Soakaway
A soakaway is an underground structure that lets rainwater or treated wastewater seep into the ground instead of leaving the plot through a pipe.
What is a soakaway?
A soakaway (vsakovací objekt) is an underground structure that lets water seep into the ground instead of leaving the plot through a pipe. In a house design, it takes either rainwater from roofs and paved areas or wastewater that a small plant has already cleaned. Decree 269/2010 uses the term for the second case. It requires an infiltration structure where a small plant discharges into groundwater (§ 5a ods. 7).
How does the water reach the groundwater?
The Water Act (364/2004 Z. z.) separates two ways. Direct discharge brings pollutants into groundwater without seepage through soil or the layers under it. Indirect discharge means seepage through soil or the layers under it (§ 2 písm. t and u). Water from a soakaway seeps through the soil, so it is an indirect discharge. The prior study for the permit looks at the soil and the rock at the site (§ 37 ods. 1).
When does a soakaway need a permit in Slovakia?
The answer depends on what enters the structure. The act defines water from surface runoff as rainwater that did not soak into the ground. The water is led from the terrain or from the outer parts of buildings into surface water or groundwater (§ 2 písm. i). Discharge of such water into surface water or groundwater needs a permit for special water use (§ 21 ods. 1 písm. d).
The act frees some uses from a permit. Catching rainwater from paved areas in ditches or tanks is one (§ 18 ods. 2 and 4). The sections read for this page do not list infiltration into the ground among these uses. So ask the water authority early whether your soakaway for roof water needs a permit. If the water carries pollutants, the permit is issued for 10 years at most (§ 21 ods. 4 písm. e).
Treated wastewater is a separate case. Discharge of wastewater into groundwater needs a permit under § 21 ods. 1 písm. c. The authority issues it for a fixed time, at most 6 years. It may extend the permit if the conditions do not change (§ 21 ods. 4 písm. d and ods. 5). The permit for the discharge comes before the decision on the building intent or together with it (§ 21 ods. 2).
What study does the water authority require?
For discharge of wastewater into groundwater, the authority issues the permit only after a prior study by an authorised person. The applicant pays for it. The study covers these points (§ 37 ods. 1 and 2):
- the hydrogeological conditions of the area
- the self-cleaning ability of the soil and rock at the site
- the risks of pollution and of a worse quality of groundwater
The study is not needed for sewage from a solitary dwelling that cannot connect to a public sewer. The dwelling must also stand outside the protection zones of water sources (§ 37 ods. 5). Discharge of wastewater with hazardous substances into groundwater is forbidden (§ 37 ods. 3). For the groundwater level at your site, see design groundwater level.
What limits apply to treated wastewater from a small plant?
Decree 269/2010 prefers discharge into surface water. If the water must go into the ground, the plant needs an infiltration structure and a sampling point. The inspection technician takes the samples (§ 5a ods. 7). The table shows the maximum values for a spot sample in mg/l by plant category (annex 6, part A.2). For the categories, see domestic wastewater treatment plant.
| Category | BOD5 | Suspended solids | Ammonia nitrogen | Total nitrogen | COD |
|---|---|---|---|---|---|
| I | 40 | 40 | not set | not set | not set |
| II | 40 | 40 | 20 | not set | not set |
| III | 40 | 40 | 15 | 25 | 125 |
Categories +P and +D add limits for total phosphorus (4 mg/l) and for E. coli and enterococci (annex 6, part A.2). For a source larger than 50 population equivalents, the water authority sets the limits one by one. See population equivalent.
How is a soakaway different from a septic tank or rainwater retention?
The three handle water on a plot, but each does a different job. A soakaway lets water seep into the ground. Rainwater retention holds water back so that it leaves the site slowly. A septic tank settles domestic sewage and releases the liquid to a further step. A soakaway does not clean sewage by itself.
| Structure | Water it takes | Where the water goes | Legal point to check |
|---|---|---|---|
| Soakaway | Rainwater, or treated wastewater from a small plant | Into the soil and groundwater below the plot | Permit under § 21 ods. 1 písm. c or d of the Water Act |
| Rainwater retention | Rainwater from roofs and yards | Held back, then released slowly | See rainwater retention |
| Septic tank | Domestic sewage | Settled liquid to a further treatment step | Not named in the Water Act. Ask the water authority |
| Domestic treatment plant | Domestic sewage | Treated water to surface water or, if needed, to a soakaway | Permit under § 21 ods. 1 písm. c. Limits in decree 269/2010 |
What does the Sewerage Act say about rainwater on a plot?
The owner of a sewer connection must tell the sewer owner or operator in writing when the plot stops draining runoff into the public sewer. The notice also says how the owner holds or uses the water (Sewerage Act 442/2002 Z. z., § 4 ods. 8 písm. d). A soakaway is one way to hold runoff on the plot. The notice should describe it.
The owner of a public sewer may refuse to connect runoff if it can be handled outside the sewer (§ 23 ods. 10 písm. d). That rule gives a reason to plan a soakaway or rainwater harvesting early.
Frequently asked questions
- Do I need a permit for a soakaway on my plot?
- It depends on what the structure takes. Discharge of runoff from roofs and yards into groundwater is a use listed in § 21 ods. 1 písm. d of the Water Act. The sections read do not exempt it, so ask the water authority. Treated wastewater needs a permit under § 21 ods. 1 písm. c.
- Is a soakaway the same as a rainwater retention tank?
- No. A soakaway lets water seep into the ground. A retention tank holds water back so that it leaves the site slowly. Some plots use both.
- What is the difference between a soakaway and a septic tank?
- A septic tank settles domestic sewage and releases the liquid to a further step. A soakaway lets water seep into the ground. A soakaway does not clean sewage by itself.
- Can a soakaway take treated wastewater from a small plant?
- Yes, with a permit. Decree 269/2010 prefers surface water. For discharge into the ground, it requires an infiltration structure and a sampling point (§ 5a ods. 7). The permit is for 6 years at most, and the authority may extend it if conditions do not change.
- What does the water authority want to know about the ground?
- For wastewater into groundwater, a prior study covers the hydrogeology, the self-cleaning ability of the soil and the pollution risk (Water Act § 37 ods. 1). A solitary dwelling that cannot connect to a sewer and stands outside protection zones needs no study.
Sources
- Zákon č. 364/2004 Z. z. o vodách a o zmene zákona Slovenskej národnej rady č. 372/1990 Zb. o priestupkoch (vodný zákon) · Slov-Lex (Ministry of Justice of the Slovak Republic) · § 2 písm. i, t, u; § 18 ods. 2, 4; § 21 ods. 1 až 5; § 37 ods. 1 až 5
- Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách · Slov-Lex (Ministry of Justice of the Slovak Republic) · § 4 ods. 8 písm. d; § 23 ods. 10 písm. d
- Nariadenie vlády Slovenskej republiky č. 269/2010 Z. z., ktorým sa ustanovujú požiadavky na dosiahnutie dobrého stavu vôd · Slov-Lex (Ministry of Justice of the Slovak Republic) · § 5a ods. 7; annex 6 part A.2