Energy Performance of Buildings Directive (EPBD)
The EPBD is an EU directive that sets energy and emission rules for buildings and aims at a zero-emission building stock by 2050.
What is the Energy Performance of Buildings Directive (EPBD)?
The Energy Performance of Buildings Directive (EPBD) is an EU directive that sets energy and emission rules for buildings in all member states. The current text is Directive (EU) 2024/1275, a recast signed on 24 April 2024 and published in the Official Journal on 8 May 2024. It entered into force on the twentieth day after publication, which is 28 May 2024 (Article 37). It repeals Directive 2010/31/EU with effect from 30 May 2026 (Article 36).
Article 1 states the aim: a zero-emission building stock by 2050. The rules are minimum rules, so a member state may keep or introduce stricter measures. A directive binds member states, not owners. Owners and designers in Slovakia deal with the national act, zákon č. 555/2005 Z. z., and its implementing decree on the energy performance of buildings.
What does the EPBD change for new buildings?
From 1 January 2030 every new building must be a zero-emission building. For a new building owned by a public body the date is 1 January 2028 (Article 7(1)). Until then new buildings must be at least nearly zero-energy buildings and meet the minimum energy performance requirements. A member state may exempt buildings whose permit application was already submitted by those dates (Article 7(4)).
Article 11 defines the zero-emission building. It causes no on-site carbon emissions from fossil fuels. Its maximum energy demand is at least 10 % lower than the member state's threshold for nearly zero-energy buildings on 28 May 2024. Its yearly primary energy use comes from renewable energy produced on site or nearby, a renewable energy community, efficient district heating or carbon-free sources. If that is not feasible, other grid energy that meets national criteria may cover it.
Two more duties apply to new buildings. Member states ensure that designers of all new buildings make best use of the solar potential of the site (Article 10(1)). Suitable solar installations are due on all new residential buildings by 31 December 2029. This applies where it is technically suitable and economically and functionally feasible (Article 10(3)(d)). The life-cycle global warming potential goes into the energy performance certificate. This applies to new buildings over 1 000 m² from 1 January 2028 and to all new buildings from 1 January 2030 (Article 7(2)). Annex III expresses it in kgCO2eq per m² of useful floor area over a 50-year study period. See whole-life carbon.
What does the EPBD change for existing buildings and family houses?
For existing residential buildings the EPBD sets a target for the whole national stock, not a duty for each house. Under Article 9(2) the average primary energy use of the national residential stock falls by at least 16 % by 2030. It falls by at least 20 to 22 % by 2035, both against 2020. At least 55 % of that fall must come from renovating the 43 % worst-performing residential buildings. Each member state sets its own trajectory by 29 May 2026 and chooses measures such as minimum energy performance standards, technical assistance and financial support.
Two rules reach an individual owner. When a building undergoes major renovation, it must meet the minimum energy performance requirements as far as technically, functionally and economically feasible (Article 8(1)). An envelope element with a significant effect on energy performance must meet the minimum requirements. This applies when someone retrofits or replaces it, as far as feasible (Article 8(2)). Article 2 defines major renovation in two ways. The work costs more than 25 % of the building value without the land, or it covers more than 25 % of the envelope surface. The member state chooses one test.
| Group | Rule | Date | Article |
|---|---|---|---|
| Non-residential buildings | All below the threshold that puts 16 % of the national stock above it | From 2030 | 9(1) |
| Non-residential buildings | All below the threshold that puts 26 % of the national stock above it | From 2033 | 9(1) |
| Residential stock | Average primary energy use down at least 16 % against 2020 | By 2030 | 9(2) |
| Residential stock | Average primary energy use down at least 20 to 22 % against 2020 | By 2035 | 9(2) |
| Building in major renovation | Meets the minimum requirements if feasible | At the renovation | 8(1) |
Member states may exempt some categories from these standards. Examples are officially protected buildings, places of worship and residential buildings used under four months a year (Article 9(6)).
Must the owner of an old house insulate it because of the EPBD?
The text of the directive does not set an insulation duty for the owner of a single house. Article 9(2) sets stock-level targets and leaves the choice of measures to the member state. National law decides what an owner must do and when. In Slovakia, amendment 246/2026 Z. z. lists "rules for existing buildings" at renovation, sale or letting in the national building renovation plan (§ 4b ods. 2 písm. j)). It takes effect on 1 January 2027, and the page does not describe those rules.
Does the EPBD ban gas boilers?
The directive does not contain a ban on boilers in individual houses. Article 13(7) says member states shall strive to replace stand-alone boilers powered by fossil fuels in existing buildings, in line with national phase-out plans. Article 17(15) stops financial incentives for installing such boilers from 1 January 2025, with exceptions for investments selected before 2025 under named EU funds. The template for national building renovation plans (Annex II) asks for the phase-out of fossil fuels in heating and cooling. Its aim is a complete phase-out of fossil fuel boilers by 2040.
What are the main EPBD deadlines?
| Date | What happens | Article |
|---|---|---|
| 1 January 2025 | No financial incentives for stand-alone fossil fuel boilers | 17(15), 35(1) |
| 31 December 2025 | First draft national building renovation plan goes to the Commission | 3(3) |
| 29 May 2026 | Transposition deadline, residential trajectory, renovation passport scheme | 35(1), 9(2), 12(1) |
| 30 May 2026 | Directive 2010/31/EU is repealed | 36 |
| 31 December 2026 | First final national building renovation plan, solar on new public and non-residential buildings over 250 m² | 3(7), 10(3)(a) |
| 1 January 2027 | Roadmap for life-cycle GWP limit values of new buildings | 7(5) |
| 1 January 2028 | Zero-emission buildings for new public-owned buildings, GWP disclosure over 1 000 m² | 7(1), 7(2) |
| 31 December 2029 | Solar installations on all new residential buildings | 10(3)(d) |
| 1 January 2030 | Zero-emission buildings for all new buildings, GWP disclosure for all | 7(1), 7(2) |
The renovation passport scheme is voluntary for owners unless the member state makes it mandatory (Article 12(2)).
Where does Slovakia stand with the EPBD?
Slovakia adopted its transposing act after the 29 May 2026 deadline, and the act applies from 1 January 2027. The National Council approved amendment 246/2026 Z. z. on 15 September 2026. Its promulgation date is 8 October 2026, and it takes effect on 1 January 2027 (Čl. IV). It amends zákon č. 555/2005 Z. z. and adds Directive (EU) 2024/1275 to the list of transposed EU acts.
- In force now (version of 555/2005 from 1 April 2025): a new building must meet the minimum energy performance requirements (§ 4 ods. 1). Technical regulations and standards give the parameters.
- From 1 January 2027: a new building owned by a public body is a zero-emission building from 1 January 2028. All other new buildings follow from 1 January 2030 (§ 4 ods. 2 as amended).
- From 1 January 2027: the national building renovation plan contains the 16 % and 26 % thresholds for non-residential buildings. It also holds the 16 % and 20 to 22 % residential targets (§ 4b ods. 2 as amended).
- From 1 January 2027: the certificate shows the life-cycle global warming potential. This applies to new buildings over 1 000 m² from 2028 and to all new buildings from 2030 (§ 7 ods. 1 písm. l)).
How does the EPBD relate to the cost-optimal level?
Member states must set minimum energy performance requirements with a view to at least the cost-optimal level (Article 5(1)). They review the minimum requirements at intervals of no more than five years. Article 2 defines a nearly zero-energy building as one no worse than the 2023 cost-optimal level that member states reported.
Frequently asked questions
- What is the EPBD?
- The EPBD is the Energy Performance of Buildings Directive, an EU directive that sets energy and emission rules for buildings. The current text is Directive (EU) 2024/1275 of 24 April 2024, which repeals Directive 2010/31/EU from 30 May 2026.
- What does the new EPBD mean for family houses?
- A new family house must be a zero-emission building from 1 January 2030. Suitable solar installations are due on new residential buildings by 31 December 2029. For existing houses the directive sets a stock-level target, not a duty for each house. Primary energy use falls by 16 % by 2030 and by 20 to 22 % by 2035.
- When must new buildings be zero-emission buildings?
- New buildings owned by public bodies must be zero-emission buildings from 1 January 2028 and all new buildings from 1 January 2030. A member state may exempt buildings with a permit application filed before those dates.
- Must the owner of an old house insulate it?
- The directive text sets no insulation duty for the owner of a single house. It sets targets for the whole residential stock and lets each member state choose measures. A building that undergoes major renovation must meet the minimum requirements if this is technically, functionally and economically feasible.
- Does the EPBD ban gas boilers?
- The directive text contains no ban on boilers in individual houses. From 1 January 2025 member states may not give financial incentives for new stand-alone fossil fuel boilers, with exceptions for earlier selected investments. Member states must strive to replace such boilers under national phase-out plans.
- Has Slovakia transposed the 2024 EPBD?
- Slovakia promulgated amendment 246/2026 Z. z. on 8 October 2026, after the 29 May 2026 deadline. It amends zákon č. 555/2005 Z. z. and takes effect on 1 January 2027. Until then the version of 555/2005 from 1 April 2025 applies.
Sources
- Directive (EU) 2024/1275 of the European Parliament and of the Council of 24 April 2024 on the energy performance of buildings (recast) · European Parliament and Council of the EU, Official Journal L 2024/1275, 8.5.2024 · Articles 1 to 3, 5 to 13, 17, 19, 35 to 37, Annex II