Building Moratorium

A building moratorium is a decision of a planning authority that bans or limits construction in an area while a land-use plan is prepared.

What is a building moratorium?

A building moratorium (stavebná uzávera in Slovak) is a decision of a planning authority that bans or limits construction in an area during plan preparation. The authority may decide it for the whole planned area or a part of it. The purpose is to protect the future use of the land according to the plan that is being prepared. The rule is in § 30 of the Spatial Planning Act (200/2022 Z. z.), in force for this section since 1 April 2024. The Slovak search term is also written "stavební uzávěra" in Czech.

Who can declare a building moratorium?

The planning authority that prepares the plan declares it. For a municipal plan this is the municipality. Under § 6 ods. 2 písm. b) of the Act, the authorities that can use § 30 are the municipality and the self-governing region (samosprávny kraj). The Office for Spatial Planning and Construction of the Slovak Republic is a planning authority under § 6 ods. 2 písm. a), but § 30 ods. 1 names only the municipality and the region.

The decision applies while the plan is in preparation. The authority can issue it only after it publishes the notice of the start of preparation. It must issue it before the discussion of the draft plan starts (§ 30 ods. 2). A moratorium is therefore tied to a municipal land-use plan or another planning document that is being prepared or changed. The same applies to a spatial plan amendment.

What does the moratorium decision contain?

The decision must contain two things (§ 30 ods. 3). The first is the reason why the moratorium is necessary to secure the future use of the area under the plan. The second is the period for which it is declared. A decision without a reason that links the ban to the plan does not meet this rule.

How long can a building moratorium last?

A building moratorium can last up to 24 months from the day the decision becomes final (§ 30 ods. 5). It ends earlier, on the day the planning document is approved, if that day comes first. The planning authority can extend it by at most 12 months. It does this by changing the decision, and the rules for the original decision apply to the change. The longest possible period is therefore 36 months, and the plan approval still ends it earlier. Amendment 243/2026 Z. z. does not change § 30 in the text read for this page.

StepTime limitSource
Appeal against the decision15 days from delivery§ 30 ods. 4
First period of the moratoriumup to 24 months from the final decision, or less if the plan is approved first§ 30 ods. 5
Extension by changing the decisionup to 12 more months§ 30 ods. 5

What does a building moratorium not stop?

The Act lists exceptions. A moratorium does not apply to maintenance work (udržiavacie práce) and to the farming of agricultural land or forest land (§ 30 ods. 1). It does not concern a building with a consenting binding opinion (súhlasné záväzné stanovisko) under § 24, issued before the decision (§ 30 ods. 6).

A transitional rule covers older permits. A moratorium does not apply to construction under a valid building permit or a final zoning decision. The permit or decision must come from the rules in force until 31 March 2024 (§ 40 ods. 11).

The Act does not say that existing use ends. An owner who only repairs a house stays outside the moratorium.

ActivityUnder the moratoriumSource
New construction in the areaBanned or limited, as the decision says§ 30 ods. 1
Maintenance workNot affected§ 30 ods. 1
Farming of agricultural land and forest landNot affected§ 30 ods. 1
Building with a consenting binding opinion issued before the decisionNot affected§ 30 ods. 6
Building under a permit or zoning decision issued under rules in force until 31 March 2024Not affected§ 40 ods. 11

How is the owner told, and can the owner appeal?

The planning authority delivers the decision to the owner and to the administrator of each property in the area by public notice (§ 30 ods. 4). It also publishes the decision on its website, on its official board and in another way usual in the place. The owner and the administrator are the parties to the proceedings. They can appeal within 15 days of delivery. The authority that issued the decision may add evidence and comment on the appeal. It then passes the case to the Office, which continues the proceedings.

The Administrative Procedure Code applies to these proceedings only through § 30 of the Spatial Planning Act. The Act also switches off several of its sections for the moratorium (§ 37).

How is a building moratorium different from expropriation?

A building moratorium bans or limits construction and does not change who owns the land. Expropriation is a different procedure under the Act on expropriation of land and buildings (282/2015 Z. z.). It takes or limits ownership by force for a public purpose, under that Act. The Act on spatial planning gives the moratorium no power to take land.

How do I find out if my plot is under a building moratorium?

Look at the website and the official board of the municipality, since § 30 ods. 4 requires publication there. Ask the municipality for the moratorium decision and the area it covers. Its planning staff or its building office can show it. A plot that lies in a zoning or building permit procedure should be checked against the decision before a design is started.

Frequently asked questions

What is a building moratorium?
A building moratorium (stavebná uzávera) is a decision of a planning authority that bans or limits construction in an area during plan preparation. The rule is in § 30 of the Spatial Planning Act (200/2022 Z. z.).
How long can a building moratorium last?
Up to 24 months from the day the decision becomes final, and it ends earlier if the planning document is approved first. The planning authority can extend it by at most 12 months (§ 30 ods. 5).
Can I appeal a building moratorium?
Yes. The owner and the administrator of a property in the area can appeal within 15 days of delivery of the decision (§ 30 ods. 4).
Can I still repair my house during a building moratorium?
Yes. A moratorium does not apply to maintenance work and to the farming of agricultural land or forest land (§ 30 ods. 1).
Does a building moratorium stop a building that already has a permit?
Not always. It does not concern a building with a consenting binding opinion issued before the decision (§ 30 ods. 6). It also does not apply to construction under a valid building permit or final zoning decision from the rules in force until 31 March 2024.
What is the difference between a building moratorium and expropriation?
A moratorium bans or limits construction for a time and ownership does not change. Expropriation takes or limits ownership by force and follows Act 282/2015 Z. z.

Sources

  1. Zákon č. 200/2022 Z. z. o územnom plánovaní (úplné znenie od 01.03.2026) · Slov-Lex · § 30, § 6 ods. 2, § 37
  2. Zákon č. 200/2022 Z. z. o územnom plánovaní (prechodné ustanovenie o stavebnej uzávere) · Slov-Lex · § 40 ods. 11
  3. Zákon č. 282/2015 Z. z. o vyvlastňovaní pozemkov a stavieb a o nútenom obmedzení vlastníckeho práva k nim · Slov-Lex
  4. Zákon č. 243/2026 Z. z. (novela stavebného zákona 25/2025) · Slov-Lex