Pre-applied membrane

A pre-applied membrane is a waterproofing sheet laid before concreting, so it bonds to the fresh concrete as a basement wall or slab is poured.

What is a pre-applied membrane and where does it go?

A pre-applied membrane is a flexible waterproofing sheet that the contractor lays before the reinforcement and the concrete. The concrete is then poured against the sheet. The sheet bonds to the fresh concrete, so the membrane and the structure form one layer. Manufacturers place it below slabs and behind basement walls. For the sheet material in general, see waterproofing membrane.

The GCP data sheet for its PREPRUFE 300R and 160R membranes says the sheets form an integral bond to poured concrete. GCP says the bond is designed to prevent lateral migration of water. That means water moving sideways between the sheet and the concrete (data sheet last updated 2019-02-21). The Sika data sheet for SikaProof A+ 08 lists the same property: no lateral water migration between concrete and membrane (file version 3.0, 29/08/2023).

How does a pre-applied membrane differ from a post-applied one?

The difference is timing. A pre-applied sheet goes down before the concrete. A post-applied sheet goes onto concrete that is already cast. Sika sells one sheet for both uses and lists a different set of system products for each.

AspectPre-applied (Sika system)Post-applied (Sika system)
Products in the systemSikaProof A+ 08, SikaProof Tape A+ and SikaProof Sandwich TapeSikaProof Primer-02, SikaProof Adhesive-02, SikaProof A+ 08 and SikaProof ExTape-100

Sika lists these products in the system structure of its data sheet. GCP adds one rule for pre-applied work on vertical walls. Its sheets should not be used with conventional twin-sided formwork, because the concrete must be cast directly against the adhesive side of the sheet.

What do the manufacturer data sheets state?

Product values come from the manufacturer and apply to one product only. The table shows values from the Sika SikaProof A+ 08 data sheet, with the test standard that the sheet cites. Sika says its data are based on laboratory tests and may vary.

PropertySika valueTest standard cited
Total thickness1.35 mm (+0.14 / -0.07)EN 1849-2
Membrane thickness0.80 mm (+0.08 / -0.04)EN 1849-2
Mass per area1.20 kg/m2 (+0.12 / -0.06)EN 1849-2
Peel adhesion to concrete after 28 daysAt least 80 N per 50 mmDIN EN 1372
Joint shear resistanceAt least 100 N per 50 mmEN 12317-2
Watertightness, 24 h at 60 kPaPassEN 1928, method B
Resistance to lateral water migrationPass, up to 7 barASTM D5385

The Sika sheet is a polyolefin (FPO) membrane with a cement-modified hybrid bonding layer. Its CE marking and declaration of performance are based on EN 13967:2012. BSI lists the current version as BS EN 13967:2012+A1:2017. The title is Flexible sheets for waterproofing: Plastic and rubber damp proof sheets including plastic and rubber basement tanking sheet. Definitions and characteristics. The GCP product is a different build: an HDPE film with a pressure-sensitive adhesive. The product data sheet governs the installation of each product.

How does the installation work before concreting?

The data sheets set the rules, and they differ between products. The points below come from the GCP PREPRUFE 300R and 160R data sheet, except where Sika is named.

  • The substrate must be regular and smooth, with no gaps or voids greater than 12 mm.
  • Sheets overlap by at least 75 mm. The underside of the overlapping sheet must be clean and dry. Tape goes centred over lap edges and cut edges.
  • The release liner comes off before reinforcement and concrete are placed, and before any tape goes on.
  • GCP gives -4 °C or above as the application temperature. Below 13 °C, GCP requires its low-temperature tape at all laps and details.
  • Sika gives +5 °C as the minimum ambient and substrate temperature for SikaProof A+ 08.
  • Concrete should be poured within 56 days of installing the membrane, or within 42 days in hot climates (GCP).
  • Sika says its sheet does not resist permanent UV exposure or weathering. It asks the contractor to protect the sheet as soon as possible and not later than 90 days after application.

GCP also describes the checks before the steel goes in. The contractor inspects the membrane before placing reinforcement, formwork and concrete. A puncture of 12 mm or less is covered with tape. A larger hole gets a membrane patch that extends 150 mm beyond the damage, with its edges taped.

What happens after the concrete is poured?

GCP recommends a concrete compressive strength of at least 20 N/mm2 before stripping formwork that supports its membranes. Early stripping can displace the membrane or spall the concrete. After the formwork is removed and before backfilling, GCP requires an approved protective course over all exposed membrane. With the GCP sheets, a wall face that stays exposed after stripping therefore still needs protection from the backfill.

The GCP data sheet states that it is valid only for use in the United States and expands its references to the Americas. A project in Slovakia needs the local data sheet of the product chosen. The same holds for Sika, which says its declared data and recommended uses vary from country to country.

Which waterproofing route suits a basement with a pre-applied membrane?

The sheet is one route among several. The choice depends on the ground and water conditions at the site. Start from the design groundwater level, because it shows whether the wall meets damp soil or water under pressure. Where water presses on the structure, see pressure water waterproofing.

The black tank, bentonite and crystalline routes each have their own page. This page does not compare them, because the comparison needs sources for each route.

Frequently asked questions

Does a pre-applied membrane need a protection layer before backfilling?
For the GCP PREPRUFE sheets, yes. The data sheet requires an approved protective course over all exposed membrane after the formwork is removed and before backfilling. Other products have their own rules, so check the data sheet.
What standard covers plastic and rubber waterproofing sheets?
EN 13967 covers flexible plastic and rubber sheets, including basement tanking sheets. It gives definitions and characteristics. BSI lists the current version as BS EN 13967:2012+A1:2017. Sika bases the CE marking of SikaProof A+ 08 on EN 13967:2012.
How wide must the laps be on a pre-applied membrane?
GCP requires a minimum overlap of 75 mm for its PREPRUFE 300R and 160R sheets, with tape centred over the lap edges. Other products set their own lap rules. The data sheet of the chosen product governs.
What is the lowest temperature for installing a pre-applied membrane?
GCP gives -4 °C or above for its PREPRUFE 300R and 160R membranes. Below 13 °C it requires its low-temperature tape at all laps. Sika gives +5 °C as the minimum for SikaProof A+ 08.
How long can the membrane wait before the concrete is poured?
GCP recommends pouring concrete within 56 days of installing the membrane, or 42 days in hot climates. Sika says SikaProof A+ 08 needs protection not later than 90 days after application because it is not resistant to permanent UV exposure.
How thick is one pre-applied sheet?
The Sika SikaProof A+ 08 data sheet gives a total thickness of 1.35 mm, of which the membrane is 0.80 mm. The mass is 1.20 kg/m2. Thickness and mass differ between products.

Sources

  1. Flexible sheets for waterproofing. Plastic and rubber damp proof sheets including plastic and rubber basement tanking sheet. Definitions and characteristics (BS EN 13967:2012+A1:2017) · BSI (British Standards Institution), knowledge portal · Scope
  2. SikaProof A+ 08 product data sheet, file version 3.0 (29/08/2023) · Sika · Description, product information, technical information, system information, application information, important
  3. PREPRUFE 300R and 160R membranes, product data sheet (last updated 2019-02-21) · GCP Applied Technologies · Product description, limitations of use, temperature requirements, substrate preparation, membrane application, membrane repair, pouring of concrete, removal of formwork