Humidity-variable vapour retarder
A humidity-variable vapour retarder is a membrane whose sd value falls as humidity rises, so a wall or roof can dry towards the room.
A humidity-variable vapour retarder is a membrane whose sd value changes with the relative humidity around it. The TU Dresden research guide says it becomes tighter at the low room humidity of winter. It becomes more open at higher humidity, for example in summer when moisture dries towards the room. That behaviour gives a small moisture load in winter and a large drying reserve in summer. The guide links this to a higher tolerance for faults.
What sd value does a humidity-variable membrane have?
The sd value is the equivalent thickness of still air that resists vapour as much as the layer does. A conventional retarder has one sd value. A humidity-variable membrane has a range, and the range is the point of the product. The table gives the figures that one manufacturer, Pro Clima, publishes for its INTELLO membrane. These are product values, not general values.
| Condition | Value stated for INTELLO | Where it is stated |
|---|---|---|
| Open state, summer | sd of 0.25 m | Pro Clima product page |
| Closed state, winter | sd of over 25 m | Pro Clima product page |
| Spread between the two states | a variation of a factor of over 100 | Pro Clima product page |
| Single fixed value, EN 1931 test | sd of 14 m | Pro Clima technical specifications |
The technical specifications quote the variable range under EN ISO 12572. The ÚNMS catalogue entry for that standard describes a cup-method procedure under isothermal conditions. The entry covers the 2003 edition, which the 2017 edition replaces. The manufacturer does not state the humidity conditions behind the 0.25 m and over 25 m values. Read the range as a product claim until the full data sheet shows the test conditions.
The research guide gives a design target for variable retarders in internal insulation, not a product value. It says the sd value should lie above about 2 m in winter and below 0.5 m in summer. The guide's classes follow the German standard DIN 4108-3. In that scheme an sd value of 0.5 m or less is vapour-open, and 10 m or more is vapour-inhibiting or tighter. The INTELLO figures fall in those two ranges.
Why does opening let a build-up dry?
Moisture that enters a timber roof or an insulation layer has to leave it again. A fixed high-resistance layer limits drying towards the room all year. The guide says a retarder with a constant high sd value can also hinder drying inwards in summer where drying is needed. A humidity-variable layer becomes more open when the humidity at the membrane is high, so moisture can move towards the room. It becomes tighter again when the humidity falls.
Bunkholt and co-authors measured an unventilated timber-frame roof with a smart vapour barrier in Norway. Moisture on the warm side of the rafters stayed below 15 weight-% for the first 15 months. On the cold side it rose to close to 25 weight-% in winter, which the authors link to moisture built into the construction. It fell to around 15 weight-% when summer arrived. The authors call this an expected redistribution of moisture and say it indicates possible drying. Only the abstract was read here, so this is a field observation of one roof and not proof of the drying path.
How is it different from a standard vapour retarder?
A standard vapour retarder keeps one resistance all year. The humidity-variable type has a low and a high state. The table compares them.
| Property | Fixed vapour retarder | Humidity-variable membrane |
|---|---|---|
| Resistance at low humidity, as in winter | One value, held all year | High |
| Resistance at high humidity, as in summer | The same value | Low |
| Drying towards the room in summer | Limited by the fixed value | Enabled by the lower value |
| Figure in product data | A single sd value from one test | A range, with the test standard named |
The comparison in product data only means something when the test conditions match. A single sd value tells you one state, while a range tells you two.
Where is it used?
The Dresden guide lists a family of variable vapour-retarding internal insulation systems. They combine a vapour-open fibre insulation, for example mineral or natural fibre, with a retarder of variable sd value. See internal insulation. The field study above concerns a timber roof. Internal insulation carries the risk that the cold wall collects moisture, which the page on interstitial condensation describes.
The guide asks for airtight connections on the room side in all systems. An sd value describes diffusion only, so joints and penetrations still need airtight detailing. See airtightness. The INTELLO specifications say the product suits structures open or closed to diffusion on the outside after appropriate design calculations. Check the approval that covers your specific build-up.
What should you check before specifying one?
This checklist is the advice of this page, not a rule from the sources. Compare it with the full product documentation.
- The test standard and the humidity conditions behind each sd figure.
- Whether the approval covers your position, such as roof, wall or internal insulation.
- The installation rules, including the sealing of joints and the detailing at penetrations.
- Whether the rest of the build-up is compatible with the membrane.
A product range is an input to the moisture calculation, not its result.
What do common misconceptions get wrong?
The first misconception is that the membrane is vapour-open all the time. The manufacturer's figures show it is tight in its closed state, with an sd value of over 25 m for INTELLO. The second is that the open state guarantees drying. The range describes the material, and the drying result depends on the whole build-up and the climate. The third is that the membrane removes the need for airtightness. It does not, because an sd value describes diffusion and not air leakage.
Frequently asked questions
- What is a humidity-variable vapour retarder?
- It is a membrane whose resistance to water vapour changes with the relative humidity around it. It is tighter at low humidity, as in a heated room in winter, and more open at high humidity, for example when moisture dries towards the room in summer.
- How much does its sd value change?
- For the INTELLO membrane, Pro Clima states an sd value of 0.25 m in summer and over 25 m in winter, a variation of a factor of over 100. The manufacturer does not state the humidity conditions behind those two values. The TU Dresden guide names a design target of above about 2 m in winter and below 0.5 m in summer.
- Why does the sd value matter for drying?
- Moisture in a timber or insulation layer can only leave through the layers on either side. A constant high sd value can hinder drying towards the room in summer. A low sd value in the open state lets the moisture move out.
- Is it used in internal insulation?
- Yes. The TU Dresden guide lists systems that combine a vapour-open fibre insulation with a retarder of variable sd value. It describes them as giving a small moisture load in winter and a high drying reserve in summer.
- Does a humidity-variable membrane replace airtightness?
- No. The sd value describes how vapour diffuses through a layer, not how air leaks through joints and penetrations. The guide asks for airtight connections on the room side in all internal insulation systems.
- What should I check on a data sheet before specifying one?
- Check the test standard and the humidity conditions behind each sd figure, and whether the approval covers your build-up and position. Ask the supplier for the full data sheet, because the pages used here do not state the humidity conditions.
Sources
- Hydrosafe high-performance vapour check (INTELLO), how it works · Pro Clima (manufacturer web page) · INTELLO humidity-variable sd value
- INTELLO, technical specifications (All-round vapour control membrane) · Pro Clima (manufacturer web page) · Technical data: sd values
- STN EN ISO 12572, Hygrothermal performance of building materials and products (catalogue entry) · Úrad pre normalizáciu, metrológiu a skúšobníctvo SR (ÚNMS), catalogue · Scope
- Pitched unventilated wood frame roof with smart vapour barrier: field measurements · Journal of Physics: Conference Series, vol. 2069 (IBPC 2021), doi 10.1088/1742-6596/2069/1/012007 · Abstract
- Leitfaden Fassadensanierung und Innendämmung (CORNET / IN2EuroBuild) · TU Dresden, Institut für Bauklimatik / CORNET-IN2EuroBuild research project · 4.2 Einteilung von Innendämmsystemen, Variabel dampfbremsende Innendämmsysteme