Black tank waterproofing
A black tank is a below-ground structure that keeps water out with a continuous sealing layer on its outer surfaces.
A black tank is a below-ground structure that keeps water out with a continuous sealing layer on all sides of the building part. In Slovak it is called čierna vaňa. BauNetz Wissen is a German technical site sponsored by the concrete industry. It says the sealing is usually bitumen or plastic sheets or bituminous coatings, and that the black colour gives the system its name. The counterpart is the watertight concrete structure, known as the white tank.
What is a black tank?
A black tank is a basement or other below-ground part whose sealing is a separate layer. BauNetz Wissen says the sealing goes on the outside of the basement walls and floors. It gives the parts to be sealed a continuous skin on all sides. In a white tank, by contrast, the reinforced concrete has both a structural and a sealing function.
German trade texts name three tank types. The black tank has an outside sealing of sheets or coatings. The white tank is waterproof concrete. The brown tank combines waterproof concrete with bentonite sheets. A fourth, the yellow tank, uses fresh-concrete bonding sheets to close possible weak spots before the concrete is poured. BauNetz Wissen describes all four.
The German standard DIN 18533-1 covers the planning, selection and execution of sealing for components that touch the soil, using sheet and liquid-applied materials. It also covers earth-covered underground structures built in open construction. DIN Media states this scope on its catalogue page. Sheet materials are the subject of waterproofing membranes, and liquid-applied waterproofing covers the coatings.
How is a black tank different from a white tank?
The two systems put the water barrier in different places. In a black tank the barrier is the sealing layer. In a white tank the barrier is the concrete itself.
| Aspect | Black tank | White tank |
|---|---|---|
| Where the barrier sits | A sealing skin on all sides of the parts to be sealed | The reinforced concrete structure, with a structural and a sealing function |
| Usual materials | Bitumen or plastic sheets, bituminous coatings | Waterproof concrete (WU concrete) with high resistance to water penetration |
| Where care is needed | Transitions, penetrations, movement joints, light wells and protection of the sealing (chapters 9 to 13 of DIN 18533-1) | Joints, reinforcing bars and injection channels |
| Dry rooms | BauNetz Wissen recommends a pressure-resistant, closed-cell insulation layer such as foam glass or XPS for usable rooms | Not absolutely tight because of diffusion, pressure gradient and capillary suction, so extra measures such as external insulation may be needed |
BauNetz Wissen also says the installation of a black tank depends heavily on the weather, which can delay the schedule. Remember that the site is sponsored by the concrete industry, so read its comparisons with that in mind. DIN 18533-1 does not cover watertight (WU) structures. Its scope excludes them. See watertight concrete structure for that system.
Which water loads does DIN 18533-1 use?
The standard sorts the water that acts on a component into four classes. DIN Media lists the loads in its scope, and the free table of contents names the classes.
| Class | Water load |
|---|---|
| W1-E | Soil moisture and non-pressing water |
| W2-E | Pressing water (the table of contents lists W2.1-E and W2.2-E under it) |
| W3-E | Non-pressing water on earth-covered decks |
| W4-E | Splash water at the base of a wall, and capillary water in and under walls |
The class decides which sealing types the standard allows. For a site with pressing water see waterproofing against pressurised groundwater and design groundwater level.
The standard also grades crack movement in the substrate (crack classes) and the use of the room. RN1-E is a low requirement, RN2-E a usual one and RN3-E a high one. A manufacturer's planning guide reproduces the crack classes. R1-E is a crack width change of up to 0.2 mm and R2-E up to 0.5 mm. R3-E is up to 1.0 mm with an offset of up to 0.5 mm. That is the guide's table, dated 15 July 2026. The rule text is paid and this page does not quote it.
What does DIN 18533-1 say about details and protection?
The free table of contents shows that the standard goes beyond the sealing layer. Chapter 9 covers the transitions between floor, wall and ceiling sealing. It includes a wall sealing that meets a base slab built as watertight concrete, and door and window connections. Chapter 10 covers penetrations, including minimum distances. Chapter 11 covers movement joints. Chapter 12 covers light wells and outside stairs.
Chapter 13 covers the protection of the sealing. It lists protective layers of concrete, screed, masonry, mastic asphalt, and foam plastic or foam glass boards. It also lists protective plies and protective measures. Section 4.5.2 of the standard deals with avoiding damage caused by protective layers. The table of contents gives only the topics, so a designer needs the paid text for the rules.
Which DIN 18533 editions are current?
DIN Media lists the 2026-06 editions of Parts 1 and 2 as current. Older catalogue pages may still show the 2017-07 editions as withdrawn. Those editions are the ones the 2026-06 editions replace.
| Edition | Subject | Replaces |
|---|---|---|
| DIN 18533-1:2026-06 | Requirements and principles for design and execution | DIN 18533-1:2017-07 and A1:2018-09 |
| DIN 18533-2:2026-06 | Sealing with sheet-form materials, applied together with Part 1 | DIN 18533-2:2017-07 and A1:2020-11 |
BauNetz Wissen names DIN 18533-3 for liquid-applied sealing. The edition of Part 3 was not checked for this page.
Is DIN 18533 binding in Slovakia?
DIN 18533 is a German standard, not Slovak law. This page uses it only to describe how a black tank is specified. No Slovak standard text was opened for this page. Ask the designer which standard the sealing detail follows and where it is named in the project documentation.
What do people get wrong about black tanks?
- A white tank is not completely dry. BauNetz Wissen says it is not absolutely tight because of diffusion, pressure gradient and capillary suction.
- DIN 18533-1 does not cover every basement. Its scope excludes watertight (WU) structures and the determination of below-grade actions such as uplift protection.
- The brown tank is not a colour variant of the black tank. It is waterproof concrete with bentonite sheets, a different system.
Frequently asked questions
- What is the difference between a black tank and a white tank?
- A black tank keeps water out with a sealing layer on the outside, usually bitumen or plastic sheets or bituminous coatings. A white tank is waterproof concrete that has both a structural and a sealing function. BauNetz Wissen, a site sponsored by the German concrete industry, describes both.
- What is a black tank sealing made of?
- BauNetz Wissen says it is usually bitumen or plastic sheets or bituminous coatings. DIN 18533-1 covers sealing with sheet and liquid-applied materials, so both forms exist.
- Does DIN 18533 cover white tanks?
- No. The scope on the DIN Media page for DIN 18533-1 excludes watertight (WU) structures. A white tank is such a structure.
- Which edition of DIN 18533 is current?
- DIN Media lists DIN 18533-1:2026-06 and DIN 18533-2:2026-06 as current. They replace the 2017-07 editions and the later amendments. The full text is paid.
- What does W2-E mean in DIN 18533-1?
- W2-E is the class for pressing water. The free table of contents lists it with two sub-classes, W2.1-E and W2.2-E. W1-E is soil moisture and non-pressing water.
Sources
- DIN 18533-1:2026-06 Abdichtung von erdberührten Bauteilen, Teil 1: Anforderungen, Planungs- und Ausführungsgrundsätze (Waterproofing of elements in contact with soil, Part 1) · DIN Media (Beuth) · Catalogue page: Ausgabedatum, Ersatzvermerk, Anwendungsbereich
- DIN 18533-1:2026-06 table of contents (Inhaltsverzeichnis) · DIN (NA Bau, free table of contents download) · Chapters 4, 5, 8 to 13
- DIN 18533-2:2026-06 Abdichtung von erdberührten Bauteilen, Teil 2: Abdichtung mit bahnenförmigen Abdichtungsstoffen (Waterproofing with materials in sheet form) · DIN Media (Beuth) · Catalogue page: Ausgabedatum, Ersatzvermerk, Anwendungsbereich
- Was sind Schwarze, Weiße und Braune Wannen? · BauNetz Wissen, Beton section, sponsored by the Deutsche Zement- und Betonindustrie (InformationsZentrum Beton) · Whole article
- Planungs- und Anwendungsratgeber für die Bauwerksabdichtung und Instandsetzung · Schomburg (manufacturer planning and application guide, version dated 2026-07-15) · p. 30, table of DIN 18533 criteria (crack classes R1-E to R3-E)