What is the difference between a protection zone and an easement?
A protection zone (ochranné pásmo) is a strip of space around a line, road, railway, forest or monument. An act or a decision of an authority sets its width. An easement (vecné bremeno) is a right that binds the owner of a plot. The owner must tolerate something, refrain from something or do something for someone else (Civil Code § 151n ods. 1).
Both can stop you from building where you planned to. Each one sits in a different document and has a different way out. The table shows the main differences.
| Feature | Protection zone | Easement |
|---|---|---|
| Legal basis | An act for each sector, or a decision of an authority | Civil Code § 151n and § 151o |
| How it arises | From the act and the distances it sets, or from a decision, for example of the heritage office | By written contract, will, agreement of heirs, decision of an authority, by law, or by long use of the right. A contract needs an entry in the cadastre (§ 151o ods. 1) |
| Where you find it | In the act, in the operator's statement and in the municipal plan | In part C of the list vlastníctva |
| Whom it serves | The line, road, railway, forest or monument | A named person or the owner of another property |
| How you change it | Consent or exception from the operator or the authority, or moving the line | Contract with entry in the cadastre, decision of an authority, change of conditions or court |
An easement tied to a property passes to the buyer with the property (Civil Code § 151n ods. 2). A personal easement ends at the latest when the beneficiary dies (§ 151p ods. 4). A protection zone follows the facility, not the owner. These sections belong to Civil Code 40/1964, which the new Civil Code 260/2026 repeals from 1 July 2027 (§ 1919).
Where do I find an easement and where do I find a protection zone?
Part C of the land registry extract (list vlastníctva) shows easements. The entry gives the content of the easement and the beneficiary (act 162/1995 § 8). They tell you whether the easement is tied to a property or to a person.
An easement of an energy operator can arise by law (act 251/2012 § 11 ods. 8). The operator must file for the cadastre entry within three months of the notice or of the first use of the right. A recent one may not be in the extract yet, so ask the operator as well.
Act 162/1995 § 8 does not list a protection zone among the items of part C. The act that creates the zone sets its distance. So an empty part C does not show that the plot is free of zones. Use three sources.
- The municipal land-use plan. It reflects the protection zones that special acts set (act 200/2022 § 22 ods. 4).
- Zoning information. The municipality issues it on request, only for plans approved before 1 April 2024. It states conditions of use and regulatives, and it is not a binding opinion (act 200/2022 § 40 ods. 13).
- The binding statement of each operator. It lists concrete requirements for the design (act 25/2025 § 22 ods. 3).
The operator has 30 days to issue the binding statement, and up to 60 days for a complex structure. If it does not answer in time, the law presumes that it has no comments (§ 22 ods. 5). Keep proof of your request and do not read silence as a clear plot.
The binding statement is for the builder or the designer (§ 22 ods. 3). Before you buy, you are neither. Ask each operator whether it answers a buyer. If it does not, ask the seller to apply. The water act is different. It gives any applicant data on a clash with the zone of a public water main or sewer. The deadline is 30 days (act 442/2002 § 19 ods. 7).
Which protection zones does a family house meet most often?
The distances come from the acts in force on 11 November 2026. The operator's statement tells you what applies to your plot. The glossary also explains utility protection zones in general.
| Source of the zone | Rule | Distance |
|---|---|---|
| Overhead power line | Act 251/2012 § 43 ods. 2 | From the outermost conductor. At 1 to 35 kV: 10 m for bare conductors, 4 m with basic insulation, 1 m for a hung cable. Above 35 kV: 15 m up to 110 kV. 20 m up to 220 kV. 25 m up to 400 kV. 35 m above 400 kV |
| Underground power line | Act 251/2012 § 43 ods. 7 | From the outermost cable: 1 m up to 110 kV, 3 m above 110 kV |
| Substation | Act 251/2012 § 43 ods. 9 | Outdoor type, from the fence: 10 m below 110 kV, 30 m from 110 kV. Indoor type: the fence or the building boundary |
| Gas pipeline | Act 251/2012 § 79 ods. 2 | From the pipe axis: 1 m for distribution in a built-up area below 0.4 MPa. Otherwise 4 m up to DN 200. 8 m for DN 201 to 500. 12 m for DN 501 to 700. 50 m above DN 700 |
| Gas safety zone | Act 251/2012 § 80 ods. 2 and 3 | 10 m for pipes below 0.4 MPa in open and unbuilt land. In continuous development below 0.4 MPa the operator sets it. At higher pressures 20 to 200 m |
| Public water main and sewer | Act 442/2002 § 19 ods. 2 and 4 | Outside built-up areas, from the axis: 1.8 m up to 500 mm, 3.0 m above. In built-up areas the district office sets it by decision, at most those distances |
| Communication cable | Act 452/2021 § 23 ods. 7 | 0.5 m from the route axis on each side |
| Road | Act 135/1961 § 11 and decree 35/1984 § 15 ods. 3 | Outside built-up areas, from the axis of the carriageway. Motorway 100 m, class I 50 m, class II 25 m, class III 20 m. Local road class I and II 15 m |
| Railway | Act 513/2009 § 5 ods. 3 | 60 m from the axis of the outermost track, and at least 30 m from the outer boundary of the railway perimeter. The decision on the building intent can say otherwise |
| Forest | Act 326/2005 § 10 ods. 1 | Land up to 50 m from the boundary of a forest plot |
| Heritage | Act 49/2002 § 18 ods. 2 | No fixed distance. The heritage office sets the area and the conditions by decision |
Gas needs one more step. A family house usually connects to a distribution main. For a pipe in a built-up area with operating pressure below 0.4 MPa, the zone is 1 m from the axis (§ 79 ods. 2 písm. e). The wider bands belong to larger pipes. The safety zone under § 80 is separate.
Roads have their own glossary entry on road protection zones. The zone of a new or rebuilt road arises when the decision on the building intent becomes final (act 135/1961 § 11 ods. 1).
What can I not do in a protection zone, and can I build there at all?
Each act has its own bans and its own route to consent. Building inside a zone is not always excluded.
- Overhead power line: the act bans structures, dumps, trees taller than 3 m and storage of flammable or explosive material (act 251/2012 § 43 ods. 4). The operator can consent to building (§ 43 ods. 14). For a structure that needs permitting, the operator gives the consent in its binding statement.
- Underground power line: no structures, dumps, permanent plants or heavy machinery. Earthworks need prior consent of the operator (§ 43 ods. 8).
- Gas: building or work in the zone is possible only with the consent of the network operator and on its conditions (§ 79 ods. 5 and 6).
- Water main and sewer: the act bans earthworks, structures, permanent plants, dumps and terrain changes (act 442/2002 § 19 ods. 5).
- Road: activity that could endanger the road or its traffic is banned or limited. The road authority can allow an exception by a binding opinion (act 135/1961 § 11 ods. 2). Apply at the stage of preparatory documentation (§ 11 ods. 5).
- Railway: some actions need the consent of the railway operator and a binding opinion of the special building authority. Examples are earthworks, terrain changes and storage of flammables (act 513/2009 § 6 ods. 1).
- Forest: siting a building in the 50 m strip needs a binding opinion of the state forestry authority (act 326/2005 § 10 ods. 2).
A building made in a power-line zone without consent must be removed. The person who made it pays (act 251/2012 § 43 ods. 15). The gas operator can ask the cadastre for a note on a building in its zone made without consent (§ 79 ods. 5).
Does an easement pass to the buyer of the plot?
An easement tied to a property passes to the buyer with the property. A personal easement belongs to a person and ends at the latest with that person. Part C shows which kind you face. Three cases come up on plots.
- An easement of way. A building owner may have no other access and no ownership of the adjoining plot. Then a court can set up an easement of way (Civil Code § 151o ods. 3). See the entry on the right of passage easement.
- An easement of an energy operator. It arises by law, and the owner has the right to a one-off compensation (act 251/2012 § 11 ods. 8 and 9).
- An easement tied to a person. The entry names the beneficiary, and the easement ends with that person (Civil Code § 151p ods. 4).
What can I do when a zone or an easement covers my plot?
Neither one ends the project by itself. You have four options.
- Redraw the house. Use the strip for the driveway, parking or garden, and move the mass of the house. Test the layout on the plot before you buy.
- Ask for consent. The acts above allow work in the zone with the consent of the operator or an exception of the authority, usually on conditions. Do not count on it until you hold it in writing.
- Move the line. Whoever caused the need pays for the move, unless the owner of the line and that person agree otherwise. The operator does the work, or sets the conditions for another authorised person. The line stays the operator's (act 251/2012 § 45 ods. 2 and § 81 ods. 2).
- End or limit the easement. It ends by decision of an authority, by law, or by contract with entry in the cadastre. It also ends when a permanent change means the thing can no longer serve the beneficiary. If the burden becomes grossly out of proportion to the benefit, a court can limit or cancel it. The beneficiary gets adequate compensation (Civil Code § 151p ods. 1 to 3).
For an energy operator's easement, the owner has the right to a one-off adequate compensation for the area. Claim it from the operator within two years of learning that the operator used the easement, and at most within three years of that use. If you cannot agree on the sum, either side can ask the court within one year (act 251/2012 § 11 ods. 9 and 10). The act sets no sum.
What should I check before I pay the deposit?
- Read part C of the list vlastníctva, including the beneficiary of each easement.
- Ask every operator for a written statement with a drawing of its network on your parcel number. Keep proof of the request.
- Check the municipal plan and look at the plot for lines, roads, railways and forest within the distances above.
- Test the house layout on the plot with the zones drawn in.
- Put a condition into the reservation contract. If a statement or the extract shows a restriction that blocks the planned house, the deposit comes back. Ask a lawyer to word it.
The rest of the checks on a plot are in How to choose a plot.
