Ground-Bearing Floor Build-Up

8 min read
The ground-floor slab of a house under construction with grey insulation boards, a polyethylene separating sheet, a white perimeter strip along the walls and freshly poured screed in one corner, seen from standing height, no people

Which layers make up a ground-bearing floor, and in what order?

A ground-bearing floor sits on the soil, so it has to stop ground moisture, limit heat loss into the ground, keep radon out where needed and carry the screed and the finish, all at the same time. A floor build-up is therefore an order, not a shopping list: the same layer in the wrong place stops doing its job.

The table shows the typical order from the bottom up, and the exact build-up comes from the design. The choice of foundations is covered in the article on strip footings, slabs and foam glass. This text continues above them. If you are still choosing the structural system of the house, start with the comparison in What to build a house from: masonry, timber frame or CLT.

LayerPurposeTypical materialCommon mistake
Compacted subbaseA level, load-bearing formationAggregate as designedFill placed without compaction in layers, which settles later
Blinding concreteA clean, level base for the membranesLower-grade concreteSharp edges and bumps that damage the membrane
WaterproofingProtection against ground moisture, and radon if designed for itBitumen sheets or a synthetic membraneNo connection to the wall damp course, unsealed penetrations
Thermal insulationLimits heat loss into the groundFloor boards of EPS or XPSBoards with low compressive strength and open joints
Separating layerSeparates the screed from the insulationPolyethylene sheetUnlapped and unconnected joints in the sheet
Perimeter stripSeparates the screed from walls and door framesPolyethylene stripGaps at columns, door frames and corners
ScreedA level surface, load spreading, embedding heating pipesCement or anhydriteLaying the floor without a moisture test
FinishThe surface you live onTiles, timber, vinylChosen after the screed is poured, ignoring levels

What does the decree say about a ground-bearing floor?

General technical requirements for buildings are still set by decree 532/2002 Z. z. Under the Building Act 25/2025 Z. z. it stays in force until new implementing regulations take effect, at the latest until 31 March 2027 (§ 84(23)).

Two provisions matter for a ground-bearing floor. An underground construction that separates the interior from the soil or from the foundation must be insulated against ground moisture, groundwater and heat flow into the ground, and where needed against the ingress of radon and other harmful substances (§ 23(3)). A floor together with the slab must, according to the purpose of the room, provide among other things structural capacity, resistance to impact and permanent deformation, impact sound insulation, thermal insulation and appropriate heat absorption (§ 32(1)). Services laid in the floor must not impair the properties of the floor (§ 32(5)).

Is waterproofing enough, or do you also need a radon barrier?

The decree names moisture and radon separately: waterproofing stops water, radon is a gas. Under act 87/2018 Z. z., the designer of a residential building that has a basement or a first above-ground storey meant for long-term occupancy must take preventive measures so that radon activity concentration in indoor air does not exceed the reference level of 300 Bq/m³ as an annual average (§ 130(1)). The owner must have it measured within one year of starting to use the building (§ 130(3)).

Decree 57/2024 Z. z. names as preventive measures determining the radon index of the plot, a measure against radon ingress from the subsoil, venting soil radon outside the building, making the ground-contact constructions tighter together with depressurisation under the building, or other construction measures (§ 6(1)). The method for the index is in annex 6 (§ 5).

Whether the waterproofing layer can also serve as a radon barrier is decided by the design, based on the radon index of the plot and the manufacturer's data for the material. With a gas, continuity is what counts: every drain, water and cable penetration must be sealed before it disappears under insulation and screed.

How thick should the floor insulation be?

Decree 364/2012 Z. z. requires the thermal assessment to calculate the thermal transmittance of every build-up of opaque constructions and to assess water vapour condensation within them (annex 1, point 1(e)). Under annex 3, the thermal requirements for constructions are set by a technical standard, namely STN 73 0540-2+Z1+Z2. The standard is paid, so we quote no values from it.

The designer therefore calculates the insulation thickness from the required value. For a floor on the ground, the soil under the house enters the calculation too. For heat transfer via the ground, the standard STN EN ISO 13370 applies, which amendment Z1 of STN 73 0540-2 lists among its cited standards. The resulting thickness depends mainly on:

  • the thermal conductivity of the insulation, stated by the manufacturer in the product documents,
  • the energy performance level the house is meant to reach,
  • where the insulation sits: on top of the structural slab under the screed, under the slab, or split between both,
  • the connection to the plinth and wall insulation, so that no thermal bridge forms at the floor edge.

The second property is compressive strength. The insulation under the screed carries the screed, furniture and people, so the board grade is chosen by the load in the design, not by price.

Why do the perimeter strip and the separating layer decide how the screed behaves?

A screed is a slab that moves slightly as it hardens, dries and changes temperature. The separating layer keeps it apart from the base and the perimeter strip keeps it apart from walls, columns and door frames. A screed manufacturer describes them the same way in its range: the separating sheet separates the screed from the base and the perimeter strip separates screeds and levelling compounds from vertical wall constructions. According to the manufacturer, the separating sheet is laid with a 5 to 10 cm overlap and at bounding constructions it is turned up to form a tub, or a strip with an integrated sheet is used. If the strip has a sheet, it goes under the separating sheet and the two are joined watertight.

A screed laid on thermal insulation and separated from the walls is called floating by the manufacturer, and the whole assembly is a floating floor.

On the ground floor there is no living space underneath, yet separation from the walls still matters: a screed bearing against a wall cannot move freely. According to the data sheet for the Ceresit DC levelling compound, perimeter joints in the base must be kept through the levelling layer as well. The manufacturer of the perimeter strip says it should protrude above the top edge of the finish, and the protruding part is removed only after the finish is laid.

Cement or anhydrite screed?

Screed materials and floor screeds are covered by STN EN 13813, as the national annex to the concrete standard STN EN 206+A2/NA also states. Cement and anhydrite screeds differ in their binder. An anhydrite screed is, in the manufacturer's words, a poured screed based on calcium sulfate, that is, gypsum. Properties vary with the mix, so the table compares two specific products from one manufacturer and the requirements of one levelling compound, as their documents state them.

PropertyCement screed (Baumit Poter)Anhydrite screed (Baumit Alpha 2000)
BinderCementCalcium sulfate (gypsum)
Class stated by the manufacturerCT-C20-F5CA-C20-F5
Wet areas and garagesListed by the manufacturer as suitable for garages and wet areasNot recommended by the manufacturer for wet areas such as garages, and it points to its cement screed
Minimum thickness with underfloor heating45 mm + pipe diameter35 mm + pipe diameter
Surface preparation before Ceresit DCRemove the cement laitance by machine and vacuumAlways sand and vacuum
Residual moisture before Ceresit DC, unheatedbelow 2 CM %below 0.5 CM %
The same with underfloor heatingbelow 1.8 CM %below 0.3 CM %

The table gives a rule of use, not a ranking: anhydrite for dry interiors, cement for wet areas too. Anhydrite is sanded before levelling and its permitted moisture is much lower. For its cement Poter, Baumit gives thicknesses of 35 to 45 mm when bonded, 35 to 70 mm when unbonded and 45 to 70 mm when floating.

How long does screed take to dry, and when can the floor go down?

Until a measurement shows that moisture has dropped below the limit the manufacturer sets for that screed and that finish. Walkable is not the same as ready for flooring. The manufacturer states that its anhydrite screeds are walkable after just 24 hours, and in the same place advises checking the residual moisture of the screed and keeping to the curing breaks before laying floor coverings.

Before the Ceresit DC levelling compound is applied to insulated floating bases, its data sheet requires residual moisture below 2 CM % for an unheated cement screed and only below 0.5 CM % for an anhydrite one. This is a condition for that compound, not a general limit for every floor covering: for tiles, timber or vinyl, the limit of the covering manufacturer and the screed manufacturer applies. Agree with the contractor before the pour how the screed moisture test is done, who does it and where samples are taken.

The same sheet requires the base under the levelling compound to be protected against rising moisture. If the waterproofing under the screed is missing or damaged, no amount of drying solves the problem, because moisture keeps coming from the ground.

What changes with underfloor heating?

With underfloor heating the screed becomes the heat emitter. The pipes lie above the thermal insulation and the screed embeds them. Several things change as a result:

  • Screed thickness. The manufacturer gives a minimum thickness over the pipes: 45 mm plus the pipe diameter for cement screed, 35 mm plus the pipe diameter for anhydrite. The build-up height must be known before door frames are set.
  • Anhydrite poured in two steps. For Alpha 2000 the manufacturer describes a first layer up to the top of the pipes and, once it has set, usually the next day, a second layer.
  • Stricter moisture limits. The limits before the Ceresit DC compound are lower for heated screeds, 1.8 CM % for cement and 0.3 CM % for anhydrite.
  • Perimeter strip. For screeds with underfloor heating Baumit prescribes perimeter strips at least 10 mm thick, and at least 5 mm for unheated ones.
  • Insulation under the pipes. Heat from the pipes should go into the room, not into the soil.
  • Services in the floor. The manifold, supply pipes and other services must not impair the properties of the floor (decree 532/2002, § 32(5)). Their routes belong on the build-up drawing so they do not cross the heating pipes within the screed depth.

What changes with a slab on foam glass gravel?

Here the main thermal insulation moves under the structural slab. European Technical Approval ETA-13/0549 for Misapor foam glass gravel, valid from 2013 to 2018, listed as intended uses a thermal insulation and frost protection layer under floor slabs with a load-bearing function, and a layer that breaks capillary rise and drains. Under load-bearing structures, it said, the gravel is compacted to obtain optimal load-bearing capacity. For FOAMGLAS T4+ foam glass boards, European Technical Assessment ETA-17/0903 describes use as a load-bearing layer and thermal insulation outside the waterproofing.

With such insulation under the slab, the thermal insulation lies outside the waterproofing, so the design places the moisture and radon layer separately.

Frequently asked questions

Can screed be poured directly onto the waterproofing without thermal insulation?
Technically yes. The screed manufacturer also lists an unbonded screed on a separating layer. However, decree 532/2002 requires the underground construction to be insulated against heat flow into the ground as well (§ 23(3)). Thermal insulation therefore has to be somewhere in the build-up, above the slab or below it.
Should the waterproofing go below or above the thermal insulation?
The insulation material and the design decide. In the build-up in the table the waterproofing lies below the thermal insulation, but that is the typical order, not a rule. Products assessed for use outside the waterproofing, such as foam glass boards under ETA-17/0903, can sit below it. The order must be drawn on the build-up drawing.
Does anhydrite screed need a separating sheet?
The manufacturer describes three ways of laying it: bonded directly to the base, unbonded on a separating layer, and floating on thermal insulation. With an unbonded or floating screed there is therefore a layer between the screed and the base. The sheet manufacturer prescribes it with a 5 to 10 cm overlap.
Can a dehumidifier speed up screed drying?
Some products allow it under precise conditions. For the Ceresit DC levelling compound applied in thicker layers, for example, the manufacturer allows drying to be sped up with a dehumidifier no sooner than 24 hours after application. For a screed, its own manufacturer's instructions apply, and readiness is decided by a moisture test, not by the number of days the dehumidifier ran.
Is anhydrite screed suitable for a bathroom?
The maker of Alpha 2000 does not recommend it for wet areas such as public showers, swimming pools or garages, and points to its cement screed. For a domestic bathroom, check its use in the product data sheet and design waterproofing under the tiles with your designer.
Do I have to deal with radon if the house has a ventilated air gap under the floor?
Act 87/2018 exempts from the preventive-measures duty a residential building whose first above-ground storey is separated from the ground by a layer of freely flowing air (§ 130(1)). The same exemption applies to the owner's measurement duty (§ 130(3)). A house with a floor directly on the ground has no such layer, so the exemption does not apply to it.
Who is responsible for the correct floor build-up?
The designer draws up the build-up and the contractor must build it to the design. Changes of material or thickness during construction, such as cheaper insulation or a thinner screed, should be agreed with the designer first, because they change the thermal calculation and the floor levels.

Sources

  1. Vyhláška MŽP SR č. 532/2002 Z. z., ktorou sa ustanovujú podrobnosti o všeobecných technických požiadavkách na výstavbu a o všeobecných technických požiadavkách na stavby užívané osobami s obmedzenou schopnosťou pohybu · Ministerstvo životného prostredia SR, via Slov-Lex · § 23 ods. 3; § 32 ods. 1 and 5
  2. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 84 ods. 23
  3. Zákon č. 87/2018 Z. z. o radiačnej ochrane a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 130 ods. 1 and 3
  4. Vyhláška MZ SR č. 57/2024 Z. z., ktorou sa ustanovujú podrobnosti o obmedzovaní ožiarenia pracovníkov a obyvateľov z prírodných zdrojov ionizujúceho žiarenia · Ministerstvo zdravotníctva SR, via Slov-Lex · § 5; § 6 ods. 1
  5. Vyhláška MDVRR SR č. 364/2012 Z. z., ktorou sa vykonáva zákon č. 555/2005 Z. z. o energetickej hospodárnosti budov a o zmene a doplnení niektorých zákonov v znení neskorších predpisov · Ministerstvo dopravy, výstavby a regionálneho rozvoja SR, via Slov-Lex (binding PDF) · Príloha č. 1 bod 1 písm. e); príloha č. 3 písm. d) and footnote 2
  6. STN 73 0540-2: 2012/Z1: 2016 Tepelná ochrana budov. Tepelnotechnické vlastnosti stavebných konštrukcií a budov. Časť 2: Funkčné požiadavky. Zmena 1 (náhľad) · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR
  7. STN EN 206 + A2/NA Betón. Špecifikácia, vlastnosti, výroba a zhoda. Národná príloha (náhľad) · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR
  8. Baumit Alpha 2000, product page · Baumit, spol. s r.o.
  9. Cementové potery · Baumit, spol. s r.o.
  10. Anhydritový samonivelačný poter: Ideálny na podlahové kúrenie · Baumit, spol. s r.o.
  11. Ceresit DC Anhydritová samonivelizačná podlahová hmota, technický list · Henkel Slovensko, spol. s r.o. · Príprava podkladu; version valid from 01/2021
  12. European Technical Approval ETA-13/0549, MISAPOR, factory made cellular glass loose fill · Deutsches Institut für Bautechnik (DIBt) · 1.2 Intended use
  13. European Technical Assessment ETA-17/0903, FOAMGLAS-Board T4+ · Deutsches Institut für Bautechnik (DIBt) · Section 2, intended use
  14. Baumit Separačná fólia FE · Baumit, spol. s r.o.
  15. Baumit Okrajová dilatačná páska PE · Baumit, spol. s r.o.

Topic

  • Materials and timber