Neighbour consent
Neighbour consent is a written agreement in which an adjacent owner accepts a building, but Act 25/2025 does not require it.
Does a neighbour have to consent to my building?
Neighbour consent (súhlas suseda) is a written agreement in which the owner of an adjacent plot accepts a planned building. Act 25/2025 Z. z. (the Building Act) does not make the decision on the building intent depend on it. The act does not name it in any of three places where such a rule would sit.
- The application. The builder files the project documentation and the report on the discussion of the building intent (§ 50 ods. 2).
- The checks of the office. It checks the builder's right to the land and the binding opinions and statements. It also checks that the comments of the parties are raised (§ 57 ods. 2).
- The grounds for rejection. They cover conflicts with the planning opinion or the environmental decision, a protected interest, missing access and no possible connection to networks (§ 59 ods. 1).
This page covers Act 25/2025 only. It does not describe the old rules of Act 50/1976. The old name "stavebné konanie" no longer exists. § 84 ods. 11 maps it to the verification of the project (overenie projektu stavby). The zoning proceedings (územné konanie) became the proceedings on the building intent.
Can a neighbour block my project by refusing to sign?
A neighbour cannot stop the decision just by refusing to sign. A neighbour that is a party has other tools. It can raise an objection, appeal the decision and start a dispute over land rights.
The objection must say where the neighbour sees a breach of its rights (§ 52 ods. 4). The office ignores an objection that only aims to harm another person, win an unlawful benefit or cause delay (§ 52 ods. 5). It also ignores one whose grant would breach a law or the binding part of the planning documentation.
When is a neighbour a party to my proceedings?
A neighbour is a party if the decision on the building intent can directly affect its ownership or other rights. These are rights to its plot or building (§ 49 ods. 1 písm. c). A neighbouring plot shares a boundary with your plot. A plot without a shared boundary also counts in one case. Your building or its expected operation must be able to directly affect the present use of that plot or its building (§ 7 ods. 2).
The party to proceedings page lists the other parties and what each can do. The office tells every known party about the start within seven days of the day your application is complete (§ 51 ods. 1).
What if my building needs something from my neighbour's land?
The office checks that you have a right to the land or building where the works will happen (§ 57 ods. 2 písm. a). It stops the proceedings if you have no legal link to that land or building (§ 56 ods. 1 písm. a). The act does not say how you gain a right to a neighbour's land. That comes from an agreement under civil law, which 25/2025 does not cover.
The act has one tool for tight sites. The building office may order the owner of a neighbouring plot or building to allow works from that plot or building (§ 46 ods. 1). The office does this in the decision on the building intent. The order must be necessary, and it lasts only for the necessary time and extent. The neighbour does not sign anything for it.
The person who gains from the order has three duties (§ 46 ods. 2).
- Announce the works in advance.
- Disturb the use of the neighbouring plot or building as little as possible.
- Restore the plot or building afterwards, or pay for the damage.
The easement page explains a right over another plot.
What happens if the neighbour disputes ownership or a right to land?
The office cannot decide disputes over ownership or other rights to land or a building. It first tries to reach an agreement or a settlement of the parties (§ 55 ods. 1). If this fails, it interrupts the proceedings. It asks the party that raised the dispute to file with the court within a period of at most 60 days (§ 55 ods. 2).
A written agreement with a neighbour can therefore help in practice, because it can settle such a dispute before it holds up the proceedings. The act does not require it.
How long do neighbours have to object?
A neighbour who is a party can object at the latest at the hearing (§ 51 ods. 2). If the office orders no hearing, the time is at least seven working days from delivery of the notice. The notice warns of this, and the office ignores later objections.
The office orders a hearing when the report on the discussion shows a conflict. The builder and designer must have rejected conditions of binding opinions or binding statements because they conflict (§ 53 ods. 1). A neighbour has no right to a hearing from the act itself. If the office orders none, the neighbour has the time stated in the notice.
Do neighbours have a say in a notification of a small structure?
The notification (ohlásenie) of a small structure or minor works names no parties (§ 63). The office may find that the structure could affect the rights of third persons. It then tells the builder that the structure needs a decision on the building intent (§ 63 ods. 5). A right of a third person does not count as affected if the effect comes from a special law. The proceedings on the building intent then follow, and § 49 applies to them.
Does the act protect neighbours during construction?
Yes, in two ways. The building inspector checks that the building works do not endanger a neighbouring plot or building (§ 72 ods. 1 písm. g). The inspectorate can also order works by decision. Neighbours are parties when the order directly affects them (§ 75 ods. 2).
What changes from 2027?
Act 243/2026 Z. z. changes Act 25/2025 from 1 January 2027. This is not current law. The points checked here add no rule of neighbour consent. The notice of start goes out within seven working days (§ 51 ods. 1). A person with other rights to the building or land is a party only if the decision can directly affect those rights (§ 49 ods. 1 písm. b). For a talk with the office before you file, see pre-application consultation.
Frequently asked questions
- Do I need written neighbour consent to get approval for a building?
- No. Act 25/2025 does not list a neighbour's consent among the attachments to the application (§ 50 ods. 2), the checks of the office (§ 57 ods. 2) or the grounds for rejection (§ 59 ods. 1).
- Can my neighbour block my project by refusing to sign?
- Not by refusing to sign. A neighbour that is a party can object, and the office must deal with each objection (§ 52 ods. 3). The office ignores objections that only aim to harm or delay (§ 52 ods. 5).
- When is a neighbour included in my building proceedings?
- When the decision on the building intent can directly affect the neighbour's ownership or other rights (§ 49 ods. 1 písm. c). A plot without a shared boundary can count too (§ 7 ods. 2).
- What is the difference between neighbour consent and a neighbour objection?
- Consent is a voluntary agreement that the act does not require. An objection is a statement in the proceedings that the decision would breach the neighbour's rights (§ 52 ods. 4).
- How long do neighbours have to object?
- At the latest at the hearing. If the office orders no hearing, at least seven working days from delivery of the notice. Later objections are ignored (§ 51 ods. 2).
- Can the office make a neighbour allow works from the neighbour's land?
- Yes, if it is necessary on a tight site. The decision on the building intent can order the owner to allow works for the necessary time and extent (§ 46 ods. 1).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 7, 46, 49 to 51, 55 to 57, 59, 63, 72, 75, 84 ods. 11
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 112, 113, 115
- Zákon č. 71/1967 Zb. o správnom konaní (správny poriadok) · Slov-Lex · § 53, § 54 ods. 1 a 2