Separating layer

A separating layer is a thin foil laid between the insulation and a floating screed that stops the screed bonding rigidly to its base.

What is a separating layer in a floor build-up?

A separating layer (separačná vrstva) is a thin sheet, usually polyethylene foil, that stops a screed from bonding firmly to the layer below it. Baumit's Slovak technology guide defines it as the layer that prevents a rigid connection between the screed and its base. In a floating screed (plávajúci poter) the layer below is the insulation, so the foil lies on the insulation boards. The screed goes on top of the foil.

The foil carries no load and gives no thermal insulation. Its job is separation. The screed rests on the foil and not on the base. The slab can then move freely when it shrinks or warms.

Where does the separating layer sit in a floating screed?

The separating layer sits between the insulation and the screed. Baumit's screed sheet describes the build-up this way. Floor insulation boards, or a layer of lightweight concrete, form the insulation layer. A separating foil divides that layer from the screed. The guide names the foil Baumit Separačná fólia FE and says it separates the screed from the thermal insulation.

The same guide sets two conditions on the layers around the foil. The insulation must be a material with small deformation under load. The screed must also be separated from walls and other vertical parts by a flexible edge strip, which is a different component. For that strip, see edge insulation strip.

Baumit names two cases where the foil is not used. If a special sound-insulating underlay is chosen, the screed is laid straight onto that resilient underlay without the foil. If a system board or mat holds the heating pipes, the foil is no longer needed. Both are Baumit's instructions for its own system, so ask the screed supplier before you leave the foil out.

How wide should the overlaps be and how should the foil be laid?

Lay the foil flat, without folds, on a prepared base, and pour the screed straight after it. Baumit's data sheet for its 0.05 mm PE separating foil recommends overlaps of at least 100 mm. Baumit Slovakia’s paper separating foil FE is a different product: its product page says to lay it with overlaps of 5 to 10 cm. It also allows butt joints taped with a suitable adhesive tape. The sheet gives the reason: protection against screed mix leaking through. It also says the foil must not span cavities in the base. The figures below belong to this one product. Another maker's sheet may give other values. The sheet of the product you install governs.

DetailBaumit PE separating foil (Baumit data sheet, 2026)
Thickness0.05 mm, LDPE
JointsOverlap of at least 100 mm, or butt joints taped
Voids in the baseThe foil must not span them
ScreedApply the screed immediately after the foil
Temperature+5 °C recommended for air, material and base during installation
UV lightDo not expose for long, UV resistance is not declared

This sheet gives no wall upturn height. No other manufacturer document opened for this page gave one for wet screed. Show any upturn on the detail drawing and agree it with the screed supplier. A UK manufacturer guide gives other overlap and upturn figures. It covers dry floors of chipboard and fibre boards, so this page does not use them.

Does the separating layer stop screed cracking?

Not by itself. The foil removes the rigid bond to the base, so the screed can move as a free slab. Baumit's guide says the separating layer must be continuous. A break in it would form a rigid connection that blocks the movement of the slab.

Other parts take up the movement. The guide uses an edge strip around the perimeter. It also uses movement joints across the screed, made with an edge strip and an L profile. For cement screed without heating, it limits bays to 40 m2. Sides are at most 8 m long, in a ratio of at most 1:2. These are one manufacturer's figures, so agree the bay layout with your screed supplier. See expansion joint for the joints in the screed field.

How does the separating layer affect impact sound?

The foil is not what insulates impact sound. In Baumit's build-up the insulation layer consists of floor insulation boards or impact-noise materials. The foil only separates that layer from the screed. A thin foil does not replace the resilient layer and should not be counted as part of it.

Sound can still bypass the floating layer where the screed touches a wall. Baumit says its edge strip also stops noise passing from the floor into vertical structures. This path has a name: flanking transmission. For the layer that does the acoustic work, see impact sound insulation.

How is a separating layer different from an insulation layer?

Both layers sit under the screed, so they are often confused. They have different jobs, as the table shows for a floating floor.

FeatureSeparating layerInsulation layer
Main jobPrevents a rigid bond between screed and baseReduces heat loss and, in suitable products, impact sound
Typical materialThin polyethylene foil, for example 0.05 mm in Baumit's sheetFloor insulation boards, such as EPS or XPS or mineral wool, with small deformation under load
ThicknessSet by the productSet by a thermal calculation, according to Baumit's guide

Confusing the two leads to specification errors. A floor with insulation and no separating layer lets screed mix run into the joints between boards. A floor with foil and no suitable insulation has no thermal performance.

What should a Slovak designer check on a floating floor?

This page draws on manufacturer documents from Baumit and Ceresit. It does not rest on a Slovak statutory rule for separating layers. No Slovak act was part of this check. Baumit and Ceresit both cite STN 74 4505 (2013), Podlahy. Spoločné ustanovenia, as the design basis for floors. Its text is behind a paywall, so this page did not read it. For a Slovak project, check these points:

  • the foil's data sheet, for overlap, taping, installation temperature and UV exposure,
  • the screed supplier's guidance, for thickness (Baumit recommends 45 to 70 mm for its floating screed) and bay layout,
  • the insulation maker's data, for deformation under load and impact sound performance,
  • the edge strip and any upturn, drawn on the detail and checked on site before the pour.

Use the Slovak names separačná vrstva and tepelná izolácia on the drawings, so the contractor can match them to the product sheets.

Frequently asked questions

Is a separating layer the same as a vapour barrier?
No. Baumit's sheet gives the PE foil only a separating role. Moisture protection of a floor on the ground is a separate layer, such as waterproofing, set by the design. Baumit does name a waterproofing membrane as an alternative separating layer under a separated screed on a concrete base.
Can the screed be poured straight onto the insulation?
Not with Baumit's standard system. Its guide places a separating foil between the insulation boards and the screed. The exception is a special sound-insulating underlay, where Baumit lays the screed directly on it. Ask the screed supplier before you leave the foil out.
How much overlap does the foil need?
Baumit's data sheet for its PE foil recommends overlaps of at least 100 mm, or taped butt joints. That is one product's figure. Follow the sheet of the foil you install.
Why does a floating screed need a strip at the walls?
So the screed can move freely as a slab. Baumit's guide separates the screed from walls with an edge strip and says the strip also stops noise passing into the walls. Baumit gives a minimum strip thickness of 5 mm for unheated and 10 mm for heated screed.
Does the separating layer make a floor quieter?
Not on its own. In Baumit's build-up the insulation boards or impact-sound materials do the acoustic work, and the foil only separates them from the screed.
How long can the foil lie uncovered?
Not long. Baumit's data sheet says the foil is meant for immediate installation and should not be exposed to UV light for long. It also says to apply the screed immediately after laying the foil.

Sources

  1. Baumit Separační PE fólie, technický list (Baumit separating PE foil, technical data sheet) · Baumit, spol. s r.o. (manufacturer, Czech Republic) · Výrobek, Použitie, Zpracování, Upozornění a všeobecné pokyny (sheet dated 02-04-2026)
  2. Technologický predpis Baumit Potery a podlahové stierky (Baumit technology guide for screeds and levelling compounds) · Baumit, spol. s r.o., Bratislava (manufacturer, Slovakia) · 1.1 Termíny a definície, 1.3.2, 1.4.1, 3.1, 3.1.4, 3.2.2, 3.2.3, 3.6.1, 4.2.3, 4.6.1, 5.2.2 (valid from 02/2022)
  3. Baumit Poter, technický list (Baumit Screed, technical data sheet) · Baumit, spol. s r.o. (manufacturer, Slovakia), copy hosted by Hornbach · Podklad, Informácie a všeobecné pokyny (PDF created 2018-08-15)
  4. Baumit Separačná fólia FE · Baumit, spol. s r.o. (Slovakia)