Utility connection agreement
A utility connection agreement is a contract with a network operator that sets the terms and the fee for connecting a plot.
What is a utility connection agreement?
A utility connection agreement (zmluva o pripojení) is a contract between an applicant and a network operator that sets the terms of a connection.
Each network has its own rules. Electricity and gas come under the Energy Act (zákon č. 251/2012 Z. z.). Water and sewer come under the act on public water mains and public sewers (zákon č. 442/2002 Z. z.). The Building Act (zákon č. 25/2025 Z. z.) has no rules for these contracts. The operator sets the technical conditions of connection for its own network (251/2012, § 19 ods. 1).
Is a connection agreement the same as a binding statement?
No. A binding statement (záväzné vyjadrenie) is a document of an affected legal person under § 22 of the Building Act. It sets requirements for the building design (§ 22 ods. 3). The builder or the designer asks for it as part of the building intent (§ 20 ods. 1 písm. c). A connection agreement is a separate contract about the connection itself.
A third document is the supply contract with the company that sells you electricity, gas or water. For water and sewer, the operator must connect the applicant within 15 working days. The period starts on the day of the contract on water supply or waste water discharge (442/2002, § 17 ods. 2 písm. o, § 18 ods. 2 písm. o). The page on the utility network statement covers the statement the operator gives before the contract.
| Document | Who issues it | What it does | Source |
|---|---|---|---|
| Binding statement (záväzné vyjadrenie) | Affected legal person, such as a network owner | Sets requirements for the building design | 25/2025, § 22 ods. 3 |
| Connection agreement (zmluva o pripojení) | Signed by you and the network owner or operator | Sets the terms of the connection | 251/2012, § 17 ods. 10. 442/2002, § 22 ods. 1, § 23 ods. 1 |
| Supply contract | Signed by you and a supplier or the water owner | Covers the supply of electricity, gas or water | 442/2002, § 17 ods. 2 písm. o) |
Do you need a connection agreement to get a building decision?
The Building Act asks for binding statements, not for connection agreements. The office rejects an application if a statement of an affected legal person shows that the site has no possible connection to public networks. The rule does not apply if the building needs no connection or the networks are out of reach (§ 59 ods. 1 písm. f).
At the final inspection (kolaudácia) the office checks the connection to working networks. This applies where the municipality has them (§ 66 ods. 4 písm. d). See final inspection. For water and sewer, you may connect only under a written contract with the network owner (442/2002, § 22 ods. 1, § 23 ods. 1).
How does an electricity connection agreement work?
The Energy Act says that the distributor connects a household customer when the technical and commercial conditions are met. The price or the method to set it comes from the regulator ÚRSO. The contract must also state the deadline for the connection (251/2012, § 17 ods. 10).
The government portal slovensko.sk describes the steps in a guide of the Ministry of Economy. It names three regional operators: Západoslovenská distribučná, Stredoslovenská distribučná and Východoslovenská distribučná. The guide says:
- You apply online, by post, by e-mail or through your electricity supplier. For a new house you attach a site plan with the position of the building and the parcel numbers.
- The operator sends a draft contract within 30 days of your application.
- You return the signed contract. Its technical conditions bind you and the operator.
- You pay the connection fee by the deadline. If you do not, the draft expires and you must apply again.
- You prepare the metering point and give the operator the documents that its technical conditions list. The operator checks them and prepares the point by the date in the contract.
- You sign a supply contract with a supplier. The operator installs the meter within 5 working days of the request, which your supplier sends.
This guide was last changed on 6 September 2023. Ask the operator for its current rules. The operator may refuse access to the grid for lack of capacity. It must then give reasons and name the measures that strengthen the network (251/2012, § 31 ods. 1 písm. d, ods. 2 písm. c).
How does a gas connection agreement work?
Only the owner or the manager of the property may ask for a gas connection. A person who is not the owner needs the prior consent of the owner or manager. A refusal needs a reason (251/2012, § 73 ods. 1).
The slovensko.sk guide describes the process of the distributor SPP – distribúcia. It was last changed on 6 May 2026.
- You apply online, by post or at a customer office. You attach proof of ownership and a copy of the cadastral map, or the owner's consent or power of attorney.
- The operator sends an invoice for the connection fee. You have 21 days to pay it.
- The operator sends a draft contract within 30 days of the payment.
- You return the signed contract by the deadline. If you do not, the draft expires. You must then apply again and pay the fee again, and the operator returns only part of the first fee.
- You order the design and build the service line to the technical conditions of the contract.
- You ask for the meter during the validity of the contract. If you do not, the contract expires. An addendum can extend the validity by 12 months.
The regulator ÚRSO states that the fee follows its price decision. The fee does not include the geodetic survey, the inspection report or the documentation of the gas installation. The operator connects the house only after the inspection of your gas installation, which includes a pressure test.
How do water and sewer connection contracts work?
You apply to the owner or operator of the public water main or sewer. The owner or operator sets the place and the method of connection. It does this in a statement, in a binding statement or in its reply to your request (442/2002, § 4 ods. 13).
The owner must sign the contract if you meet the technical conditions and the network has capacity (§ 22 ods. 2, § 23 ods. 3). A building or plot gets one connection. In justified cases the operator may consent to more than one connection or to one shared connection for several buildings. For water the consent must be written (§ 22 ods. 3, § 23 ods. 4).
The sewer operator must show and explain the grounds in writing within 30 days of receiving the request (§ 23 ods. 11). If the municipality has a public sewer, the owner of a building must connect to it. An exception needs the permit of the state water authority for another way (§ 23 ods. 2). More on the pipes themselves is on the utility connections page.
Who pays for the connection?
For water and sewer, the person who builds the connection at their own cost owns it (442/2002, § 4 ods. 6). That owner also pays for its repair and maintenance (§ 4 ods. 7 písm. b, ods. 8 písm. b). The sewer owner pays for the junction with the public sewer, unless you agree to pay it (§ 4 ods. 11). You may build a further section of a public water main or sewer that joins the existing one. You pay for it unless you agree otherwise (§ 22 ods. 6, § 23 ods. 12).
For electricity, the Ministry of Economy guide says the operator builds the connection line up to the plot boundary or the meter. The person who needs the line pays. The cost is part of the connection price. You pay for the line from the meter into the building. For gas, you pay the fee described above and the cost of the service line you build.
This page prints no euro amounts. Prices differ by operator and by connection size, and the regulator changes them. Ask the operator for the current price list.
How do electricity and gas deadlines compare?
The table shows the deadlines that the two slovensko.sk guides state. Other operators may use other deadlines.
| Step | Electricity (slovensko.sk, Ministry of Economy) | Gas (slovensko.sk, SPP – distribúcia) |
|---|---|---|
| Draft contract | Within 30 days of the application | Within 30 days of the fee payment |
| Fee | Pay by the deadline in the contract documents | Pay within 21 days of the invoice |
| Meter | Within 5 working days of the request | After the contract conditions are met and the inspection is done |
What if you want to connect a solar plant?
For a plant that produces electricity, the distributor must send a draft contract within 30 calendar days of a complete application. The draft has technical and commercial conditions. The distributor must make the grid changes within six months of the signed contract. This applies if the grid works need no decision on the building intent (251/2012, § 19 ods. 9).
ÚRSO says that an owner who wants to connect a small source of up to 10.8 kW must first apply to the operator. The operator may limit the power you feed into the grid. It does this by setting a low or zero maximum reserved capacity.
What if the connection crosses a neighbour's land?
You need a right from the neighbour. The usual form is an easement (vecné bremeno). It arises by a written contract and you acquire the right only with an entry in the cadastre (Občiansky zákonník, § 151o ods. 1). Lines also bring protection zones that limit building near them.
Frequently asked questions
- Is a connection agreement the same as a binding statement?
- No. A binding statement comes from an affected legal person and sets design requirements (25/2025 Z. z., § 22 ods. 3). A connection agreement is a separate contract with the network owner or operator about the connection itself.
- How long does the electricity operator take to send the draft contract?
- The slovensko.sk guide of the Ministry of Economy says the draft comes within 30 days of your application. For a power plant, the Energy Act sets 30 calendar days from a complete application (251/2012 Z. z., § 19 ods. 9).
- How long does the gas distributor take to send the contract?
- According to the slovensko.sk guide for SPP – distribúcia, you have 21 days to pay the invoice for the fee. The operator then sends the draft contract within 30 days of the payment.
- What happens if I miss a deadline in the process?
- The draft or the contract can expire. If you do not pay the electricity fee in time, the draft expires. The same happens if you do not return the signed gas contract in time. You then apply again. For gas, the operator returns only part of the first fee.
- Who pays for the water and sewer connection?
- The person who builds the connection at their own cost owns it. That owner also pays for repair and maintenance (442/2002 Z. z., § 4 ods. 6 to 8). The sewer owner pays for the junction with the public sewer, unless you agree to pay it (§ 4 ods. 11).
- Can the operator refuse to connect my house?
- Yes, in the cases the acts list. A water owner may refuse if you do not meet the technical conditions (442/2002 Z. z., § 22 ods. 4). An electricity operator may refuse access to the grid for lack of capacity. It must give reasons (251/2012 Z. z., § 31 ods. 1 písm. d, ods. 2 písm. c).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 20 ods. 1, § 22 ods. 3, § 59 ods. 1 písm. f), § 66 ods. 4 písm. d)
- Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 17 ods. 10, § 19 ods. 1 a 9, § 31 ods. 1 písm. d), ods. 2 písm. c), § 73 ods. 1
- Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách a o zmene a doplnení zákona č. 276/2001 Z. z. o regulácii v sieťových odvetviach · Slov-Lex · § 4 ods. 6 až 8, 11 a 13, § 17 ods. 2 písm. o), § 18 ods. 2 písm. o), § 22, § 23
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 151o ods. 1
- Elektrina a plyn (pripojenie do distribučnej siete) · Úrad pre reguláciu sieťových odvetví
- Ako pripojiť nehnuteľnosť do distribučnej siete – plyn · Ústredný portál verejnej správy (slovensko.sk)
- Zriadenie novej elektrickej prípojky a pripojenie odberného miesta pre domácnosti · Ústredný portál verejnej správy (slovensko.sk), content owner Ministerstvo hospodárstva SR