Snow guard

A snow guard is a device on a pitched roof that catches sliding snow. Decree 532/2002 requires one on roofs steeper than 25 degrees.

What is a snow guard?

A snow guard is a device fixed to a pitched roof that catches snow sliding down the roof. The Slovak building decree calls it zachytávač zosúvajúceho sa snehu, a catcher for sliding snow. The device belongs to the roof covering. It does not carry the roof and it does not remove the snow.

The decree names the purpose. A roof must catch snow and ice so that they do not endanger pedestrians or road users. A snow guard is one way to meet that requirement on a sloping roof.

When does the Slovak decree require a snow guard?

The general technical requirements for buildings are in Vyhláška 532/2002 Z. z. The new building act, 25/2025 Z. z., keeps this decree in force until its implementing regulations apply, and at the latest until 31 March 2027 (§ 84 ods. 23 písm. b). We read the version dated 1 March 2020 on Slov-Lex. Section 26 on roofs has two rules for snow.

RuleWhat the text saysWhere it sits
Snow and ice on any roofThe roof must catch snow and ice so that they do not endanger pedestrians or road users.Decree 532/2002, § 26 ods. 1
Pitch triggerA pitched roof with roof planes steeper than 25 degrees must have a catcher for sliding snow.Decree 532/2002, § 26 ods. 6
Snow load valuesThe standard gives guidance for determining snow load values for designing buildings and civil engineering structures.STN EN 1991-1-3, ÚNMS catalogue record

The decree sets the duty and the 25 degree trigger. It does not say how many devices to fit, how far apart to place them, or how much load each device must hold. Those choices belong to the designer. Check the current text on Slov-Lex before you rely on the numbers in a permit file.

Act 25/2025 adds one more rule. Where a manufacturer's instructions apply to the use of a building product, the work must follow them (§ 27 ods. 2). A snow guard system has such instructions.

Does a flatter roof need snow protection?

The 25 degree figure belongs to the specific rule in ods. 6. A roof at or below 25 degrees falls outside that sentence. Section 26 ods. 1 still applies to every roof, because it speaks of snow and ice that endanger people below. The designer decides how the roof meets that duty.

What kinds of snow guard are there?

Roof makers and trade articles describe several forms. The table follows two sources, a Tondach technician and a Ruukki roofing specialist.

FormWhat it isSource
Snow hooks or snow tilesSingle units fixed at points on the coveringTondach
Snow gridsMesh barriers, recommended in addition to hooks on taller buildingsTondach
Tube guardsBeams with two long tubes, the more common and more attractive formRuukki specialist
Sheet-metal guardsProfiled sheets with stiffeners along the roof edgeRuukki specialist
Snow divertersUnits in front of chimneys and roof windows that break up the snow layerRuukki specialist

A standing-seam metal roof uses clamp supports on the seam, so nothing passes through the covering. Choose a device made for your covering, and follow the maker's fixing instructions.

Where do snow guards go on a roof?

The advice below comes from manufacturers and trade press, not from the decree. The decree gives no placement rule. It does not name a row or a distance from the eaves.

  • Tondach advises one guard on each tile in the second row above the gutter, then more guards spread over the roof surface to a scheme.
  • The same technician calls guards only along the eaves insufficient. Snow sliding from higher up can damage or tear off a single row.
  • The Ruukki specialist places diverters in front of chimneys and roof windows.
  • Both sources link the number and size of guards to roof pitch, roof size and local snowfall, so the designer sets them.

Think about the ground below as well. The decree speaks of pedestrians and road users. A roof edge above an entrance, a path, a drive or a public place needs the most attention.

How do snow guards fit to the roof structure?

A guard holds back snow, so snow load acts on its fixings and passes into the roof. The Ruukki specialist describes one example. A tube guard on wavy tiles has screws through each beam into the batten. A sealing washer sits between the covering and the beam. The article lists these errors:

  • fixing outside the battens.
  • fixing without sealing washers.
  • using wood screws smaller than 6 x 70 mm, or not driving them at 90 degrees.
  • fixing a tube guard to the tile crest instead of the structure.
  • using too few or undersized guards, which can pull the anchors out and damage the roof.

These figures describe one example roof from one article. For your roof, use the instructions of the product you buy. Where a fixing passes through the covering, check the flashing detail at the same time.

How is a snow guard different from a snow load?

A snow load is the weight of snow that the roof structure must carry. It is a structural value, and the standard gives the method for finding it. A snow guard controls where moving snow goes. It does not remove the snow and it does not reduce the load.

STN EN 1991-1-3 is the Slovak snow load standard. The ÚNMS catalogue describes it as guidance for determining snow load values for designing buildings and civil engineering structures. The catalogue lists STN EN 1991-1-3:2026-10 as the replacing text and shows the older version withdrawn on 1 April 2028. Check the current edition before use. The record does not mention snow guards, so the standard is the source for the load, not for guard placement.

Can a snow guard go on an existing roof?

Yes, but check the structure first. Tondach advises a static assessment before you place guards, especially in a renovation. An older roof structure may carry less load than a new one. Ask a structural engineer to assess the roof truss and the roof boarding before a row of devices is added. The Ruukki article notes that owners often fit guards only after the first snow problems. Plan them in the project instead.

What should I check before fitting a snow guard?

Work through these steps in order.

  1. Measure the roof pitch and note which roof planes are steeper than 25 degrees.
  2. Mark the places below the eaves where people, vehicles or neighbours are exposed.
  3. Choose a device that suits the covering, since devices are made for specific tiles and profiles.
  4. Read the maker's fixing instructions and ask the designer for the number and layout of guards.
  5. Ask an engineer to check the roof structure if the roof is old or lightly framed.
  6. Read the current decree text on Slov-Lex, and the catalogue entry for the snow load standard.

The eaves detail and the roof pitch decide where the first row sits, so settle both before the covering goes on.

Frequently asked questions

What is the Slovak decree's name for a snow guard?
Decree 532/2002 uses the term zachytávač zosúvajúceho sa snehu, which means a catcher for sliding snow. This glossary calls the same device a snow guard. Slovak roof makers and trade articles also write about snehové zábrany.
At what roof pitch does the decree require a snow guard?
A pitched roof with roof planes steeper than 25 degrees must have a catcher for sliding snow. The rule is in § 26 ods. 6 of Decree 532/2002, in the version dated 1 March 2020. The decree does not set a number of devices or their spacing.
Does a roof at 25 degrees or less need no snow protection?
Not automatically. § 26 ods. 1 applies to every roof. It says the roof must catch snow and ice so that they do not endanger pedestrians or road users. Only the specific catcher rule has the 25 degree trigger.
Which standard gives the snow load on a roof?
STN EN 1991-1-3 is the Slovak snow load standard. The ÚNMS catalogue describes it as guidance for determining snow load values for designing buildings and civil engineering structures. The record does not mention snow guards.
Can snow guards be added to an existing roof?
Tondach advises a static assessment before you place guards, especially in a renovation. An older roof structure may carry less load than a new one. Ask a structural engineer before you fit a row of devices.
Can I fit snow guards myself?
A trade article quoting a Ruukki roofing specialist says the work is possible after a talk with the project designer. It lists fixing outside the battens, missing sealing washers and too few guards as common mistakes.

Sources

  1. Vyhláška 532/2002 Z. z. o všeobecných technických požiadavkách na výstavbu (§ 26 strechy stavby) · Ministerstvo životného prostredia SR, via Slov-Lex · § 26 ods. 1 and ods. 6
  2. Zákon 25/2025 Z. z. Stavebný zákon (§ 27 ods. 2, § 84 ods. 23) · Slov-Lex · § 27 ods. 2; § 84 ods. 23 písm. b
  3. STN EN 1991-1-3/Zmena A1: Eurokód 1. Zaťaženia konštrukcií. Časť 1-3: Všeobecné zaťaženia. Zaťaženie snehom · ÚNMS SR (Úrad pre normalizáciu, metrológiu a skúšobníctvo SR), norm catalogue · catalogue record: scope and status
  4. Podceňovaná montáž sněhových zábran · Dům a byt (dumabyt.cz), 17 Dec 2014, quoting J. Hála, Ruukki · Whole article
  5. Protisněhová opatření na střechu? Ano, a nejen v horských oblastech · Dům a byt (dumabyt.cz), 30 Nov 2023, quoting R. Prus, Tondach · Whole article