Design groundwater level
A design groundwater level is the water level in the ground that a designer assumes when checking waterproofing, drainage and uplift.
What is a design groundwater level?
A design groundwater level is the water level in the ground that a designer assumes when checking a structure against groundwater. A designer uses it for waterproofing, drainage and the check against uplift (buoyancy). It is a chosen value. It is not a single reading from a survey.
The value matters most for a basement, a semi-buried garage or any structure that sits below the water level. Water pushes on its walls and floor from outside.
Act 25/2025 (version to 31 December 2026) and the geological act 569/2007 (version from 1 April 2025) do not define this term. They give no method to calculate it. This page found no Slovak rule that says how to set the value.
What does Slovak law say about the survey behind the value?
The survey is where the water observations come from. Act 25/2025 gives two duties. The builder arranges the engineering-geological, hydrogeological and other survey work for the design documentation, unless the builder and the designer agree otherwise (§ 30 ods. 2 písm. b). The designer sets the scope of a hydrogeological survey and other surveys when the character of the structure requires them (§ 35 ods. 6 písm. c).
From 1 January 2027, amendment 243/2026 Art. I point 88 deletes the word "hydrogeological" from the builder's list in § 30 ods. 2 písm. b). The designer's duty in § 35 ods. 6 písm. c) is not changed by that point.
The geological act 569/2007 defines the surveys.
| Survey | What the act says it examines |
|---|---|
| Engineering-geological survey (§ 3 písm. g) | The engineering-geological and hydrogeological conditions of an area, especially for planning, documentation and the foundation of buildings |
| Hydrogeological survey (§ 3 písm. f) | Groundwater, including its quantity and quality |
A person with a geological authorisation carries out geological works. The state geological institute, universities and some other bodies may also carry them out in set cases (§ 4 ods. 1). For the survey types, see hydrogeological survey and geotechnical survey.
What does the Eurocode framework say about groundwater values?
The Slovak standards office (ÚNMS) states that Slovakia has used Eurocodes exclusively to design structures since April 2010. It also states that the national annexes contain country-specific data, such as geological and climatic data. The groundwater values for a Slovak design therefore sit inside the Eurocode framework.
The European Commission Joint Research Centre (JRC) quotes EN 1997-1 (Eurocode 7, geotechnical design, 2004 edition) on groundwater pressures. The table shows the wording, with the clause as the JRC report gives it.
| Case | Design values of groundwater pressures (EN 1997-1 clause 2.4.6.1) |
|---|---|
| Ultimate limit states | Must represent the most unfavourable values that could occur during the design lifetime of the structure |
| Serviceability limit states | Must be the most unfavourable values that could occur in normal circumstances |
| How to derive them | By applying partial factors to characteristic water pressures, or by applying a safety margin to the characteristic water level |
The JRC report notes that it is not clear what "normal circumstances" means. A JRC training presentation lists the uplift limit state (UPL) among the ultimate limit states of Eurocode 7-1. It describes UPL as loss of equilibrium due to uplift by water pressure (buoyancy) or other vertical actions.
This page did not read STN EN 1997-1 or the Slovak national annex. The wording above is from the 2004 edition as quoted by the JRC. Check the edition and the national annex in force before fixing a value for a real project.
What do retaining-wall guidelines say about water levels?
The same JRC report discusses retaining walls. For a wall that retains soil of medium or low permeability, the report says Eurocode 7 expects a design water level above the formation level. Without reliable drainage, the water level should normally be taken at the surface of the retained material. With reliable drainage, the level may be assumed below the top of the wall. That choice brings a maintenance requirement, because the drainage must stay reliable. See perimeter drainage system.
Does the waterproofing standard set the groundwater value?
No. The German standard DIN 18533-1, edition June 2026, covers waterproofing of elements in contact with soil. It replaces the 2017 edition and its 2018 amendment. Its scope text lists what it does not cover. That list includes watertight components, such as a watertight concrete structure. It also lists the determination of actions on components below ground level, for example protection against flotation. The 2026 edition also renames the former water exposure classes as water stress classes. The catalogue page does not explain how a groundwater level is set. This page did not read the standard text, which is paid.
How does a design level differ from a measured level?
Eurocode 7 derives the design value from a characteristic water level or characteristic water pressure. A design value is therefore a separate number from the level seen in a borehole on one day. The act texts above say nothing about how a Slovak designer must choose the margin. Ask the designer which water level the design assumes, which survey it comes from and which margin the designer applied.
Frequently asked questions
- Is the design groundwater level the same as the highest level ever recorded?
- Not by definition. EN 1997-1, as quoted by the JRC, sets this rule for ultimate limit states. Design values must represent the most unfavourable values that could occur during the design lifetime of the structure. A record is one input to that judgement.
- Who orders the survey for a house?
- Under Act 25/2025 § 30 ods. 2 písm. b), the builder arranges the engineering-geological, hydrogeological and other survey work, unless the builder and the designer agree otherwise. The designer sets the scope of a hydrogeological survey where the structure needs one (§ 35 ods. 6 písm. c).
- Does Slovak law define a design groundwater level?
- This page found no definition and no calculation method in Act 25/2025 or in the geological act 569/2007. The value sits inside the Eurocode framework, with the national annex supplying country-specific data.
- Does DIN 18533-1 give the groundwater value?
- No. The scope text of DIN 18533-1, edition June 2026, excludes the determination of actions on components below ground level, for example protection against flotation. The standard covers the waterproofing, not the water level.
- What is the uplift check?
- Eurocode 7-1 lists an uplift limit state (UPL). A JRC presentation describes it as loss of equilibrium due to uplift by water pressure (buoyancy) or other vertical actions.
- Who may carry out a geological survey in Slovakia?
- Act 569/2007 § 4 ods. 1 names a person with a geological authorisation, the state geological institute, and universities, schools, museums and other bodies in set cases. Check the act for the conditions.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex (Národná rada SR) · § 30 ods. 2 písm. b); § 35 ods. 6 písm. c)
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (Art. I from 1 January 2027) · Slov-Lex, Ministerstvo spravodlivosti SR · Čl. I bod 88
- Zákon č. 569/2007 Z. z. o geologických prácach (geologický zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 3 písm. f) a g), § 4 ods. 1
- Eurokódy (eurocodes) - status of adoption into the STN system · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR (ÚNMS SR) · page text
- Eurocode 7: Geotechnical Design, Worked examples, Report EUR 26227 EN (2013), Retaining structures I · European Commission Joint Research Centre · Retaining structures I, water levels and water pressures
- General presentation of Eurocode 7 'Geotechnical design' (R. Frank), Workshop Eurocodes: background and applications, Brussels, 18-20 February 2008 · European Commission Joint Research Centre · Ultimate limit states - Eurocode 7-1
- DIN 18533-1:2026-06 Abdichtung von erdberührten Bauteilen - Teil 1: Anforderungen, Planungs- und Ausführungsgrundsätze · DIN Media (Deutsches Institut für Normung) · Anwendungsbereich, Ersatzvermerk, Änderungen