An injection hose is a perforated hose cast into a concrete joint and filled later with injection resin or grout to seal a leak.

What is an injection hose?

An injection hose is a perforated hose that a contractor lays along a construction joint before the second concrete pour. The new concrete then encloses it. If the joint leaks, a specialist pumps an injection material through the hose to seal the joint. The hose is a service channel inside the structure. It is not a waterproofing layer on the wall surface.

Sika, a manufacturer, describes its hose system in the same way. Its method statement says the system is cast into the concrete and is ready for injection when the concrete reaches its final strength. Sika says it is typically used in construction joints. It also serves as a back-up system with other joint sealing systems such as waterbars (Method Statement, SikaFuko VT System, version 5, 4 January 2022).

How does an injection hose work in a construction joint?

The system works in two stages. The first stage happens during construction and the second only if a leak needs sealing.

  1. The contractor assembles the hose with vent ends and attaches it continuously on the concrete surface of the first pour. Sika uses plastic clips in 6 mm drilled holes, or alternatively shooting nails.
  2. The vent ends run to junction boxes at the formwork face. Each vent end is closed with a plug before concreting.
  3. The contractor places the second pour. The outer layer of the hose keeps cement paste out of the hose during concreting (Sika SikaFuko Eco-1 data sheet).
  4. When the concrete reaches its final strength, the applicator connects a pump to one vent end. The pump runs until the material flows out of the opposite vent end. The applicator then closes that end and pumps again at the lowest possible pressure.

Sika states that slow, low-pressure injection is more effective than rapid, high-pressure injection. The injection is complete when the pump refuses more material or the material seeps out along the joint. The applicator then holds the pressure for about 1 to 2 minutes.

What does one manufacturer state about its injection hose?

The table lists values from the Sika data sheet for SikaFuko Eco-1 (May 2026, version 01.02) and its method statement. They are product values for one hose. Sika says its data come from laboratory tests and that measured data may vary. Another product can differ.

PropertySika statement
ConstructionWhite perforated PVC spiral core with a foamed plastic outer layer
Internal diameter6 mm
Test pressureTested in water pressures up to 10 bar (100 m)
Section lengthStandard section of 10 m, including the vent ends
Intended useConstruction joints in watertight concrete structures, also as a back-up for waterbars
Not intended forExpansion or movement joints

Can an injection hose be injected more than once?

It depends on the injection material. Sika states that its acrylate resins and cement suspensions allow re-injection. Its polyurethane and epoxy materials do not. After an acrylate or cement injection, the applicator flushes the hose with water by vacuum. The hose is then ready for a later injection. After a polyurethane or epoxy injection, no cleaning and no re-injection is possible.

Sika injection materialBase and characterRe-injection
Injection-306 and 307Acrylate, low viscosity, flexiblePossible
Injection-190 GBCement suspension, rigidPossible
Injection-201 CEPolyurethane, low viscosity, flexibleNot possible
Injection-458Epoxy, low viscosity, rigidNot possible

The method statement also describes a check. After injection and cleaning, the applicator flushes the joint with water at low pressure. If water flows out of the joint, re-injection is necessary.

How is an injection hose different from a water-stop strip?

A water-stop strip is a separate element that sits in the joint. Sika presents its injection hose as a back-up system in combination with waterbars. The German Concrete Association (DBV) publishes one leaflet for injection hose systems and swellable sealing strips. Its edition is December 2020. The DIN Media catalogue page lists its title and edition. The leaflet text is paid and was not read for this page.

Which standard governs the design of the joint?

Sika describes its hose for construction joints in watertight concrete structures. The German standard DIN 18533-1, edition June 2026, covers waterproofing of elements in contact with soil. Its scope text says it does not apply to watertight (WU) structures. This page did not find a Slovak or German standard that sets rules for the hose itself. The product data sheet and the method statement are therefore the working documents. A watertight concrete structure and its joints are part of the structural design.

What should be checked on site?

The Sika method statement lists an inspection procedure. The points below come from it and from the data sheet. They apply to the Sika system, so check the documents of the product the project uses.

  • The concrete surface must be clean and free of loose material before the hose is installed and the concrete is placed.
  • The hose needs joint contact along its entire length.
  • Hoses must not cross each other.
  • Only the vent ends may be visible after concreting. The hose itself must not be visible.
  • Vent ends are tied with cable binders and not with wire, because wire can block or damage the hose.
  • Areas next to the joint with honeycombing or poor compaction must be repaired before injection, with repair material approved by the structural engineer. Otherwise a large part of the injection material can be lost.
  • Before injection, the applicator tests the cure time of a small sample of the injection material, because temperature changes the working time.

The method statement also says that a qualified supervising officer or specialist must direct the work. It says the statement must be adapted to local products, standards and legislation. A joint at the base of a wall is described on the foundation joint page.

Frequently asked questions

What is an injection hose used for?
An injection hose is a perforated hose cast into a construction joint. If the joint leaks, a specialist pumps injection resin or cement suspension through the hose to seal the joint. Sika describes it as a seal for construction joints and a back-up for waterbars.
Is an injection hose the same as a water-stop strip?
No. A water-stop strip is a separate element in the joint. Sika presents its injection hose as a back-up system used together with waterbars. The hose is injected only if a leak needs sealing.
When is an injection hose injected?
Sika states that injection starts only when the concrete has reached its final strength. The applicator pumps at low pressure until the material flows out of the opposite vent end, then pumps again until the pump refuses more material.
Can an injection hose be injected more than once?
Only with some materials. Sika states that acrylate resins and cement suspensions allow re-injection after the hose is flushed. Polyurethane and epoxy materials do not. Check the data sheet of the product in use.
Can an injection hose seal an expansion joint?
No, not according to Sika. Its data sheet for SikaFuko Eco-1 says not to use the hose for sealing expansion or movement joints. It is intended for construction joints.
Which German document covers injection hose systems?
The German Concrete Association (DBV) leaflet on injection hose systems and swellable sealing strips for construction joints, edition December 2020. DIN Media lists its title and edition. The leaflet text is paid, so this page does not quote it.

Sources

  1. Leaflet: Injection hose systems and swellable sealing strips for construction joints (Merkblatt Injektionsschlauchsysteme und quellfähige Einlagen für Arbeitsfugen) · DIN Media (technical rule catalogue), issued by the German Concrete Association (DBV) · catalogue page: title, status, edition
  2. DIN 18533-1: Waterproofing of elements in contact with soil - Part 1: Requirements and principles for design and execution · DIN Media (DIN standards catalogue) · Anwendungsbereich (scope), Ersatzvermerk
  3. SikaFuko Eco-1 product data sheet, May 2026, version 01.02 · Sika (Sika Singapore) · Description, uses, characteristics, product information, important considerations
  4. Method Statement: SikaFuko VT System, version 5, 4 January 2022 · Sika UK · System description, installation, working procedure (concreting, injection, vacuum cleaning), application limitations, inspection and quality control