Objection in proceedings
An objection in proceedings is a statement by a party that the building decision would breach its rights or legally protected interests.
What is an objection in building intent proceedings?
An objection (námietka) is a statement by a party that the decision on the building intent would breach its rights or legally protected interests. Act 25/2025 Z. z. (the Building Act) groups proposals, comments and objections together. The party raises them with the building office during the building intent proceedings.
The act does not use the name "building permit proceedings". Since 1 April 2025 the old zoning step is the proceedings on the building intent. They end with the decision on the building intent (§ 84 ods. 11, § 60 ods. 1).
Who can raise an objection?
A party to proceedings raises objections to protect its own rights. A neighbour is a party only if the decision can directly affect its ownership or other rights (§ 49 ods. 1 písm. c). The affected authorities and affected legal persons may also raise proposals, comments and objections (§ 51 ods. 2).
An affected authority gives its view in a binding opinion (záväzné stanovisko). A utility or other legal person gives its view in a binding statement (záväzné vyjadrenie). Neither is an objection of a neighbour.
What is the deadline for an objection?
The act sets no fixed number of days. The office states the deadline in its notice of the start of proceedings (§ 51 ods. 2).
- If the office orders a hearing, objections come at the latest at the hearing. Later ones are ignored.
- If the office orders no hearing, the time for objections is at least seven working days from delivery of the notice.
The office ignores objections that arrive after the deadline (§ 52 ods. 6 písm. d). Fifteen days is not the deadline for an objection. Fifteen days is the time limit for an appeal against the decision.
What must an objection say?
An objection must give three things (§ 52 ods. 4).
- Who raises it.
- Which proceedings it concerns.
- Where the party sees a breach of its rights and protected interests, or an unlawful limit on them.
A general dislike of the project does not meet the third point. The party must name the right it says the decision breaks. The act does not list topics such as noise, light or privacy. The office tests each objection against the rights of the party.
The office also ignores anonymous submissions (§ 52 ods. 6 písm. e).
Which objections does the office ignore?
The office does not take into account several kinds of objection. Two paragraphs list them (§ 52 ods. 5 and 6).
| Objection that the office ignores | Section |
|---|---|
| It aims at harming another person, gaining an unlawful benefit, causing delay or obstruction | § 52 ods. 5 |
| Granting it would breach a law, the binding part of the planning documentation or the final opinion of the environmental assessment body | § 52 ods. 5 |
| The same matter was already finally decided in another proceeding that binds this one, with no big change of facts | § 52 ods. 6 písm. a |
| It has no effect on the rights or protected interests of the party or on legal duties | § 52 ods. 6 písm. b |
| It does not relate directly to the subject of the decision | § 52 ods. 6 písm. c |
| It came after the deadline | § 52 ods. 6 písm. d |
| It is anonymous | § 52 ods. 6 písm. e |
What does the office do with an objection?
The office must deal with all proposals, comments and objections of the parties (§ 52 ods. 3). When it decides, it checks that the comments and proposals of the parties are raised (§ 57 ods. 2 písm. f). In the decision it rules on the objections (§ 60 ods. 1 písm. b).
The act ties the hearing to conflicting conditions, not to objections. The office orders a hearing when the report on the discussion shows a conflict. The builder and designer must have rejected conditions of binding opinions or binding statements because they conflict (§ 53 ods. 1). It orders none if it knows the site well and the application is enough. This does not apply to a set of structures (§ 53 ods. 2).
The decision period is 30, 60 or 90 days (§ 58 ods. 1 and 2). A large number of parties gives the 90-day period.
What happens if the objection is about ownership or another right to land?
The office first tries to settle a dispute over ownership or other rights to land or a building. It cannot decide the dispute itself. It tries to reach an agreement of the parties or a settlement (§ 55 ods. 1).
If this fails, the office interrupts the proceedings. It asks the party who raised the objection to ask the court to decide it. The office sets a period for this that is not longer than 60 days (§ 55 ods. 2).
If the party does not show a court filing in that period, the office may judge the objection as a preliminary question. It does this on the basis of public documents (§ 55 ods. 3).
Is an objection the same as an appeal?
No. A party raises an objection before the decision. A party files an appeal after it. The appeal goes to the office that issued the decision. The regional office decides it (§ 14 ods. 1 písm. a). The time limit is 15 days from the announcement of the decision, unless a special law sets another (správny poriadok § 54 ods. 1 and 2).
The two are linked. The appeal body ignores objections that the party could have raised in the first stage and did not raise in time. A party that the office left out is the exception (§ 52 ods. 7). Read more on appeal against decision.
Does an objection stop the building?
The act does not say that an objection stops the proceedings. It names two interruptions. One is for a dispute over a right to land (§ 55 ods. 2). The other is for conflicting binding opinions (§ 54 ods. 2).
Neighbour consent is a different matter. See neighbour consent. Two related topics are building setback distances and pre-application consultation.
What changes from 2027?
Act 243/2026 Z. z. changes Act 25/2025 from 1 January 2027. This is not current law. The rules for objections in § 52 stay as they are, because the amendment does not touch § 52. Four changes sit near it (Art. I, points 115, 116, 117, 118).
- The notice of start goes out within seven working days.
- A public notice "delivers" the notice instead of "announcing" it.
- The office "invites" (prizve) parties to the hearing instead of "summoning" them.
- The paper for the hearing is called a notice of the hearing, not a summons.
Frequently asked questions
- Can neighbours object to a building project in Slovakia?
- Yes, if they are parties. A neighbour is a party when the decision on the building intent can directly affect its ownership or other rights (§ 49 ods. 1 písm. c of Act 25/2025).
- What is the deadline for filing an objection?
- At the latest at the hearing. If the office orders no hearing, at least seven working days from delivery of the notice (§ 51 ods. 2). The office ignores later objections (§ 52 ods. 6 písm. d).
- What must an objection contain?
- Three things: who raises it, which proceedings it concerns, and where the party sees a breach of its rights (§ 52 ods. 4).
- Is an objection the same as an appeal?
- No. A party raises an objection during the proceedings. A party files an appeal after the decision. The limit is 15 days from its announcement unless a special law sets another (§ 54 of the Administrative Procedure Code).
- What happens if the office rejects my objection?
- The office rules on all objections in the decision on the building intent (§ 60 ods. 1 písm. b). You can appeal. The appeal body ignores objections you did not raise in time (§ 52 ods. 7).
- What if my objection is about ownership of land?
- The office tries to settle the dispute. If it fails, the office interrupts the proceedings and sets up to 60 days for you to ask the court to decide (§ 55 ods. 1 and 2).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 14, 49, 51 to 55, 57, 58, 60, 84 ods. 11
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 115 to 118
- Zákon č. 71/1967 Zb. o správnom konaní (správny poriadok) · Slov-Lex · § 53, § 54 ods. 1 a 2