Hazardous construction waste
Hazardous construction waste is demolition and building waste that the waste catalogue marks as hazardous, such as asbestos, and must be kept apart.
What is hazardous construction waste?
Hazardous construction waste is building and demolition waste that the waste catalogue marks as hazardous, so it needs stricter handling than ordinary demolition waste. The regime comes from the waste act, zákon č. 79/2015 Z. z. o odpadoch. The act applies its hazardous waste rules to waste with hazardous substances. The waste must also meet at least one catalogue criterion for hazardous properties (§ 25 ods. 8). The waste holder must classify the waste correctly under the catalogue (§ 14 ods. 1 písm. a)). Slovak texts call it nebezpečný odpad, and the building-site version is nebezpečný stavebný odpad.
The catalogue is decree 365/2015 Z. z. It gives each waste a six-digit code. Hazardous wastes carry the letter N and all other wastes carry the letter O (§ 1 ods. 2 of the decree).
Which fractions in demolition waste are hazardous?
The clearest case is azbest (asbestos). The catalogue lists building materials containing asbestos under code 17 06 05 and insulation materials containing asbestos under code 17 06 01, both marked N. Other fractions are hazardous only when they contain hazardous substances, so a label or a name does not settle the question. The table lists construction codes from group 17 that carry the N marking.
| Fraction | Catalogue code | Where to act |
|---|---|---|
| Building materials containing asbestos | 17 06 05 | Identify before work, remove through a permit holder, keep separate and packed |
| Insulation materials containing asbestos | 17 06 01 | Same route as other asbestos waste |
| Bituminous mixtures containing coal tar, coal tar and tar products | 17 03 01 and 17 03 03 | Check the composition before choosing a disposal route |
| Soil and stones containing hazardous substances | 17 05 03 | Sample and classify before excavation, keep separate from clean soil |
| Wood, glass and plastic containing or contaminated with hazardous substances | 17 02 04 | Separate at source and classify before collection |
| Gypsum-based materials contaminated with hazardous substances | 17 08 01 | Separate from clean gypsum boards |
| Other construction and demolition waste containing hazardous substances | 17 09 03 | Do not send to a mixed skip |
Whether a particular board, felt or soil belongs under an N code depends on its composition. The originator of hazardous waste must arrange sampling and analysis by a qualified person (§ 25 ods. 5). The exception is waste whose hazard and handling conditions are clear from the product safety data sheet or its documents.
Who may remove and handle asbestos waste in Slovakia?
Only a sole trader or legal person with a permit may remove asbestos from buildings (§ 41 ods. 1 of zákon č. 355/2007 Z. z.). The Úrad verejného zdravotníctva SR (ÚVZ SR) issues the permit and keeps a list of permit holders. The ÚVZ information page states that owners may not remove the material themselves. A natural person also may not handle construction waste containing asbestos from simple or small buildings (§ 12 ods. 6 of the waste act). A residential building is a simple building if it has at most three flats and at most 300 m2 of built-up area. It must also have at most two above-ground floors (§ 2 ods. 6 of zákon č. 25/2025 Z. z.). Many family houses meet these limits.
The ministry methodology of 13 September 2022 adds a second step. When the demolition contractor also dismantles and partly stabilises the material, that work counts as disposal. The contractor then needs a disposal consent from the district office under § 97 ods. 1 písm. b) of the waste act. The contractor also needs the bound trade licence Podnikanie v oblasti nakladania s nebezpečnými odpadmi. The ministry codes the partly stabilised waste as 19 03 04.
Who is responsible for hazardous waste on a demolition job?
The waste originator (pôvodca odpadu) answers for the waste under the act (§ 77 ods. 3). Take work at the seat or place of business of a legal person or sole trader. There the originator is the legal person or sole trader that holds the permit under the building act. For similar work done for natural persons, the originator is the person who does the work (§ 77 ods. 2). A private owner who orders a demolition from a contractor is therefore not the originator. A company that owns the site and holds the permit is.
The 2022 ministry methodology words the first rule differently, as the party for whom the work is finally carried out. The act text above is the later and binding one. Whoever the originator is, ask the contractor in writing who will collect, transport and dispose of each hazardous fraction. A holder may hand waste only to a person authorised to handle it (§ 14 ods. 1 písm. e)).
What must be checked before demolition starts?
Government regulation 185/2026 Z. z. on protecting employees from asbestos exposure applies from 15 July 2026. Take demolition, maintenance or refurbishment in a building built before 1 January 2005. Before it, the employer must take every available step to identify materials that may contain asbestos. This includes asking owners and other employers for information. If that information is missing, the employer must have the materials examined for asbestos before work starts (§ 8 ods. 1).
The employer must also prepare a risk assessment that covers handling of asbestos waste (§ 2 ods. 2 písm. e)). A work plan is due before demolition or asbestos removal starts (§ 8 ods. 5). The permit holder notifies the public health authority at least 30 days before work starts. The notice includes proof of disposal arrangements for the asbestos waste (§ 3 ods. 1 písm. j)). The workplace limit is 0.002 fibres per cm3 over eight hours for long, thin fibres (§ 2 ods. 4).
Separate waste duties apply to demolition. They include a written notice to the waste authority three working days before demolition and a report within 90 days afterwards. Construction and demolition waste explains them.
How must hazardous waste be separated and stored on site?
The waste act prohibits diluting hazardous waste. It also prohibits mixing it with other types of hazardous waste, with non-hazardous waste, or with materials that are not waste (§ 25 ods. 1). The act allows exceptions only under conditions such as a consent under § 97 ods. 1 písm. i) (§ 25 ods. 2). If mixing occurred, the waste authority may order the waste to be separated again when that is technically and economically possible (§ 25 ods. 3). In practice the hazardous fraction goes into its own container from the first day of stripping.
During collection, transport and storage, hazardous waste must be packed in suitable packaging and labelled (§ 25 ods. 4). For asbestos, the ministry methodology describes the usual approach. Coat the material with a penetrating stabiliser before dismantling. Dismantle with as little breakage as possible. Pack it in marked polyethylene bags, sheeting or big bags. Then collect it for transport to a hazardous waste landfill. A skip of general rubble cannot take these fractions, even in small quantities.
How is hazardous waste different from ordinary construction and demolition waste?
Holders sort ordinary construction and demolition waste for reuse, recycling or recovery where possible, following the waste hierarchy (§ 14 ods. 1 písm. d)). The same hierarchy applies to hazardous waste, but the act adds stricter rules at each step. The two categories occur on the same site, so the separation has to happen before the main demolition, not afterwards. The table compares the two routes.
| Aspect | Ordinary C&D waste | Hazardous construction waste |
|---|---|---|
| Collection on site | Collected sorted by type (§ 14 ods. 1 písm. b)) | Collected separately by type and labelled (§ 14 ods. 1 písm. c)) |
| Mixing | Not prohibited as such | Prohibited, with narrow exceptions (§ 25 ods. 1 and 2) |
| Packaging | No special rule in § 25 | Suitable packaging and labelling (§ 25 ods. 4) |
| Analysis | Not required by § 25 | Sampling and analysis by a qualified person, with exceptions (§ 25 ods. 5) |
| Handing over | Only to an authorised person (§ 14 ods. 1 písm. e)) | Only to an authorised person (§ 14 ods. 1 písm. e)) |
The act also says that hazardous waste is recovered or disposed of before waste that is not hazardous (§ 25 ods. 6).
Is hazardous waste always more expensive to remove?
This page quotes no price, because no dated public source gives one. The cost depends on the survey, the permit holder's work, the packaging, any sampling and the disposal route. Ask for the hazardous fractions to be priced as separate line items, so you can see what each step adds to the job. Selective approaches such as building deconstruction also help to sort the remaining material for recovery.
What misunderstandings are common about hazardous construction waste?
The first is that a small amount does not matter. Section 25 ods. 1 sets no volume threshold, and the ban on a natural person handling asbestos waste from a simple building has none either. The second is that the demolition contractor always carries the responsibility. The act names the permit holder as the originator for work at a company's premises. The third is that any licensed waste carrier can take asbestos. The permit to remove asbestos and the consent to dispose of it are separate permissions. Check each document before the first sheet is removed and keep the paperwork with the site file.
Frequently asked questions
- Is asbestos-cement waste hazardous in Slovakia?
- Yes. The waste catalogue lists building materials containing asbestos under code 17 06 05, marked N for hazardous waste. After partial stabilisation the ministry methodology codes it 19 03 04, which is also hazardous.
- Who may remove asbestos from a building in Slovakia?
- Only a sole trader or legal person with a permit from the Úrad verejného zdravotníctva SR (§ 41 ods. 1 of act 355/2007 Z. z.). ÚVZ SR issues the permit and keeps a list of permit holders. Owners may not do it themselves.
- Can I put hazardous waste in a normal skip with other rubble?
- No. The waste act prohibits mixing hazardous waste with non-hazardous waste or with other types of hazardous waste (§ 25 ods. 1). Hazardous fractions need their own packaging and labels.
- Does a survey have to be done before demolishing an older house?
- For buildings built before 1 January 2005, the employer must identify materials that may contain asbestos before demolition, maintenance or refurbishment starts. If information from owners or other employers is missing, the employer must have the materials examined before work starts (regulation 185/2026, § 8 ods. 1).
- Who is the waste originator on a demolition job?
- For work at the premises of a company or sole trader, it is the one that holds the permit under the building act. For similar work done for a natural person, it is the person who does the work (§ 77 ods. 2 of act 79/2015 Z. z.). Agree in writing who handles each hazardous fraction.
- How is hazardous construction waste different from construction and demolition waste?
- Hazardous waste must be collected separately, packed and labelled, and may not be mixed with other waste (§ 25 and § 14 ods. 1 písm. c)). Holders sort ordinary construction and demolition waste by type for reuse, recycling and recovery.
Sources
- Zákon č. 79/2015 Z. z. o odpadoch a o zmene a doplnení niektorých zákonov (version from 1 January 2026) · NR SR, consolidated PDF on Slov-Lex · § 12 ods. 6; § 14 ods. 1, 2; § 25 ods. 1, 4, 5, 8; § 77 ods. 2; § 97 ods. 1 písm. b)
- Nariadenie vlády SR č. 185/2026 Z. z. o ochrane zamestnancov pred rizikami súvisiacimi s expozíciou azbestu pri práci · Vláda SR, Slov-Lex PDF · § 1 ods. 3; § 2 ods. 4, 5; § 3 ods. 1; § 4 ods. 1, 2; § 5 ods. 1; § 8 ods. 1, 5, 6; § 15
- Zákon č. 355/2007 Z. z. o ochrane, podpore a rozvoji verejného zdravia (version from 1 August 2026) · NR SR, consolidated PDF on Slov-Lex · § 41 ods. 1, 6, 8, 11, 13
- Odstraňovanie azbestu zo stavieb (informácia) · Úrad verejného zdravotníctva SR
- Vyhláška MŽP SR č. 365/2015 Z. z., ktorou sa ustanovuje Katalóg odpadov (version from 1 January 2018) · MŽP SR, Slov-Lex PDF · Príloha č. 1, skupina 17 (17 06, 17 05, 17 03, 17 02, 17 09), podskupina 19 03
- Zákon č. 25/2025 Z. z. Stavebný zákon (version 1 November 2025 to 31 December 2026) · NR SR, consolidated text on Slov-Lex · § 2 ods. 6
- Metodická pomôcka MŽP SR k udeľovaniu súhlasu týkajúceho sa zneškodňovania stavebných odpadov s obsahom azbestu činnosťou D9 a D14 (13 September 2022) · MŽP SR · Zaradenie odpadu s obsahom azbestu; Udelenie súhlasu; Podnikanie v oblasti nakladania s nebezpečnými odpadmi