Water-Source Heat Pump

A water-source heat pump is a heat pump that takes heat from groundwater or surface water and supplies it to the heating system.

What is a water-source heat pump?

A water-source heat pump is a heat pump that takes its heat from water. It raises the temperature with an electric compressor and delivers the heat to the heating system of a building.

Regulation (EU) No 813/2013 defines a heat pump space heater. It is a heater that uses ambient heat from an air source, a water source or a ground source. The regulation covers units that supply water-based central heating. Its information table lists water-to-water and brine-to-water heat pumps. The Slovak name is "tepelné čerpadlo voda-voda".

Directive (EU) 2018/2001 defines ambient energy as thermal energy that can be stored in ambient air, surface water or sewage water. Ambient energy and geothermal energy are renewable energy sources in the directive. It defines geothermal energy as energy stored as heat beneath the surface of solid earth. The act 364/2004 Z. z. calls the heat that waters can supply the "tepelný potenciál" (§ 2 písm. ba).

Does a water-source heat pump need a water permit in Slovakia?

Yes, in the cases that § 21 ods. 1 of the Water Act lists. The permit is the "povolenie na osobitné užívanie vôd". The authority for state water administration issues it.

For groundwater the act lists two uses that apply here. They are the abstraction of groundwater (písm. b bod 1) and the use of its thermal potential without direct abstraction (písm. b bod 5). For surface water the act lists abstraction and use of thermal potential without direct abstraction (písm. a bod 1 and 4).

The permit has a set period. The authority issues a permit for abstraction or for use of thermal potential for at most ten years (§ 21 ods. 4 písm. a a i). It may extend the permit if the conditions do not change (§ 21 ods. 5). The permit does not guarantee the permitted quantity or quality of the water (§ 21 ods. 6).

Anyone may use water for the personal needs of a household without a permit. This applies only with a simple water device (§ 18 ods. 1). For groundwater the act names hand-pumped house wells, spring catchments below 10 l/min and portable containers as simple devices (§ 18 ods. 3).

Does the well need its own permit?

A structure that enables the special use of water is a water structure. The act names wells among the water structures (§ 52 ods. 1 písm. d).

The authority for state water administration permits the building of a water structure (§ 26 ods. 1). It can do so only after it issues the permit for special use of waters, where the act requires one.

If the work needs the decision on a building intent under the Building Act 25/2025 Z. z., the water-use permit comes before that decision or together with it in a joint procedure (§ 21 ods. 2). This applies if the structure is neither existing nor already permitted.

Ask the water authority whether a closed ground loop without contact with groundwater needs a permit. Ask the water authority and the building office about drilling rules before you plan a borehole.

Which source types does the EU rating use?

Regulation 813/2013 gives standard rating conditions for each heat source. For water-source units the heat source water enters at +10 °C and leaves at +7 °C. For brine-source units the brine enters at 0 °C and leaves at -3 °C. These are test conditions and not site values.

Heat sourceInlet and outlet temperature at the outdoor heat exchangerIndoor heat exchanger outlet
Outdoor air+7 °C dry bulb (+6 °C wet bulb) inlet55 °C or 35 °C
Water+10 °C and +7 °C55 °C or 35 °C
Brine0 °C and -3 °C55 °C or 35 °C

The outlet is 35 °C for a low-temperature heat pump and 55 °C for other units. The regulation counts the electricity of the groundwater pumps in ηs for water-to-water and brine-to-water units. This lets a buyer compare them with units that have no such pump.

What efficiency must a water-source heat pump reach?

Water-to-water and brine-to-water units fall under Regulation 813/2013. From 26 September 2017 the minimum seasonal space heating energy efficiency (ηs) is 110 % for medium-temperature units. For low-temperature heat pumps it is 125 %.

Unit typeMinimum ηs from 26 September 2015Minimum ηs from 26 September 2017
Medium-temperature100 %110 %
Low-temperature heat pump115 %125 %

The regulation declares ηs for average climate, which is the climate of Strasbourg. See seasonal COP for the link between SCOP and ηs. Regulation 813/2013 names no recommended SCOP value for water-source units, so this page gives none.

What data does a design need that this page cannot give?

This page gives no groundwater temperature, well yield, loop length or land area. These values come from a survey of the site. A figure from a general text does not apply to a given plot.

The EU training syllabus for heat pump installers shows what a survey covers. It lists ground source temperatures of different regions, identification of soil and rock for thermal conductivity, and the regulations on using geothermal resources.

Who may install a water-source heat pump?

Act 309/2009 Z. z. requires a certificate for installers of heat pumps and of shallow geothermal systems (§ 13a ods. 2 písm. c a d). The Ministry issues it after proof of education, practice and an exam. It is valid for five years and renews once for five years after update training (§ 13a ods. 7).

Directive (EU) 2023/2413 limits the permit procedure for ground source heat pumps to three months.

Is there a subsidy for a water-source heat pump?

The programme Zelená domácnostiam supports heat pumps in family houses. As of November 2026 the SIEA page gives 400 € per kW with a maximum of 4 000 €. With the 15 % supplement it gives 460 € per kW with a maximum of 4 600 €.

The SIEA conditions page (November 2026) does not say which heat pump types qualify. It also does not say whether drilling or well work is eligible. The installed device must be on the list of eligible devices. See Zelená domácnostiam.

How does it fit into a low-energy house?

A heat pump uses electricity. A photovoltaic panel can supply part of it, and home battery storage can hold some of that electricity. A passive house has a low heating demand. A hybrid heat pump adds a second heat source to the heat pump.

How does it differ from other heat pump types?

The heat source differs. An air-to-air heat pump takes heat from outdoor air and heats indoor air. An air-to-water heat pump takes heat from outdoor air and heats a water circuit. A ground-source heat pump takes heat from the ground.

Frequently asked questions

What is the difference between a water-source and an air-source heat pump?
The heat source. A water-source unit takes heat from water, an air-source unit takes it from outdoor air. Regulation 813/2013 gives each source its own standard rating conditions.
Do I need a permit to use groundwater for a heat pump?
Yes in the cases in § 21 ods. 1 písm. b of act 364/2004 Z. z. Abstraction of groundwater and use of its thermal potential without direct abstraction both need the permit for special use of waters.
For how long is the water permit valid?
The authority issues the permit for at most ten years for abstraction and for use of thermal potential (§ 21 ods. 4). It may extend the permit if the conditions do not change.
What minimum efficiency applies to a water-source heat pump?
Under Regulation 813/2013 the minimum ηs from 26 September 2017 is 110 % for medium-temperature units and 125 % for low-temperature heat pumps.
Does a closed ground loop need a water permit?
Ask the water authority. Act 364/2004 Z. z. lists use of the thermal potential of groundwater without direct abstraction as a use that needs a permit. It does not name closed loops.
Does Zelená domácnostiam pay for a water-source heat pump?
The SIEA page lists heat pumps at 400 € per kW, maximum 4 000 €, as of November 2026. It does not say which types or which ground works qualify, so read the list of eligible devices.

Sources

  1. Commission Regulation (EU) No 813/2013 of 2 August 2013 implementing Directive 2009/125/EC with regard to ecodesign requirements for space heaters and combination heaters · European Commission (Official Journal of the European Union, L 239/136) · Art. 1, Art. 2 pts 17, 20 and 23, Annex I pts 20, 22, 28, 52 to 54, Annex II pt 1, Annex III pt 4 and Tables 2 to 5, Annex V
  2. Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources · European Parliament and Council (Official Journal of the European Union, L 328/82) · Art. 2 pts 1 to 3, Annex IV, Annex VII
  3. Directive (EU) 2023/2413 of the European Parliament and of the Council of 18 October 2023 amending Directive (EU) 2018/2001 · European Parliament and Council (Official Journal of the European Union) · Art. 16e of Directive 2018/2001 as inserted
  4. Zákon č. 364/2004 Z. z. o vodách a o zmene zákona Slovenskej národnej rady č. 372/1990 Zb. o priestupkoch v znení neskorších predpisov (vodný zákon), version effective from 14.10.2025 · Národná rada Slovenskej republiky (Slov-Lex) · § 2 písm. ba), § 18 ods. 1 a 3, § 21 ods. 1, 2, 4 a 6, § 26 ods. 1, § 52 ods. 1
  5. Zákon č. 309/2009 Z. z. o podpore obnoviteľných zdrojov energie a vysoko účinnej kombinovanej výroby a o zmene a doplnení niektorých zákonov, version from 01.09.2026 · Národná rada Slovenskej republiky (Slov-Lex) · § 2 ods. 1 písm. a), § 13a ods. 2 a 7
  6. Zelená domácnostiam: Podmienky pre rodinné domy (SIEA) · Slovenská inovačná a energetická agentúra (zelenadomacnostiam.sk)