Liquid-applied waterproofing

Liquid-applied waterproofing is a coating brushed, rolled or troweled onto a substrate under tiles to make it watertight.

What is liquid-applied waterproofing under tiles?

Liquid-applied waterproofing is a coating that is brushed, rolled or troweled onto a substrate before ceramic tiles are bonded with adhesive. It cures into a film with no seams. In Slovak it is called hydroizolačná stierka. A waterproofing membrane is a sheet product and has its own article.

The European standard EN 14891 covers these products. The Slovak catalogue of ÚNMS gives its English title as Liquid applied water impermeable products for use beneath ceramic tiling bonded with adhesives. Requirements, test methods, assessment and verification of constancy of performance, classification and marking. The catalogue lists STN EN 14891 as valid. It is identical with EN 14891:2017. It dates from 1 August 2017 and replaces STN EN 14891:2012-09.

The catalogue entry gives no installation steps. This article takes them from two maker data sheets, Ceresit CL 50 and CL 51.

Which types of liquid waterproofing are there?

The two products below differ in base, and so do their drying and tiling schedules. CL 50 is a two-component product made of cements, mineral fillers and a synthetic resin dispersion. CL 51 is a one-component, ready-to-use dispersion.

ProductBaseUse stated in the sheetKey data from the sheet
Ceresit CL 50Two-component, cement-basedUnder tiles indoors and outdoors, for areas with floor drains, balconies, terraces and poolsPrinted designation CMO2P; bridges cracks in the substrate up to 2.5 mm; at least two coats, each not over 1 mm
Ceresit CL 51One-component, dispersionCoating with no seams under ceramic tiles indoors, in bathrooms, kitchens, toilets, showers and laundriesAt least two coats, about 1.0 mm in total; for showers with a recessed drain channel the sheet recommends CL 50 instead

The Slovak sheet for CL 51 dates from 05/2023. An English sheet from 03/2024 gives a lower minimum total thickness of 0.5 mm and tiling about 2 hours after the second coat. The Slovak sheet gives about 1.0 mm and 4 hours. The English sheet also sends permanently wet areas, such as swimming baths, to CL 50. The schedule therefore depends on the version your supplier sells, so check the sheet that comes with the product.

What do the EN 14891 class letters mean?

The CL 50 sheet prints an EN 14891 label with the designation CMO2P. The label describes a cement-based liquid product that bridges cracks at a very low temperature (-20 °C) and resists contact with chlorinated water. The sheet's test table gives crack bridging of at least 0.75 mm in normal conditions, at -5 °C and at -20 °C.

A declaration of performance from another maker, Köster, for a product designated CM O1, shows the same logic. It states a cement-based product with crack bridging of at least 0.75 mm at -5 °C. The first letters therefore name the product type, and the later letters name optional properties.

The sheets quote different editions. The CL 50 label names EN 14891:2012. The Slovak CL 51 sheet quotes test values to STN EN 14891:2009 and prints no class letters. The 2024 English CL 51 sheet prints the class DMP. The current Slovak edition is the 2017 one. Ask the supplier for the class of your product and the edition of the test.

How many coats are needed, and how long do they take to dry?

Both sheets ask for at least two coats, put on crosswise. Each coat must be dry or hardened before the next goes on. CL 50 asks for the first coat with a brush. CL 51 allows a trowel, roller or brush, but the first coat goes on with a trowel or brush. The times below come from the Slovak sheets.

ProductCoatsTotal thicknessBetween coatsTiling
CL 50At least 2Each coat not over 1 mmSecond coat when the first has hardened and changed colour; first coat about 2 hours to dryAbout 5 hours after the last coat, according to the sheet's wall schedule
CL 51At least 2About 1.0 mmSecond coat about 1.5 hours after the firstAbout 4 hours after the second coat

The sheets give a working range of +5 to +25 °C. The stated times apply at +23 °C for CL 50 and at +20 °C for CL 51. Consumption is given per millimetre of dry layer for CL 50, at 1.65 kg/m². For CL 51 the sheet gives about 1.1 kg/m² for two coats. The CL 50 mix is 1.5 parts of powder to 1 part of liquid by weight. Its working time is about 1 hour.

How thick must a CL 50 layer be on a balcony, terrace or pool?

The CL 50 sheet gives a minimum dry thickness that rises with the water load. The thickness for each use is in the table. The sheet also asks for a fall of at least 2.5 % on exterior surfaces, so that no puddles form.

UseMinimum dry thicknessConsumption
Balconies and loggias, protection against moisture1.4 mmAbout 2.3 kg/m²
Terraces, and protection against pressurised water2.0 mmAbout 3.3 kg/m²
Pools and water tanks2.5 mmAbout 4.1 kg/m²

The sheet also gives 2.0 mm for protection against ground moisture or non-pressurised water. It says CL 50 may isolate a substrate only from the side the moisture acts on. The CL 51 sheet likewise asks to exclude moisture from the back, from the substrate side.

How are corners, movement joints and the drain sealed?

Both Ceresit sheets ask to reinforce the coating at movement and connection joints with a sealing tape, CL 82 or CL 152. The CL 152 tape is 120 mm wide. It is pressed into the fresh first coat without air gaps and covered by the second coat. At a movement joint it is formed into a loop in the corner, which the sheet says helps to bridge movement in the substrate.

At a drain, the CL 51 sheet points to CL 50 for a shower with a recessed channel, so the drain type decides the product. A shower channel drain is covered in its own article. The tray-free shower article covers the floor fall and the drain joint.

What condition should the substrate be in before coating?

The CL 51 sheet asks for a dry, firm, clean and stable surface, free of fats, dust and dirt. It asks to remove existing paint and weakly bonded coats. The surface should be even, without deep cracks. Dusting and absorbent substrates get a Ceresit CT 17 primer, which must dry for at least 2 hours.

The CL 51 sheet gives these residual moisture limits in % CM:

  • Concrete older than 3 months: 4 % CM.
  • Lime-cement plaster older than 28 days: 4 % CM.
  • Gypsum substrates thicker than 10 mm: 1 % CM.
  • Anhydrite: 0.5 % CM, and 0.3 % CM with underfloor heating.

The CL 50 sheet gives 4 % CM for cement substrates, 0.5 % for anhydrite and 1 % for gypsum. The limits are the maker's and differ by product, so the sheet for the chosen product governs the job.

Which mistakes happen most often?

  • One thin coat. Both sheets ask for at least two coats crosswise, and the stated total thickness is the target to check against.
  • Second coat too early. The second coat goes on only when the first is dry (CL 51) or hardened (CL 50).
  • No tape at the joints. Both sheets ask for tape at movement and connection joints, laid between the two coats.
  • Tiling on the wrong schedule. Use the times of the product you bought. The 2024 English CL 51 sheet differs from the 2023 Slovak one.
  • Moisture from behind. Both sheets ask to keep moisture from reaching the coating from the substrate side.
  • Heating switched on too early. With a cement screed and underfloor heating, the CL 50 sheet says to switch the heating on no sooner than 7 days after application.

Frequently asked questions

Can liquid waterproofing go under tiles in a shower without a tray?
Yes, if the product sheet allows it. For a shower with a recessed channel drain, the Ceresit CL 51 sheet recommends CL 50 instead of CL 51. The tray-free shower article covers the floor fall and the drain joint.
How many coats of liquid waterproofing are needed?
At least two for both CL 50 and CL 51. The Slovak CL 51 sheet gives about 1.0 mm in total. The CL 50 sheet says no single coat should be thicker than 1 mm. Each coat goes on crosswise after the previous one has dried or hardened.
How long after liquid waterproofing can you tile?
It depends on the product. The Slovak CL 51 sheet gives about 4 hours after the second coat, and its 2024 English sheet gives about 2 hours. The CL 50 sheet gives about 5 hours after the last coat for walls. Check the sheet of the product you bought.
Does liquid waterproofing need sealing tape at the joints?
Both the CL 50 and CL 51 sheets call for sealing tape in movement and connection joints. The Ceresit CL 152 tape is 120 mm wide. It is pressed into the fresh first coat and covered by the second.
Can liquid waterproofing be used with underfloor heating?
Yes, the CL 50 and CL 51 sheets both allow it on heated screeds. For CL 50 on a cement screed, the sheet says to switch the heating on no sooner than 7 days after the waterproofing is applied.
What does the class CMO2P on a waterproofing mean?
It is the EN 14891 designation printed on the Ceresit CL 50 sheet. The sheet describes a cement-based liquid product that bridges cracks at -20 °C and resists chlorinated water. Ask the supplier for the class of the product you buy.

Sources

  1. Ceresit CL 50 Express 2-K, dvojzložková elastická hydroizolácia pod obklady a dlažbu, technický list · Henkel Slovensko, spol. s r.o. · Oblasti použitia; Príprava podkladu; Spracovanie; Technické údaje; EN 14891 label (09/2015 sheet)
  2. Ceresit CL 51 Express 1-K, jednozložková elastická hydroizolácia pod obklady a dlažbu v interiéri, technický list · Henkel Slovensko, spol. s r.o. · Oblasti použitia; Príprava podkladu; Spracovanie; Technické údaje; platný od 05/2023
  3. Ceresit CL 51 Express 1-K, fast drying flexible dispersion-based waterproofing film, technical data sheet · Henkel Slovensko, spol. s r.o. · Scope of use; Substrate preparation; Application; Technical data; CERESIT_CL51_TDS_03_2024
  4. Ceresit CL 152 Izolačný pás, technický list · Henkel Slovensko, spol. s r.o. · Oblasti použitia; Spracovanie; Neprehliadnite; CERESIT CL 152_TDS_1_0217
  5. STN EN 14891 Tekuté hydroizolačné membrány na použitie pod keramické obkladové prvky (English title: Liquid applied water impermeable products for use beneath ceramic tiling bonded with adhesives - Requirements, test methods, assessment and verification of constancy of performance, classification and marking) · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR · Catalogue entry
  6. KÖSTER NB 4000 declaration of performance No W 236 (DIN EN 14891 CM O1) · KÖSTER BAUCHEMIE AG · Points 1, 3 and 8