What is an extension and what is an added storey?
Under § 5 ods. 1 of Act 25/2025 (the Building Act), an extension and an added storey are changes to a completed building. An extension is a widening of an existing building in plan, while the building keeps its structural and operational unity (§ 5 ods. 3). An added storey raises an existing building by at least one floor, an attic or a recessed floor, with the same unity (§ 5 ods. 4).
A building alteration is a different matter. It modifies the structure of an existing building but is not a change to the building (§ 2 ods. 9 písm. a). The text on removing a load-bearing wall covers an alteration that keeps the size, for example removing a wall.
An extension takes plot area, and an added storey takes load capacity from the existing house. The spatial plan governs both, and both need a design of the load-bearing structures. If you are still deciding whether to keep the house, read the text on renovating or demolishing.
| Aspect | Extension | Added storey |
|---|---|---|
| What the act describes | widening of an existing building in plan (§ 5 ods. 3) | raising by a floor, an attic or a recessed floor (§ 5 ods. 4) |
| Type of change under the act | change to a completed building | change to a completed building |
| What the spatial plan can limit | built-up share of the plot and distances | building height and number of floors |
| What the static part of the project assesses | load-bearing structures of the extension and their link to the house | load-bearing structures of the new floor and the capacity of the existing structures |
What permit does an extension or an added storey need?
Act 25/2025 no longer uses the word "building permit" (stavebné povolenie). A change to a completed building needs a decision on the building intent, unless the act says otherwise (§ 18 ods. 2). Under § 18 ods. 3 notification applies to minor structures and building alterations, not to a change to a completed building. Occupancy approval (kolaudácia) follows completion (§ 66 ods. 1).
A free-standing ground-floor garage up to 50 m² of built-up area and 5 m in height is a minor structure. It needs notification (§ 2 ods. 4 písm. a, § 18 ods. 3). A garage attached to a house can be an extension if it keeps structural and operational unity with the house (§ 5 ods. 3). The act has no further test. Ask the building office to classify it.
The builder must have a legal relation to the plot or the building. If the applicant has none, the office stops the proceedings (§ 56 ods. 1 písm. a).
How does the approval process run, step by step?
- An authorised person prepares the documentation. The static part belongs to the structural designer (§ 35 ods. 4, 8).
- The builder or designer makes the documentation available in the information system. They ask the planning authority and the affected authorities for binding opinions, and the affected legal persons for binding statements (§ 20 ods. 1).
- The builder files an electronic application with the documentation and the report on the discussion of the building intent (§ 50 ods. 1 and 2).
- The office notifies the parties of the start of proceedings within seven days of the complete application (§ 51 ods. 1). It decides within 30 days if no hearing or site inspection is needed, and within 60 days if one is (§ 58 ods. 1).
- The office verifies the project within 30 days. If it decided on the intent together with the project, it verifies the project at the same time as the decision (§ 65 ods. 2).
If the application lacks required parts, the office asks you within 15 days to complete it. It warns that it will otherwise stop the proceedings (§ 50 ods. 3).
The planning authority issues its binding opinion within 30 days for notified and simple structures. It has 60 days for other structures and 90 days for reserved structures (Act 200/2022, § 24a ods. 5). If it is late, it is presumed to have no comments and to find the proposal compliant with the spatial plan (§ 35 ods. 1 písm. a). An affected authority issues a binding opinion, and an affected legal person issues a binding statement.
A decision on the building intent is valid for two years from legal force, unless the office sets a longer period. It does not lapse if you applied for project verification within that period (§ 61 ods. 1). A verification clause lapses if work has not started within two years of its issue, unless the office sets a longer period (§ 65 ods. 6).
From 1 January 2027, Act 243/2026 also changes § 5 and § 51. A change to a completed building becomes a change to the outer plan and height limits of the building. The period in § 51 ods. 1 counts in working days. Check the text in force on the day you file.
What does the structural engineer check for an added storey?
The designer of the static part is responsible for the design of the load-bearing structures and their static assessment. A checkable static calculation is part of it (§ 35 ods. 8). Act 138/1992 gives the design of load-bearing structures and opinions on their changes to the engineer for structural statics (§ 5 ods. 4).
An added storey puts more load on the existing masonry, on the ceiling under the new floor and on the foundations. The engineer must know the existing state. If documents are missing, the engineer measures the house and carries out a survey and diagnostics of the load-bearing structures (Act 138/1992, § 5 ods. 4 písm. c). The engineer checks mainly:
- what the load-bearing walls are made of, how thick they are and whether they run down to the foundation, as in a masonry bearing system
- what the foundations and the ground under them are
- what the ceiling under the new floor is and whether it can carry the new load
What should an added storey be built from?
Every kilogram of the new floor loads the old house. So an added storey often uses a light structure, for example timber frame construction or structural insulated panels. The engineer's calculation decides the material, not the type of construction. A masonry storey is possible if the existing structures can carry it.
Where possible, the new load-bearing walls should stand above the existing load-bearing walls. Then their load goes through the masonry to the foundation. A wall that stands in the span of a ceiling loads the ceiling at one place. The engineer checks such a point load separately.
Why does the joint between the old and new part crack?
The old part of the house has already settled and the new part has yet to settle. The materials also shrink and expand differently. If you tie the parts together rigidly, the difference in movement shows as a crack at the joint. So the designer decides whether to separate the new part with a settlement joint or to tie it to the house. That decision belongs in the design, not on site.
Before work starts, photograph the existing cracks with dates. An owner must not endanger a neighbour's building or plot by changing a building without adequate measures. An owner also must not disturb neighbours beyond what is reasonable with noise, dust, shading and vibration (Civil Code, § 127 ods. 1).
How much room do the spatial plan and distances leave, and what do neighbours do?
A spatial plan can set numeric limits on building, called regulatives (Act 200/2022, § 5 písm. i and j). Decree 392/2023 defines the built-up limit as the highest share of built area against the plot in percent (§ 2 písm. w). The height limit is a limit in metres or in standard floors. An attic or recessed floor counts as a floor under one condition. Its area must be above 50 % of the area of the highest standard floor under it (§ 2 písm. aa). See the entry on the building coverage ratio.
Decree 532/2002 sets the distance between family houses at 7 m or more. From common plot boundaries it sets 2 m or more (§ 6 ods. 3). In tight conditions the distance between houses can drop to 4 m if the facing walls have no windows of habitable rooms (§ 6 ods. 4). The decree stays in force until the new technical decrees apply, at the latest to 31 March 2027 (Act 25/2025, § 84 ods. 23).
Owners of neighbouring plots and buildings are parties to the proceedings if the decision can directly affect their ownership (§ 49 ods. 1 písm. c). The office must deal with all their comments and objections (§ 52 ods. 3). If the office ordered no hearing, the period for comments must be at least seven working days from delivery of the notice (§ 51 ods. 2). So show the neighbours the design before you file the application.
What must I prepare for occupancy approval after an extension or an added storey?
Occupancy approval (kolaudácia) starts on the builder's request. The attachments depend on the type of building and can include (§ 66 ods. 2):
- the site diary and the final statement of the site manager
- the as-built documentation of the building
- surveying documents from the setting-out, a control record of the position measurement and a land survey plan to update the cadastre
- the survey of the completed building as built
- the energy certificate of the building, if it needs one
The office announces the date of the inspection within seven working days of the complete request. The inspection must take place within 30 days of the announcement (§ 66 ods. 3). The building can enter permanent use only after occupancy approval (§ 66 ods. 1).
