A listed house, or a house in a heritage zone, is renovated under the same building act as any other house. One more authority comes first: the regional monuments office (krajský pamiatkový úrad). It decides before the design is finished, and its conditions limit what the design can contain. This page follows Act 49/2002 on the protection of the heritage fund and Act 25/2025, the building act, as in force on 11 November 2026.
What is the difference between a listed house, a heritage zone and a protection zone?
They are three separate statuses with separate rules in Act 49/2002. A listed building (kultúrna pamiatka) is a thing of heritage value. The Monuments Board of the Slovak Republic declares it a monument (§ 2 ods. 3). A heritage area (pamiatkové územie) is a reservation or a heritage zone (§ 2 ods. 4). A reservation has a large concentration of immovable monuments (§ 16 ods. 1). A zone has a historic settlement layout (§ 17 ods. 1). A protection zone (ochranné pásmo) is set around a monument, reservation or zone to protect its surroundings (§ 18 ods. 1).
One house can have more than one status. The register notes whether a listed building stands in a reservation, a zone or a protection zone (§ 22 ods. 4 písm. a). Nobody may build within 10 metres of an immovable monument, or do anything else there that could endanger its heritage values. The distance runs from the outer wall of the building (§ 27 ods. 2).
| Aspect | Listed building | Unlisted house in a reservation or zone | Unlisted house in a protection zone |
|---|---|---|---|
| Answer of the regional office before work | Decision on the renewal intent (§ 32 ods. 2) | Decision on the intent to modify the property (§ 32 ods. 5) | Binding opinion on the intent to modify the property (§ 32 ods. 11) |
| What the office sets | Whether the intent is acceptable, the conditions, and whether research and documentation must come first (§ 32 ods. 4) | Whether the intent is acceptable and the conditions, in particular massing, height and exterior (§ 32 ods. 7) | Whether the intent is acceptable and the conditions, in particular massing, height and exterior (§ 32 ods. 11) |
| Binding opinion on the documentation | Yes, on each preparatory and design document (§ 32 ods. 10) | Yes, on each preparatory and design document (§ 32 ods. 10) | Not named in § 32 ods. 10, which covers renewal and heritage areas |
| Duty of the owner | Keep the monument in good condition at own cost, and report any planned change of use (§ 28 ods. 2 písm. a, ods. 3 písm. b) | Use the property so that heritage values are not endangered (§ 28 ods. 4 písm. b) | Use the property so that heritage values are not endangered (§ 28 ods. 4 písm. b) |
How do you find out what status a house has?
Ask the regional monuments office and check the central list. The Monuments Board keeps the central list (ústredný zoznam) in four registers: movable monuments, immovable monuments, reservations and zones (§ 22 ods. 1 a 2). Each regional office keeps the list of the heritage fund in its district (§ 22 ods. 6). Owners may ask the regional office for free expert advice. This applies to listed buildings and to unlisted houses in a reservation, zone or protection zone (§ 28 ods. 1 písm. a, ods. 4 písm. a).
Do this before buying. The owner of a monument must tell the other party to a transfer that the monument regime applies (§ 28 ods. 2 písm. c). The owner must also offer the monument to the state in writing before selling it. The state has 60 days to accept (§ 23 ods. 1 a 4). The owner reports every change of ownership of a monument within 30 days. The report goes to the regional office and the municipality (§ 28 ods. 3 písm. c). The post on buying an old house covers the rest of the purchase check.
Who do you talk to first, the building office or the monuments office?
The regional monuments office comes first. It is the first-instance authority in heritage matters (§ 11 ods. 1). Before renewal of a listed building the owner must ask it for a decision on the renewal intent (§ 32 ods. 2). The request includes the renewal intent: identity of the monument, ownership data, planned future use and the expected changes (§ 32 ods. 3). For an unlisted house in a heritage area the intent covers property data and planned use. It also covers the expected changes of area and space (§ 32 ods. 5 a 6). Demolition is not a modification of property in this sense (§ 32 ods. 5).
If an owner starts without a final decision, the office opens proceedings. It tells the owner to stop work until it decides (§ 32 ods. 2 a 5). Its decisions and opinions together form what the glossary calls heritage authority consent. The binding opinion is a separate act from the decision. The general administrative procedure law does not apply to binding opinions (§ 44 ods. 5).
What is the order of steps?
Heritage steps run before and alongside the building act steps. The table follows § 32 of Act 49/2002.
| Step | What happens | Source |
|---|---|---|
| 1 | Check the status and ask the regional office for advice | § 28 ods. 1, 4 |
| 2 | Submit the intent. The office decides whether it is acceptable and on what conditions | § 32 ods. 2 to 7 |
| 3 | Commission the research the decision requires | § 32 ods. 4, 7, § 39 ods. 1 |
| 4 | Design by an authorised person, discussed with the office while it is prepared and again after every change | § 32 ods. 8, 9 |
| 5 | Submit the preparatory and design documentation. The office issues a binding opinion on each | § 32 ods. 10 |
| 6 | Do the building act step, with the office as an affected authority | § 32 ods. 12 |
| 7 | Build under state monument supervision and tell the office the start and planned end in advance | § 32 ods. 4, 7, 13 |
| 8 | For a listed building, hand over the documentation of the renewal as done, free, within 15 days after the work ends | § 32 ods. 15 |
The design may be prepared only by a person authorised under Act 138/1992 (§ 32 ods. 8). Decisions on the renewal intent and on the modification intent lose validity three years after they become final if nothing was done under them. A binding opinion loses validity three years after issue if it was not used for its purpose (§ 44a).
Do you need a building intent decision or only a notification?
It depends on the work, and the heritage rules apply on top. Act 25/2025 has no building permit. It requires a decision on the building intent for each structure, change of a completed building, demolition and building alterations. The act names exceptions (§ 18 ods. 2). A change of a completed building is an extension (prístavba), a raising (nadstavba) or an insert into its volume (vstavba) (§ 5 ods. 1).
A notification replaces the decision for an alteration of a listed building or a building in a heritage area (§ 18 ods. 3 písm. f, g). Maintenance of a listed building also needs a notification (§ 18 ods. 4 písm. d). Other maintenance needs neither. Examples are facade repair, roof covering and replacement of windows and doors (§ 18 ods. 5 písm. a). One exception applies. The work needs a notification if it could affect stability, fire safety or the environment. The same holds for the look of the building in public space (§ 18 ods. 4 písm. c). From 1 January 2027 Act 243/2026 changes the heritage rule. A notification for an unlisted house in a heritage area is then needed only if the works change the exterior (Čl. I body 61, 62, Čl. XV).
The heritage act applies in any case. Even where the building act asks for nothing, an unlisted house in a heritage area still needs the regional office's decision (§ 32 ods. 5). Even for a notification the building office must ask the regional office for its opinion (§ 32 ods. 12). The notification includes the binding opinions of affected authorities (25/2025 § 63 ods. 2). The office verifies the project within 30 days, and only if the binding opinions agree (§ 63 ods. 6). The procedure is described in the post on timelines under the building act.
An affected authority has 30 days to issue a binding opinion to the building intent, or 60 days for a complex structure. If it stays silent, the act presumes no comments (§ 21 ods. 9). Act 49/2002 contains no presumption for its own decisions, so a missing decision of the regional office is not an approval.
What do investigations involve, and who pays?
Heritage research (pamiatkový výskum) is expert work that collects knowledge about a monument or a heritage area. It prepares renewal and restoration of monuments and modifications of property in heritage areas (§ 35 ods. 1, 2). The four kinds are art-historical, architectural-historical, urban-historical and archaeological (§ 35 ods. 3). The regional office decides the kind, scope and method (§ 39 ods. 1). The owner of the monument, the owner of the property in a heritage area or the builder pays for it (§ 38 ods. 1).

Restoration (reštaurovanie) is a special kind of renewal with its own decision on the restoration intent (§ 33 ods. 1, 2). Only the qualified persons named in § 33 ods. 7 may do it, for example members of the Chamber of Restorers. If work uncovers an unexpected find, the person doing the work must report it and stop the work that endangers it. The regional office decides how to proceed within three working days of the report (§ 32 ods. 14). The site manager must also record the find in the site diary (25/2025 § 44 ods. 1).
What can the monuments office decide about windows, insulation and extensions?
Act 49/2002 bans no measure by name. It lets the office set conditions case by case. For an unlisted house in a heritage area it names massing, height and the architecture of the exterior (§ 32 ods. 7). For a listed building the conditions aim to keep the monument from being endangered, damaged or destroyed (§ 32 ods. 4). Facade insulation, window replacement, roof changes and extensions are therefore all questions for the office's decision on the specific house. No published rule answers them in advance.
The energy rules bend to this. The requirements of Act 555/2005 do not apply to buildings protected for architectural or historical value where compliance would unacceptably change their character or appearance. The act lists three examples: monuments, buildings in a reservation or zone, and buildings in use before 1 January 1947 (§ 2 ods. 2 písm. a, ods. 4). From 1 January 2027 Act 246/2026 adds a rule for a building protected as part of a zone or reservation, or for exceptionally valuable architecture. Its renovation proposes only measures that meet the minimum requirements. They must not unacceptably change its appearance or heritage value (Čl. I bod 23, Čl. IV).
Which measures to choose, and in which order, is a design question outside the heritage act. The posts on facade insulation, window replacement and the order of measures in a deep renovation cover them. A deep renovation of a protected house still starts with the regional office's decision.
Can Obnov dom or other aid pay for it?
Possibly. Call 26-MFOD-V01 of the Obnov dom mini+ programme pays up to 11 000 EUR per house. The house must be built before 2016 and be registered as a family house on the ownership sheet. The sheet must show no note or encumbrance that restricts rights to the property. The call text does not mention heritage status, so ask the operator whether it matters. The call closes on 31 December 2026 or when its allocation is spent, so check the current round. The Obnov dom guide has the details.
Act 49/2002 has its own route. An owner who cannot pay for the renewal or restoration may ask the Ministry of Culture and the municipality for a contribution (§ 34 ods. 1). There is no legal claim to it. The request includes the regional office's decision on the renewal intent, and for the ministry also the municipality's statement (§ 34 ods. 2). The ministry may require repayment if the monument is sold for payment within ten years (§ 34 ods. 3).
What happens if work starts without the office's consent?
The office stops the work and may fine the owner. It can stop work that endangers heritage values or breaks its decision. An appeal does not suspend the stop (§ 32 ods. 13). A private person who renews a monument without a decision or binding opinion can be fined up to 200 000 EUR. For an unlisted house in a heritage area or protection zone the fine is up to 100 000 EUR. It applies to building or maintenance work without the decision or binding opinion (§ 42 ods. 1 písm. h, p, ods. 2). A business or legal person faces higher maximum fines (§ 43 ods. 2). The office can also order the owner to repair the damage at his own cost (§ 31 ods. 1).
What drives the cost, and how big should the reserve be?
The act creates cost items but gives no amounts. They are research paid by the owner (§ 38 ods. 1), an authorised designer (§ 32 ods. 8), qualified restorers (§ 33 ods. 7) and stops for finds (§ 32 ods. 14). No source opened for this page gives a percentage for a heritage reserve, so none is quoted. Agree a figure with your architect after the investigations, when the unknowns are smaller. The post on budget overruns and the reserve explains how to set one.