Road and traffic authority opinion

A road authority binding opinion is the opinion that protects a public road when a planned building adds or changes a road connection.

What is a traffic authority approval?

A road authority binding opinion is the binding opinion that the road authority issues to protect a public road when a building connects to it.

People search for it as traffic authority approval or vyjadrenie dopravného inšpektorátu. The acts give the binding opinion to the road authority (cestný správny orgán), not to the police traffic inspectorate. In the proceeding on the building intent, the road authority has the status of an affected authority (§ 3b ods. 3 of the road act 135/1961 Zb.). It applies its competence to protect the road by a binding opinion.

Up to three documents can be involved when a building touches a road.

  • The binding opinion of the road authority (§ 3b ods. 3 of the road act).
  • The opinion of the road administrator (správca) and the opinion of the traffic inspectorate (dopravný inšpektorát). The road authority uses both when it decides on the connection (§ 3b ods. 4).
  • The binding statement of the owner, administrator or operator of a transport infrastructure structure. This is an affected legal person under § 22 ods. 1 písm. a) of the Building Act 25/2025 Z. z.

The acts read for this page do not say whether the administrator opinion and the binding statement are one document. The general rules for the opinion are on the binding opinion page.

When does a building need a road authority opinion?

The road authority decides on the connection of roads and on driveways from a road or a local road to neighbouring property. It also decides on changes and on cancellation of such connections. It acts with regard to the protection of the road and the safety of traffic on it (§ 3b ods. 1).

Sometimes the connection relates to the location of a building or to the use of land. Then the decision is part of the proceeding on the building intent (§ 3b ods. 3). The act ties the opinion to a connection or a driveway. It gives no list of building types.

Motorways are different. Driveways and exits from a motorway to adjacent property are prohibited. Connections of purpose roads (účelové cesty) are prohibited too. The exceptions are roads that serve motorway maintenance or rest area facilities (§ 3b ods. 2).

Who is the road authority?

It depends on the class of the road.

RoadRoad authoritySource
MotorwayThe ministry§ 3 ods. 3 písm. g)
Class I roadThe district office in the seat of the region (okresný úrad v sídle kraja)§ 3 ods. 4 písm. a)
Class II and III roadThe district office (okresný úrad)§ 3 ods. 5 písm. a)
Local road and purpose roadThe municipality, as transferred state administration§ 3 ods. 2

The table follows the road act 135/1961 Zb. in the version from 1 September 2026.

What does the police traffic inspectorate do?

Under § 3b ods. 4, the road authority decides on a connection on the basis of two opinions. They are the opinion of the road administrator and the opinion of the traffic inspectorate. The inspectorate issues its opinion within its competence under special regulations. For motorways the opinion comes from the Ministry of Interior. The footnote of the paragraph names the road traffic act 8/2009 Z. z. and decree 9/2009 Z. z. as examples of those regulations.

The same two opinions are the basis for traffic signs and reserved parking spaces on roads (§ 3 ods. 7).

The road traffic act 8/2009 Z. z. names the police in a building procedure in one place. Section 140a makes the police body the affected authority for an information structure (informačná konštrukcia) that affects the safety and flow of traffic. For a motorway it is the Ministry of Interior. That section still uses the names of the 1976 procedures. Section 84 ods. 11 of the Building Act maps them to the current ones.

The text of the act 8/2009 Z. z. read for this page has no rule that gives the inspectorate a binding opinion on a driveway. The competence of the inspectorate itself sits in a regulation not read for this page.

Does a road administrator also give a statement?

The Building Act makes the owner, administrator or operator of a transport infrastructure structure an affected legal person (§ 22 ods. 1 písm. a)). Such a legal person must give the data and information needed for the building intent. It must also issue a binding statement with concrete requirements for the project (§ 22 ods. 3).

The period is 30 days from delivery of the request, or at most 60 days for complex structures. If the legal person does not issue the statement in time, the act presumes no comments and no justified requirements (§ 22 ods. 5).

What about the road protection zone?

Outside the built-up area of a municipality, road protection zones protect roads and traffic. An implementing regulation sets their width. It is 50 to 100 m from the axis of the adjacent carriageway for motorways and higher-class roads. It is 15 to 25 m for lower-class roads and local roads (§ 11 ods. 1).

For a new or rebuilt road the zone starts when the decision on the building intent becomes final. Activity that could endanger the road or traffic is prohibited or limited in the zone. The road authority grants exceptions by binding opinion (§ 11 ods. 2). See also road protection zone.

How many days does the road authority have?

Section 21 ods. 9 of the Building Act sets the periods for an affected authority. The table shows them with the effect of silence. The building permit timeline page shows the other deadlines.

StepPeriod or effectSource
Binding opinion of an affected authority30 days from delivery of the request, or 60 days for complex structures. The authority must tell the applicant which one applies§ 21 ods. 9
No binding opinion in timeThe act presumes no comments and no requirements on the content of the building intent, unless a special regulation says otherwise§ 21 ods. 9
Compliance declaration on the project30 days from delivery of the request, or 60 days for complex structures§ 24 ods. 2
No compliance declaration in timeThe act presumes that the requirements of the binding opinion are met and that a consenting declaration was issued§ 24 ods. 3
Builder's objection to an opinion15 days from delivery, to the competent superior authority of the affected authority§ 21 ods. 13
Date of the final inspectionThe office announces it within 7 working days of a complete proposal. The inspection takes place within 30 days of the announcement§ 66 ods. 3

Section 3b of the road act sets no period of its own. This page found no period for the opinion of the traffic inspectorate. Section 3b ods. 3 adds that the general rules on administrative proceedings do not apply to the binding opinion.

Does the final inspection check the access?

Yes. At the inspection the office checks that the building is finished. This includes the required adjustments and the access and approach road to the building (§ 66 ods. 4 písm. a)). The builder attaches the binding opinions and statements obtained before the proposal to the final inspection proposal (§ 66 ods. 2 písm. k)).

Section 21 ods. 3 písm. c) of the Building Act lists a binding opinion on the final inspection for every affected authority within its competence. The road act text read for this page gives the road authority a binding opinion only in the proceeding on the building intent.

What can you do if you disagree with the opinion?

The builder can object to the content of the opinion within 15 days of delivery (§ 21 ods. 13). The objection goes to the competent superior authority of the affected authority. A participant other than the builder objects by appeal against the decision on the building intent (§ 21 ods. 15).

What changes from 1 January 2027?

Act 243/2026 Z. z. amends the Building Act and, in Čl. II, the road act (Čl. XV). The 30 and 60 day periods in § 21 ods. 9 stay. New § 24 ods. 5 applies the compliance declaration rules to a change of the project (Čl. I bod 84). The road act version from 1 January 2027 has the same text of § 3b ods. 1 to 4. The text above describes the law in force on 11 November 2026.

Frequently asked questions

Do I need traffic authority approval for my driveway?
If the driveway connects to a road or a local road, the road authority decides on the connection. See § 3b ods. 1 of the road act 135/1961 Zb. When it relates to the location of a building, it is part of the proceeding on the building intent. The road authority then issues a binding opinion (§ 3b ods. 3).
Does the traffic inspectorate give a statement on a driveway?
The road authority decides on a connection on the basis of two opinions. They come from the road administrator and the traffic inspectorate (§ 3b ods. 4 of the road act). The text of the act 8/2009 Z. z. read for this page has no rule that gives the inspectorate a binding opinion on a driveway.
Which authority do I contact for a road connection?
It depends on the road. For a class I road it is the district office in the seat of the region. For a class II or III road it is the district office. For a local road or a purpose road it is the municipality. For a motorway it is the ministry (§ 3 of the road act).
How many days does the road authority have?
The Building Act gives an affected authority 30 days from delivery of the request, or 60 days for complex structures (§ 21 ods. 9). Section 3b of the road act sets no other period. If the authority does not answer, the act presumes no comments and no requirements on the building intent.
Do I also need a statement from the road administrator?
The owner, administrator or operator of a transport infrastructure structure is an affected legal person. It issues a binding statement under § 22 ods. 1 písm. a) of the Building Act. The road authority also uses the opinion of the road administrator (§ 3b ods. 4 of the road act).
Can I connect a driveway to a motorway?
No. Driveways and exits from a motorway to adjacent property are prohibited. Connections of purpose roads are prohibited too. The exceptions are roads that serve motorway maintenance or rest area facilities (§ 3b ods. 2 of the road act).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 20, § 21, § 22 ods. 1 to 5, § 24, § 66 ods. 2 and 4, § 84 ods. 11
  2. Zákon č. 135/1961 Zb. o pozemných komunikáciách (cestný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 3, § 3b, § 11
  3. Zákon č. 8/2009 Z. z. o cestnej premávke a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 140a
  4. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 84, Čl. II, Čl. XV