Differential settlement

Differential settlement is uneven sinking of different parts of a building. It distorts the structure and can crack the walls.

What is differential settlement?

Differential settlement is the uneven sinking of different parts of one building, so that one section drops more than another. In Slovak it is called nerovnomerné sadanie. Some sinking is expected, because soil under a foundation compresses under load. The damage starts when the movement is not the same everywhere. A building that sinks evenly keeps its shape. One that sinks unevenly twists and cracks. The difference between the two points is the rozdiel sadania, and that difference is what cracks walls.

How does differential settlement differ from building settlement?

The general mechanism of soil compressing under a foundation is covered by building settlement. This term narrows the focus to the uneven part of that movement. The Canadian digest on foundation movements names three basic types: uniform settlement, tilt and non-uniform settlement. Non-uniform settlement is the type this term describes.

FeatureUniform settlementDifferential (non-uniform) settlement
Movement patternThe whole building sinks togetherParts of the building sink by different amounts
Effect on the structureGenerally less harmful to the building itselfAngular distortion, which can cause cracks or even structural failure
Other effectsCan still strain services such as water mainsCan be serious even when the subsoil is fairly uniform, if the loads vary

Why does uneven sinking crack a wall?

A wall is stiff, and a house is a frame of such walls and floors. When one support drops more than its neighbour, the wall bends or shears instead of moving as a whole. The digest measures this as angular distortion, the ratio of the differential settlement to the distance between supports. The digest gives a range of ratios. At 1/750, difficulties with sensitive machinery may occur. At 1/150, structural damage is to be feared. A ratio of 1/150 means, for example, that two supports 3 m apart settle 20 mm differently.

The STU textbook Konštrukcie spodnej stavby gives the same warning in Slovak terms. Larger but uniform settlement does not endanger a building, but uneven settlement is very dangerous for it and can cause serious deformation and cracks.

Loads matter as much as soil. The digest notes that if the loads on a foundation vary, the differential settlement can be more serious even when the subsoil is relatively uniform. A heavier part of a house next to a lighter part, on the same ground, is one way this happens.

What usually causes uneven settlement in a house?

The ground under a house is rarely uniform, and the causes tend to fall into a few groups:

  • Varying loads. Parts of the foundation carry different weights, even on the same soil.
  • Clay that shrinks and swells. The British Geological Survey (BGS) explains that clay soils shrink when dry and swell when wet. Uneven shrinkage beneath foundations can damage buildings.
  • Trees and hedges. Tree roots take water from the soil, and BGS lists planting, severe pruning or removal of trees and hedges as factors that enhance soil movement.
  • Drainage and leaks. BGS names changes to surface drainage and paving, and leaks from water supply pipes or drains, as causes of ground movement.

The STU textbook names two main reasons for uneven settlement. The first is unequal weight of different parts of the building. The second is uneven composition of the ground, for example a compressible layer of varying thickness. Where a compressible layer varies in thickness, a stiff foundation can limit the effect. Deep foundations that carry the load to firm ground can limit it too. Movement joints that run through the whole building down to the foundation base can also help. The textbook also requires that a repair lead to reliable removal of the cause of settlement. Several causes can act at once, so the cause has to be found before the crack is treated.

What does a differential settlement crack look like?

No single feature proves movement, but several features point toward it. Designing Buildings notes that stepped cracks tend to follow the lines of horizontal and vertical joints. It adds that cracks wider at the top or bottom may indicate foundation movement. BGS lists further signs of subsidence cracking that are useful during an inspection.

SignWhat it may suggestSource
Stepped crack following the mortar jointsMovement that the brickwork is followingDesigning Buildings
Crack wider at the top or bottomFoundation movement. The direction of widening suggests the direction of movementDesigning Buildings
Diagonal crack, wider from top to bottomOne of the subsidence signs listed by the ABI, as cited by BGSBGS
Crack more than 3 mm wideA sign to investigate, not a safety thresholdBGS
Crack visible inside and outside, or near doors and windowsAnother subsidence sign on the same listBGS

How serious is a differential settlement crack?

The BRE Digest 251 method, published by the Building Research Establishment, sorts crack damage into six categories by width and number. Its categories 0 to 2 cover cracks up to 5 mm and are aesthetic. Categories 3 and 4 are serviceability problems that affect weather-tightness and how doors and windows operate. Category 5 is a stability issue and is likely to require structural work.

BRE categoryType of issueWhat it affects
0, 1 and 2Aesthetic, with widths up to 5 mmAppearance, often just redecoration
3 and 4ServiceabilityWeather-tightness, and the operation of doors and windows
5StabilityLikely to require structural intervention

BRE calls its scheme a simplification. The category can change if the crack is widening over time, and the page advises consulting a building professional where damage is significant. The table is a guide for that conversation, not a verdict on a house.

How do you find out whether a crack is still moving?

Designing Buildings says it is important to establish whether cracking is static or progressive. Measuring answers that question. A crack gauge placed across the crack shows whether it opens, closes or stays put. A record of the crack width and position, with dated photographs and a scale, does the same. BGS describes seasonal movement of clay ground, so a record that covers a full year is more useful than one taken over a few weeks.

Not every crack is settlement. Shrinkage cracks, for example, come from materials changing volume, and they are a separate kind. See shrinkage crack. Telling them apart is part of the diagnosis.

What should you do when you suspect differential settlement?

Start by recording the cracks and then bring in a structural engineer. The engineer checks the cause, the ground and the history of the building, and the result is what decides the repair. A survey of the whole building, covering its condition as well as its cracks, is described in building condition survey. Techniques such as crack stitching join masonry across a crack. Choose them after the cause is known, because stitching does not stop the ground from moving.

Differential settlement is one of the causes behind a structural crack, which is a crack that affects load-bearing parts of the building.

Frequently asked questions

Is some settlement normal?
Yes. The National Research Council of Canada digest on foundation movements says uniform settlement and tilt, within reason, do not greatly affect a structure. The trouble starts when one part of the building sinks more than another, because that is what bends and cracks the walls.
What is the difference between differential settlement and building settlement?
Building settlement is the general downward movement of a foundation as the soil under it compresses. Differential settlement is the uneven form of that movement, where different parts of the same building drop by different amounts. The Canadian digest says uniform settlement, within reason, does not greatly affect a structure, so it is the uneven form that damages it.
Are all wall cracks caused by differential settlement?
No. The British Geological Survey notes that cracks can arise from other causes, so a crack alone does not prove subsidence. Designing Buildings advises finding out whether a crack is static or progressive. The pattern, the width and the direction of the crack help separate the causes, and a structural engineer should make the final call.
Does a crack wider than 3 mm mean the house is unsafe?
Not by itself. The British Geological Survey lists cracks more than 3 mm wide among the signs of subsidence. That is a sign to investigate, not a safety threshold. The BRE crack categories show that width alone does not decide the severity, since stability depends on the cause and the trend.
Can trees cause differential settlement?
They can, on clay soils. Tree roots take water out of clay, which shrinks. The British Geological Survey lists planting, severe pruning or removal of trees and hedges among the causes of enhanced soil movement. Uneven shrinkage beneath the foundations can damage the building.

Sources

  1. Canadian Building Digest 148: Foundation Movements · National Research Council of Canada (mirror hosted at MIT) · Types of settlement; Uniform versus non-uniform settlement; Angular distortion; Effect of varying loads
  2. Swelling and shrinking soils · British Geological Survey · What causes shrinking and swelling soils?; What are the effects of shrink-swell?
  3. Assessing cracks in houses · BRE (Building Research Establishment) · How cracks are assessed; When to consult a professional
  4. Cracking and building movement · Designing Buildings Wiki · What are the most common causes of cracks in buildings?; What do the shapes of cracks in buildings mean?; How to repair cracks in buildings
  5. Konštrukcie pozemných stavieb: Konštrukcie spodnej stavby · Slovenská technická univerzita v Bratislave, Stavebná fakulta (Juraj Žilinský a kol.) · Sadanie základov (p. 47); 22 Sanácie základov (p. 89)