Service cavity

A service cavity is a space between the airtight layer and the interior lining of a wall. It carries cables and pipes, so they do not pierce the layer.

A service cavity is the space between the airtight layer and the interior lining of a wall, where cables, sockets, pipes and ventilation ducts run. In a timber frame house the airtight layer is usually a membrane or a board on the warm side of the frame. The service cavity sits on the room side of it. The installations live in the cavity, so the airtight layer itself stays whole.

Why does the service cavity sit in front of the airtight layer?

Airtightness depends on a continuous layer. Every box, cable or pipe that pierces that layer is a possible leak. The UK Passivhaus Trust guidance on building fabric names an internal service void as the ideal for walls. Then services do not penetrate the airtight and vapour barrier. The same guidance notes that a membrane on the inner face of a wall benefits from a service void that protects it. Once the layer is covered by a cavity, electricians can drill into the cavity and fix boxes to battens without touching the membrane.

The idea is simple, but it changes the build sequence. The airtight layer is installed first, taped with an airtight tape at the joints, and only then do the installers work in the cavity. Without the cavity, the electrician and the plumber cut through the layer that the builder has just sealed. Each penetration must then be planned and sealed.

How does a service cavity differ from the vapour retarder?

People sometimes treat the service cavity as a second vapour layer. It is not. It is an air space with installations in it. The vapour retarder and the airtight layer are the material layers that slow vapour and air. The table below separates the roles. For the wider idea of how tight the envelope must be, see airtightness.

ElementMain jobPosition in the wallTypical risk if damaged
Airtight layer (membrane, board or taped OSB)Stops air movement through the wallDirectly behind the service cavity, on the room side of the frameAir leaks and possible condensation in the construction
Service cavityCarries cables, boxes and pipes without piercing the airtight layerBetween the airtight layer and the interior liningPoor planning leads to fixings that reach the airtight layer
Interior lining (plasterboard or similar)Closes the wall on the room sideOn the room side of the service cavityLong fixings can pass the cavity and reach the layer behind

The table also shows why the cavity matters later, not only during construction. Passivhaus Trust guidance warns that polythene sheeting is vulnerable to damage during the build and during later alterations. A cavity gives later installers a space to work in, so they do not need to reach the airtight layer to add a socket.

What does a service cavity change in the wall build-up?

A service cavity adds depth to the wall. The designer must count that depth in the wall thickness, in window reveals and in the position of the insulation relative to the frame. Its thermal effect depends on how the cavity is closed and whether it holds insulation. Calculate the wall as built, not as drawn.

It also adds a trade decision. The cavity can be formed by battens fixed to the inner face of the airtight layer, with the lining fixed to the battens. The designer should show this in the drawings, so that the electrician and the plumber know where they may fix and where they may not.

How are services routed through a timber frame wall?

The sources describe two ways to handle services. The table sets out what each says.

QuestionWith a service cavityWithout a service cavity
Do services pass through the airtight layer?No. Cables and pipes run in front of the layerYes. Each crossing is an opening that must be sealed
Who must take more care?The installers still need a drawing that shows where they may fixThe designer and installers, because the Passivhaus Trust guide says services need more care in design and execution
Is a membrane at risk?The cavity protects a membrane on the inner facePolythene sheeting is vulnerable during the build and during later alterations
How is the result checked?A blower door test of the whole building, if possible during construction (EGGER)

What goes wrong when there is no service cavity?

The main failure is the penetration. Each cable or pipe that crosses the airtight layer needs a sealed detail, and in the wall it is easy to miss one. The EGGER guidance on timber construction recommends suitable tapes over panel joints and connections. It also recommends a blower door test of the building, if possible during construction. Air leaks cause heat loss and, in the worst case, condensation inside the construction.

The standard method for condensation risk does not model this. The Slovak standard STN EN ISO 13788 states that its method ignores air movement from the building into the construction. This covers leaks and air gaps. So a condensation calculation made with that method does not, on its own, show the effect of leaks from penetrations. The service cavity reduces the number of penetrations the installers must seal, but it does not replace the blower door test.

Is a service cavity required?

The UK Passivhaus Trust guide calls an internal service void the ideal and says a membrane on the inner face benefits from one. That is UK guidance, not a Slovak rule, and this page found no Slovak act that requires a service cavity. The same guide says that without a void, services need more care in design and execution. Plan, seal and check each penetration. Ask the builder who seals each crossing, which tape or collar is used, and when the airtightness is measured.

For a family house in Slovakia, the practical question is simple. Who will install the electrical and water work, and will they work in the cavity or through the layer? The answer changes the detail more than any single material choice.

Frequently asked questions

Is a service cavity the same as a vapour barrier?
No. The vapour control or airtight layer is the membrane, board or foil that slows air and vapour. The service cavity is the space in front of it, where cables and pipes run so that the layer is not pierced.
Does a service cavity make the wall thicker?
Yes. The depth of the cavity adds to the wall build-up. The designer must include it in the wall thickness, the window reveals and the detail at the insulation.
Can a timber frame wall be built without a service cavity?
Yes. The Passivhaus Trust guide calls an internal service void the ideal. It says that without one, services need more care in design and execution. Each penetration of the airtight layer must then be planned, sealed and checked before the lining is fixed.
Which tape seals the airtight layer where services cross it?
Use the airtight tape or sealing collar named in the detail drawing for that junction. Ask the installer which product is used and how the joint is checked.
How is the airtightness of a timber frame wall checked?
The building is tested with a blower door, and EGGER recommends doing it during construction if possible. The test measures the whole building, so it also catches leaks from penetrations.

Sources

  1. How to Build a Passivhaus: Rules of Thumb · Passivhaus Trust (UK) · Building fabric, section 1 Walls (introduction; timber frame; airtightness)
  2. Moisture protection (Planning and design for timber construction) · EGGER · Moisture protection, airtightness, windproofness
  3. STN EN ISO 13788 Tepelno-vlhkostné vlastnosti stavebných dielcov a konštrukcií. Vnútorná povrchová teplota na vylúčenie kritickej povrchovej vlhkosti a kondenzácie vnútri konštrukcie. Výpočtové metódy (ISO 13788: 2012) · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR (ÚNMS), catalogue · Predmet normy (scope)