Public health authority binding opinion
A public health authority binding opinion is the opinion that RÚVZ issues on the possible negative effect of a planned building on public health.
What is a public health authority binding opinion?
A public health authority binding opinion is the binding opinion that the regional public health authority (RÚVZ) issues on a planned building.
The act 355/2007 Z. z. on public health calls this work assessment (posudková činnosť). It is the process of assessing measures and proposals for their possible negative effect on public health. The result is a binding opinion or a decision (§ 13 ods. 1). People often say vyjadrenie (statement). The law says záväzné stanovisko (binding opinion).
Under the Building Act 25/2025 Z. z., the RÚVZ is an affected authority (dotknutý orgán), as described on the binding opinion page. A utility or a road administrator is a different body. It gives a binding statement under § 22.
Who issues the opinion?
The regional public health authority (regionálny úrad verejného zdravotníctva, RÚVZ) issues it. Section 13 ods. 3 names the Public Health Authority of the Slovak Republic (Úrad verejného zdravotníctva, ÚVZ) or the RÚVZ as the affected authority. Section 6 ods. 3 písm. g) gives the RÚVZ the power to issue binding opinions and to decide on proposals under § 13. Annex 1 of the act lists the seats and territorial districts of the RÚVZ (§ 6 ods. 1).
The ÚVZ acts when the matter goes beyond the district of one RÚVZ (§ 5 ods. 4). The ÚVZ is also the superior service office of the RÚVZ (§ 5 ods. 3).
Which buildings need a public health authority opinion?
Section 13 ods. 3 písm. c) gives the opinion on the building intent for a structure that affects healthy living conditions or healthy working conditions. Part five of the act covers these conditions. The exception is residential buildings that are simple structures.
Under the Building Act, § 2 ods. 6 písm. a) names the residential buildings that are simple structures. They have at most three flats and at most two above-ground floors. Their built-up area is up to 300 m².
The act gives no list of the other buildings. Part five starts at § 17. It covers topics such as drinking water (§ 17) and noise, infrasound and vibration in the living environment (§ 27). Ask the RÚVZ whether your building affects these conditions.
At which steps does the RÚVZ act?
Section 13 ods. 3 lists these acts of the RÚVZ in the Building Act procedures.
| Step | What the RÚVZ issues | Source |
|---|---|---|
| Building intent | A binding opinion, for a structure that affects healthy living or working conditions | § 13 ods. 3 písm. c) |
| Project | A compliance declaration, if the RÚVZ reserved it in its binding opinion | § 13 ods. 3 písm. d) |
| Trial operation and early use of a structure | A binding opinion on the permission | § 13 ods. 3 písm. e) |
| Final inspection or change of use | A binding opinion, for a structure that affects those conditions | § 13 ods. 3 písm. f) |
| Protection zones of drinking water sources | A binding opinion on the proposal | § 13 ods. 3 písm. g) |
The list has no item for a notification (ohlásenie) of a building.
Is there a separate RÚVZ step after the final inspection?
Yes, for some premises. The RÚVZ also decides on proposals to put premises into operation. It decides on proposals to put food premises into use too (§ 13 ods. 4 písm. a) and c)). These are decisions, not binding opinions.
In such a decision the RÚVZ can depart from its binding opinion on the final inspection in two cases. The assessed facts changed, or the facts did not exist at the final inspection.
What must the request contain?
Under the Building Act, the builder or the designer makes the documentation available in the information system. Then they ask the affected authority (§ 20 ods. 1 písm. b)). Section 13 ods. 5 of the act 355/2007 Z. z. sets the content of the request.
- The identification data of the applicant.
- The name and address of the person responsible for operating the assessed activity.
- Documentation with a description of the activity.
- A noise load assessment, if the structure is a motorway, a class I road, a railway, a waterway or an airport with motor aircraft.
The RÚVZ can ask for further documents (§ 13 ods. 6).
How many days does the RÚVZ have to answer?
The periods come from the Building Act and are the same for every affected authority. The building permit timeline page shows the other deadlines.
| Step | Period or effect | Source |
|---|---|---|
| Binding opinion of an affected authority | 30 days from delivery of the request, or 60 days for complex structures. The authority must tell the applicant which one applies | § 21 ods. 9 |
| No binding opinion in time | The act presumes no comments and no requirements on the content of the building intent, unless a special regulation says otherwise | § 21 ods. 9 |
| Compliance declaration on the project | 30 days from delivery of the request, or 60 days for complex structures | § 24 ods. 2 |
| No compliance declaration in time | The act presumes that the requirements of the binding opinion are met and that a consenting declaration was issued | § 24 ods. 3 |
| Builder's objection to an opinion | 15 days from delivery, to the competent superior authority of the affected authority | § 21 ods. 13 |
| Date of the final inspection | The office announces it within 7 working days of a complete proposal. The inspection takes place within 30 days of the announcement | § 66 ods. 3 |
The act uses the words complex structure (zložitá stavba) only in the deadline sentences. It gives no definition. If a request lacks precise data, the authority must ask for clarification. The period does not run in the meantime (§ 21 ods. 8).
Section 13 ods. 2 of the act 355/2007 Z. z. says other bodies decide only after a positive binding opinion of the RÚVZ. The paragraph makes an exception where a special regulation says otherwise. Its footnote names § 21 ods. 9 of the Building Act as an example.
What can you do if you disagree with the opinion?
The builder can object to the content of the opinion within 15 days of delivery (§ 21 ods. 13). The objection goes to the competent superior authority of the affected authority. This page did not confirm which body decides the objection against a RÚVZ opinion.
A participant other than the builder objects by appeal against the decision on the building intent (§ 21 ods. 15). The RÚVZ is bound by its own opinion. The exception is a change of law or a material change of facts (§ 21 ods. 7).
What changes from 1 January 2027?
Act 243/2026 Z. z. amends the Building Act from 1 January 2027 (Čl. XV). The 30 and 60 day periods in § 21 ods. 9 stay. New § 24 ods. 5 applies the compliance declaration rules to a change of the project (Čl. I bod 84). The same act changes the public health act in one place. It adds a § 7 ods. 3 on structures for state security (Čl. VI bod 1). The text above describes the law in force on 11 November 2026.
Frequently asked questions
- Do all residential projects need a RÚVZ opinion?
- No. Section 13 ods. 3 písm. c) of the act 355/2007 Z. z. excludes residential buildings that are simple structures. Such a building has at most three flats, at most two above-ground floors and a built-up area up to 300 m² (§ 2 ods. 6 písm. a) of the Building Act). Other buildings need an opinion if they affect healthy living or working conditions.
- How many days does the RÚVZ have to issue its opinion?
- The RÚVZ has 30 days from delivery of the request, or 60 days for complex structures (§ 21 ods. 9 of the Building Act). It must tell the applicant which period applies. A request for clarification stops the period (§ 21 ods. 8).
- What happens if the RÚVZ does not answer?
- The Building Act presumes that the RÚVZ has no comments and no requirements on the building intent (§ 21 ods. 9). For a compliance declaration the act presumes that the requirements are met (§ 24 ods. 3).
- Is it a vyjadrenie or a stanovisko?
- The law calls the RÚVZ document a binding opinion (záväzné stanovisko), see § 13 ods. 3 of the act 355/2007 Z. z. The word záväzné vyjadrenie (binding statement) is for a utility or a road administrator under § 22 of the Building Act.
- Is the RÚVZ the same as the ÚVZ?
- No. The RÚVZ is the regional authority and the ÚVZ is the national one. Both are named as affected authorities in § 13 ods. 3. The ÚVZ acts when a matter goes beyond the district of one RÚVZ (§ 5 ods. 4).
- How is it different from a fire authority opinion?
- The two authorities protect different interests under different acts. The RÚVZ works under the act 355/2007 Z. z. The HaZZ works under the act 314/2001 Z. z., see the fire authority binding opinion page. The Building Act rules on periods and silence are the same for both.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 6, § 20 ods. 1, § 21, § 22, § 24, § 66 ods. 3
- Zákon č. 355/2007 Z. z. o ochrane, podpore a rozvoji verejného zdravia a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 5, § 6, § 13
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 84, Čl. VI bod 1, Čl. XV