasonably high costs (§ 23 ods. 2)
One connection for several buildings or plots, or several for one buildingAllowed in justified cases with the consent of the sewer operator (§ 23 ods. 4)

What does the connection contract cover?

The applicant may connect only under a written contract with the sewer owner (§ 23 ods. 1). The owner signs it if two conditions hold. The applicant meets the technical conditions for place and method, and the sewer capacity allows the connection (§ 23 ods. 3). The utility connection agreement entry describes the contract in general.

The sewer owner or operator sets the conditions for the connection, above all the place and method. It does this in a statement (vyjadrenie) to a request for connection. In the proceedings on the building intent, the conditions come in a binding statement (záväzné vyjadrenie) or a statement (§ 4 ods. 13). The operator must set the technical conditions free of charge. It must also provide technical documents for the connection free of charge (§ 18 ods. 2 písm. f to h). It comments on the project documentation of a family house for a fee. It does so within 30 days of receiving the request (§ 18 ods. 2 písm. i).

The sewer owner may refuse the connection for reasons the act lists. Examples are insufficient capacity of the sewer and treatment plant, and equipment that does not meet the technical conditions (§ 23 ods. 10). The operator must give the applicant its reasons in writing within 30 days of receiving the request (§ 23 ods. 11).

A person who discharges wastewater into the public sewer is a producer. A producer has a contract with the sewer owner on discharging wastewater (zmluva o odvádzaní odpadových vôd, § 4 ods. 4). The operator must connect the applicant's connection to the sewer within 15 working days. The period starts on the day the parties conclude this contract (§ 18 ods. 2 písm. o).

DocumentWhat it gives the ownerBasis
Statement or binding statement of the operatorThe place, method and conditions of the connection§ 4 ods. 13
Connection contractThe right to connect, in writing§ 23 ods. 1 and 3
Contract on discharging wastewaterThe status of a producer. The 15-working-day period for the operator starts on the day the parties conclude it§ 4 ods. 4, § 18 ods. 2 písm. o

What does the building act require for a sewer connection?

The building act 25/2025 Z. z. lists a sewer connection and its junction among minor structures (§ 2 ods. 4 písm. e). For minor structures of this type, the act requires notification to the building office only in listed cases. Examples are works in a public space and works closer than 2 m to the plot boundary. Another example is works in a flood area with retention potential (§ 18 ods. 3 písm. a, b, i). The notification includes the binding statements of the affected legal persons (§ 63 ods. 2). The sewer operator is such a person. The minor structure notification entry describes the procedure. From 1 January 2027, amendment 243/2026 moves the list of minor structures to § 2 ods. 7 of the act.

How is a sewer connection different from a holding tank or treatment plant?

A sewer connection sends wastewater to the public network. A holding tank or a domestic wastewater treatment plant keeps the wastewater on the plot. The sewerage act says that holding tanks and domestic treatment plants are not a public sewer (§ 3 ods. 5 písm. f). Where a public sewer is available, the owner must connect unless a permit allows another way.

What do architects check before designing the connection?

These points follow from the rules above. They are design advice, not legal requirements.

  • Ask the sewer operator for its written conditions early. The operator sets the place and method of the connection (§ 4 ods. 13).
  • Check which connection type the sewer system uses, because the act mentions gravity, pressure or vacuum connections by system (§ 23 ods. 4).
  • Agree a shared connection with a neighbour with the operator first, because it needs the operator's consent (§ 23 ods. 4).
  • Plan where rainwater goes. If the owner disconnects surface runoff from the connection, the owner must tell the sewer owner in writing. The notice says how the plot holds back or uses the water (§ 4 ods. 8 písm. d).

What are the common misconceptions about sewer connections?

  • The water company owns the connection. The act gives ownership to the person who built it at their own cost (§ 4 ods. 6). The junction and the public line belong to the sewer owner.
  • The connection is part of the public sewer. The act excludes connections from the definition (§ 3 ods. 5 písm. h). The owner pays for repair and maintenance (§ 4 ods. 8).
  • Once the connection exists, nothing else is needed. The owner must still keep it watertight (§ 4 ods. 8 písm. a). A person who discharges wastewater needs a contract with the sewer owner (§ 4 ods. 4).

Frequently asked questions

Can one sewer connection serve two houses?
Yes, in justified cases and with the consent of the sewer operator. The act allows one connection for several buildings or plots, or several connections for one building or plot (442/2002, § 23 ods. 4).
Does a sewer connection go to a new owner when the house is sold?
Yes, if the owner of the property owns the connection. Ownership passes to the new owner of the property (§ 4 ods. 6). The new owner then keeps the connection watertight and pays for its repair (§ 4 ods. 8).
What if my village has no public sewer yet?
The duty to connect applies only where the municipality has a public sewer (§ 23 ods. 2). Ask the municipality whether one exists or is planned before you finish the drainage design.
What if I send rainwater into the sewer connection?
The sewer operator may refuse a connection if surface runoff can be handled outside the public sewer (§ 23 ods. 10 písm. d). If you disconnect runoff from the connection, tell the sewer owner in writing. Say how the plot holds back or uses the water (§ 4 ods. 8 písm. d).
Who sets the place where the connection enters the public sewer?
The owner or operator of the public sewer sets the place and method of connection. It does so in its statement or binding statement, or in its reply to your request (§ 4 ods. 13).
How fast must the operator connect me?
The operator must connect your connection to the public sewer within 15 working days. The period starts on the day you conclude the contract on discharging wastewater (§ 18 ods. 2 písm. o).

Sources

  1. Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách a o zmene a doplnení zákona č. 276/2001 Z. z. o regulácii v sieťových odvetviach · Slov-Lex · § 3 ods. 5 písm. c, f, h; § 4 ods. 2, 4, 6, 8, 11 to 14; § 18 ods. 2 písm. f to i, o; § 23 ods. 1 to 4, 10, 11
  2. Zákon č. 25/2025 Z. z. o výstavbe a o zmene a doplnení niektorých zákonov (stavebný zákon) · Národná rada SR, via Slov-Lex · § 2 ods. 4 písm. e; § 18 ods. 3; § 63 ods. 2
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, points on § 2 (minor structures)