White or Black Tank for a Basement

8 min read
Illustration: a basement under construction seen from inside the excavation, plain grey reinforced concrete walls with formwork tie holes, a concrete floor slab, a strip and starter bars at the wall base joint, and a stack of formwork panels

What decides between a white tank and a black tank?

Water first, material second. The white tank and the black tank answer one question. What water load will the basement carry over the whole life of the house? Until the ground survey and the designer know that, comparing quotes makes no sense. This text follows the comparison of structural systems in What to build a house from and covers only the underground storey.

The Slovak decree 532/2002 Z. z. on general technical requirements for construction sets a goal, not a solution. An underground structure that separates the interior from the soil must be insulated against ground moisture, groundwater and heat loss into the ground. Where needed, it must also be insulated against radon ingress (§ 23 ods. 3). Foundations are protected against aggressive water as needed (§ 23 ods. 4). The decree stays in force until the new implementing regulations take effect. This is at the latest 31 March 2027 (Act 25/2025 Z. z., § 84 ods. 23).

What water loads can a basement face?

A clear classification comes from the German standard DIN 18533-1 on waterproofing of building parts in contact with soil, June 2026 edition. The text is paid, so we give only the classes from its published table of contents. It is not a Slovak requirement, but it is a useful vocabulary for talking to the designer.

ClassLoad as named in the standardWhere it occurs in a house
W1-EGround moisture and non-pressing water, subclasses W1.1-E and W1.2-E with drainageWalls and slab in the ground without pressing water
W2-EPressing water, subclasses W2.1-E and W2.2-EWalls and slab under pressing water
W3-ENon-pressing water on soil-covered slabsRoof slab of an underground part covered with soil
W4-ESplash water at the wall base and capillary water in and under wallsWall base and the damp-proof layer in the wall section

Under W2-E the standard has a separate chapter on ground with held-up water (German Stauwasser). The standard also has three room-use classes, RN1-E to RN3-E, from low to high requirement. The requirement for the waterproofing therefore also depends on how the basement will be used.

Where will the groundwater be, and who finds out?

The builder arranges the engineering-geological, hydrogeological and other survey work needed for the design, unless the builder agrees otherwise with the designer (25/2025 Z. z., § 30 ods. 2 písm. b). The designer sets the scope of the hydrogeological survey where the nature of the structure requires it (§ 35 ods. 6 písm. c). From 1 January 2027 the amendment 243/2026 Z. z. removes the word "hydrogeological" from § 30 ods. 2 písm. b (Art. I point 88). Still, nobody knows the water level under a basement without a survey.

From the survey report the designer derives the design groundwater level. When reading the report, tell two levels apart. One is the level measured in the borehole on the day of drilling. The other is the level the designer uses for the design. The German standard DIN 4095-1 sets the water actions on walls and slabs in the ground. According to the publisher's accompanying note, it is also the basis for checking a structure against flotation. A basement submerged in water is therefore threatened not only by damp but also by uplift.

How does a white tank work?

A white tank is a basement of watertight concrete without a separate waterproofing layer. The German DAfStb guideline on watertight concrete structures (WU-Richtlinie, 2017 edition) describes it this way. The concrete structure carries the loads. Together with sealing of joints and cracks, it also does the sealing on its own. The guideline limits moisture transport through the concrete, joints, built-in parts and cracks under permanently or temporarily pressing water and under ground moisture.

This shows where tightness needs watching: joints, built-in parts and cracks.

  • Construction joints. The joint between slab and wall is sealed with a water-stop strip or an injection hose. One maker warns that the hose does not seal the joint by itself. It is only a path for the injection material, which fills the joint. Some types can be injected again and serve as a back-up to water-stop strips.
  • Cracks. The design of the structure limits crack width. Even the maker of a crystalline admixture writes in its data sheet that the designer must keep to the crack-width limits in every case. The values are set by the WU-Richtlinie, whose text is paid and was not opened, so we give none.
  • Formwork tie holes. The maker of a bentonite system states that through-holes must be filled with non-shrink grout with a sealing profile in the middle of the wall.

A white tank therefore depends on details and on site procedure, not only on the material. Before the pour, agree the joint drawing, the pour sequence and concrete curing. Have the person appointed for site supervision accept every joint. The record belongs in the site diary, which is the documentary record of the progress of the works (25/2025 Z. z., § 10 ods. 2).

How does a black tank work, and how is a leak found?

A black tank is a concrete or masonry basement with sheet or membrane waterproofing on the outside. The concrete carries, the layer seals. DIN 18533-1 has separate chapters on the transition from wall to slab waterproofing and on backfilling the excavation. It also has one on protection layers of concrete, masonry or foam plastic and cellular glass boards. So the standard also deals with keeping the protection layer and the backfill from damaging the waterproofing.

The weak point of a black tank is finding a leak. The maker of a fully bonded membrane states that the bond to the concrete is meant to prevent lateral water migration. With a layer that does not bond to the concrete, water can therefore travel further from the damaged spot. The fault is then harder to find. The waterproofing lies on the outside of the wall under the backfill, so a repair from outside starts with removing the backfill. The open sources do not describe how a fault is located.

Pre-applied membranes

A pre-applied membrane is laid on the subgrade or on permanent formwork and the concrete is poured directly against it. One maker states it can be applied to permanent formwork or to an adjoining structure, which it uses on confined sites. It does not recommend it with conventional two-sided formwork. Exposed parts must be protected before backfilling.

Brown tank and crystalline systems: where are the limits?

Bentonite waterproofing uses sodium bentonite, which swells in water. According to one maker's data sheet, unconfined bentonite can swell up to 15 times its dry volume. Confined under pressure, it forms a dense sealing layer. Crystalline waterproofing in the form of an admixture is added straight into the concrete. The table sums up what the sources say about each system.

SystemWhat sealsWhat the source warns about
White tankConcrete together with sealing of joints and cracksMoisture transport through joints, built-in parts and cracks must be limited (WU-Richtlinie)
Black tankSheets or membrane on the outsideTransitions, penetrations, protection layer and backfill have their own chapters (DIN 18533-1)
Bentonite (brown tank)Swollen bentonite under confinementFor contaminated groundwater, for example with chlorides or sulfates, the maker points to a more resistant type. Not intended for masonry block walls or expansion joints
Crystalline admixtureConcrete with the admixtureThe maker states healing of cracks up to 0.4 mm, but movements of the structure can open healed cracks again. It excludes concrete of exposure class XA3
Pre-applied membraneMembrane bonded to the concreteThe bond is meant to prevent lateral water migration. Not with two-sided formwork

So both systems have limits. A crystalline admixture belongs in concrete for which the crack-width limits must still be kept. Bentonite needs confinement, must stay dry until backfilling, and the maker advises scheduling the pour or the backfill right after it is laid.

How does waterproofing meet radon protection?

The designer of a residential building with a basement or a ground storey for long-term occupancy must take preventive measures. Indoor radon must not exceed the reference level of 300 Bq/m3 as an annual average (Act 87/2018 Z. z., § 130 ods. 1). The owner arranges a measurement within one year of the start of use (§ 130 ods. 3). Decree 57/2024 Z. z. lists preventive measures. They include determining the radon index of the plot and a measure against radon entry from the ground. Another is tighter contact structures with depressurisation under the building (§ 6 ods. 1).

Water and gas are not the same. The maker of a pre-applied membrane describes it as a barrier to water, moisture and gas, but that is a claim for one product. Whether the waterproofing also serves as a radon barrier is decided by the design, based on the radon index and the maker's documents. With a white tank, ask how joints and penetrations are sealed against gas.

Why are light wells and penetrations weak points?

The standard gives the details their own chapters. DIN 18533-1 has separate chapters on penetrations, including minimum distances. Others cover built-in parts such as flanges and a service entry with a sealing flange. One covers waterproofing light wells and outside stairs under both W1-E and W2-E. The maker of a bentonite system describes a sheet collar, sealing paste and a swelling profile around a pipe.

For the design this means:

  • Draw the penetrations of water, sewer and power connections in the design with the distances between them. A chapter of the standard covers minimum distances.
  • Design a light well in pressing water under the standard's chapter for W2-E. The contents of the standard give an example of a pressure-tight light well component under W2.1-E.
  • Draw the outside stairs to the basement and their threshold in the design, not improvise them on site.

Is a basement worth it with a high water table?

It depends on the water level. Pumping groundwater and discharging it into surface or ground waters when founding a structure is a special use of water. It needs a permit from the state water authority (Act 364/2004 Z. z., § 21 ods. 1 písm. g). A basement in pressing water (class W2-E) also needs a check against flotation, for which, according to the publisher, DIN 4095-1 gives the basis.

There are three options. One is a basement as a white or black tank for the design level. Another is a shallower basement above the design level. The third is a house without a basement and with a plant room on the ground floor. The decision is worth making before buying the plot, or at least before the concept design, while the layout is not yet drawn.

What to ask the designer and the contractor for?

  1. The survey report with the measured water level and an estimate of its variation.
  2. The water load class and the required use of the basement, stated in the technical report.
  3. For a white tank, a drawing of construction joints with water-stop strips or hoses and instructions for curing the concrete.
  4. For a black tank, the waterproofing build-up with its protection layer and instructions for backfilling.
  5. Details of penetrations, light wells and the link to radon protection.
  6. Acceptance of every joint and every waterproofing layer before it is covered, recorded in the site diary. Among others, the designer and the person appointed for site supervision may write in it (25/2025 Z. z., § 39 ods. 2).

Frequently asked questions

Is a white tank cheaper than a black tank?
The sources used in this text give no prices, so we do not compare them. When comparing quotes, compare the whole solution. For a white tank, include joint sealing, injection and supervision of the pour. For a black tank, include the protection layer and the backfill.
Can a leaking white tank be repaired?
If the construction joints contain injection hoses, the joint can be filled with injection material afterwards. One maker states that no drilling is needed for the injection and that some hose types can be injected again. Cracks outside the joints are dealt with separately, as a specialist designs.
Do I need drainage around a basement?
The design decides. DIN 18533-1 has a separate subclass W1.2-E with drainage for ground moisture and non-pressing water. According to the publisher, DIN 4095-1 is also the basis for designing drainage.
What if the survey found no groundwater?
Finding no groundwater does not yet rule out water around the basement. Under pressing water (W2-E), DIN 18533-1 also covers ground with held-up water (German Stauwasser). Ask the author of the geotechnical survey whether water can be held up around the basement.
Does the Slovak decree prescribe a specific waterproofing?
No. Decree 532/2002 Z. z. names no specific waterproofing in § 23. It requires an underground structure to be insulated against ground moisture, groundwater, heat loss into the ground and, where needed, radon (§ 23 ods. 3). Whether it needs pressure-water waterproofing is set by the design, based on the survey.
Does a white-tank basement also need thermal insulation?
Decree 532/2002 Z. z. also requires insulation against heat loss into the ground (§ 23 ods. 3). DIN 18533-1 covers cellular glass boards on or under the ground slab and protection layers of boards. The designer sets the thickness and position of the insulation.

Sources

  1. Vyhláška MŽP SR č. 532/2002 Z. z., ktorou sa ustanovujú podrobnosti o všeobecných technických požiadavkách na výstavbu a o všeobecných technických požiadavkách na stavby užívané osobami s obmedzenou schopnosťou pohybu a orientácie · Slov-Lex (Ministerstvo spravodlivosti SR) · § 23 ods. 3 a 4
  2. Zákon č. 25/2025 Z. z. Stavebný zákon · Slov-Lex (Ministerstvo spravodlivosti SR) · § 10 ods. 2, § 30 ods. 2 písm. b, § 35 ods. 6 písm. c, § 39 ods. 2, § 84 ods. 23
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. · Slov-Lex (Ministerstvo spravodlivosti SR) · Čl. I bod 88
  4. Zákon č. 364/2004 Z. z. o vodách (vodný zákon) · Slov-Lex (Ministerstvo spravodlivosti SR) · § 21 ods. 1 písm. g
  5. Zákon č. 87/2018 Z. z. o radiačnej ochrane · Slov-Lex (Ministerstvo spravodlivosti SR) · § 130 ods. 1 a 3
  6. Vyhláška MZ SR č. 57/2024 Z. z. o obmedzovaní ožiarenia z prírodných zdrojov · Slov-Lex (Ministerstvo spravodlivosti SR) · § 6 ods. 1
  7. DIN 18533-1:2026-06 Abdichtung von erdberührten Bauteilen, Teil 1: Inhaltsverzeichnis · DIN e. V. (Normenausschuss Bauwesen) · Table of contents, sections 5, 8.6.5, 9 to 14, Annex A
  8. Begleithinweis zur Veröffentlichung von DIN 4095-1 und DIN 18533 (alle Teile) · DIN Media · Whole note
  9. DAfStb-Richtlinie Wasserundurchlässige Bauwerke aus Beton (WU-Richtlinie), Ausgabe 2017-12 · DIN Media · Kurzreferat (abstract)
  10. SikaFuko injection hose systems: waterproofing solutions for construction joints · Sika AG · Function of SikaFuko, key advantages
  11. VOLTEX DS bentonite geotextile waterproofing, technical data (2015-06, v4) · CETCO (Minerals Technologies) · Description, installation, limitations
  12. BETOCRETE-CL210-WP crystalline waterproofing admixture, technical data sheet (22/05/2025) · Schomburg GmbH & Co. KG · Advantages, notes
  13. PREPRUFE 300LT and 160LT membranes data sheet (US version) · GCP Applied Technologies · Product description, advantages, installation