Between-rafter insulation

Between-rafter insulation is a layer of insulation fitted between the rafters of a pitched roof, with its thickness limited by rafter depth.

What is between-rafter insulation in a pitched roof?

Between-rafter insulation (medzikrokvová izolácia) is a layer of insulation fitted in the space between the rafters of a pitched roof. Greenspec, an independent UK guide, shows mineral wool and PUR or PIR board used in this position. The rafter depth sets the largest thickness the layer can reach.

Greenspec calls insulating the full depth of the rafters the most straightforward treatment. It raises the existing roof line only a little and keeps the internal space and head height. Dörken says the same about the height of the roof. A pure between-rafter roof is structurally not so high.

The method has two weaknesses. Greenspec says the shallow depth of the rafters might inhibit achievement of performance standards. It also lists thermal bridging through the rafters.

How does between-rafter insulation differ from above-rafter insulation?

The two methods differ in where the insulation sits relative to the timber. Above-rafter insulation lies on top of the rafters, so the rafter depth does not cap its thickness. Between-rafter insulation fills the space between them. The table shows the layouts that Greenspec describes.

LayoutHow the insulation is arrangedWhat Greenspec notes
Between rafters onlyInsulation fills the full depth of the raftersMinimal raising of the roof line. Shallow rafters might limit the performance. Thermal bridging through the rafters
Between and below raftersA second layer sits under the rafters. It is rigid board with an integral vapour control layer, or the rafters are extended with counter battensExtra depth for insulation, but it reduces the internal space and can compromise head height
Between and over raftersA layer over the rafters combines with the layer between themExtra depth and no loss of internal space, but it requires raising the roof line

Why does rafter depth limit how much between-rafter insulation fits?

The rafter depth is the upper limit for a between-rafter layer. A ventilation gap, if the design has one, takes part of that depth. Greenspec notes that some Victorian houses have rafters as shallow as 75 mm. With a continuous 50 mm gap under the sarking, there is often very little space left for insulation.

Greenspec gives typical U-values for several layouts. The table shows a selection.

Layout in the Greenspec guideThicknessU-value (W/m²K)
Between rafters only, mineral wool150 mm0.26
Between rafters only, PUR or PIR board150 mm0.22
Between and below rafters, mineral wool100 mm plus 100 mm0.18
Between and below rafters, mineral wool160 mm plus 100 mm0.15
Between and below rafters, mineral wool200 mm plus 100 mm0.12

These figures come from one UK guide and its product data. Greenspec attributes the mineral wool figures with a second layer to the manufacturer Knauf. Greenspec also quotes an Energy Saving Trust target of 0.20 W/m²K for rafter-level insulation. It says the normally achievable values are between 0.20 and 0.16 W/m²K, depending on the rafter depth and the available space.

A Slovak project does not take its target from this table. Section 26 subsection 3 of the Slovak decree refers the thermal requirements to the Slovak technical standards. Use the U-value that the design calculates for the actual build-up.

Where does the air and vapour barrier go in a between-rafter roof?

In most cases Greenspec places a combined air tightness and vapour control layer on the warm side of the insulation. That is the room side of the roof. Dörken describes the same position for a roof without hard sheathing. The air and vapour barrier sits on the room side, directly on the insulation and on the underside of the rafters. It protects the insulation from water vapour that escapes from the room air.

The Sd value compares how much vapour each layer passes. The entry on the vapour retarder covers the layer in more detail.

Greenspec adds three points about the layer on the inside:

  • It is essential to keep the air tightness of the construction.
  • If services run behind the layer, expect punctures where pipes and wires enter the room. Find them by site inspection and seal them.
  • A service zone, made with battens on the underside of the layer before the plasterboard goes on, is an alternative.

Greenspec also does not advise a vapour-resistant board over the rafters combined with low-resistance mineral wool between them. The exception is a roof with an effective vapour control layer on the underside of the rafters.

Is a ventilation gap needed above between-rafter insulation?

The answer depends on the underlay and the roof type. Greenspec describes two types.

  • Ventilated roof. The roof has a continuous 50 mm gap above the between-rafter insulation, vented to the eaves and to the ridge. Greenspec asks for ventilation at the eaves equal to a 25 mm continuous strip and at the ridge equal to a 5 mm continuous strip.
  • Unventilated roof. A breather membrane with low vapour resistance lets moisture from inside pass through it. A ventilated cavity formed by counter battens over the rafters then disperses the moisture. This lets the insulation fill the full depth of the rafter.

Dörken describes the unventilated case for a new building. A roofing membrane goes directly on the insulation above the rafters. The membrane also works as the underlay, and it protects the insulation from moisture from the outside.

The gap figures are UK values. The Slovak design should follow the roof covering manufacturer and the Slovak technical standards. The ventilated roof cavity entry and the roof underlay membrane entry explain the layers above the insulation.

What does Slovak regulation say about condensation in a roof?

Decree 532/2002 Z. z. sets the general technical requirements for construction. Under Act 25/2025 Z. z. the decree stays in force until new implementing regulations take effect, at the latest until 31 March 2027 (§ 84 ods. 23 písm. b of the act). Section 26 subsection 4 says the roof must be designed so that water vapour does not condense in it. The same subsection accepts a roof where vapour does condense, if the function and service life of the external wall are not endangered.

Section 26 subsection 3 says the roof must meet the requirements for heat transfer, water vapour diffusion and airtightness that the Slovak technical standards set. The decree gives no thickness or U-value. We read the consolidated text dated 1 March 2020 on Slov-Lex. Check that it is the version in force for your project.

The decree also requires a guard against sliding snow on a pitched roof with roof planes steeper than 25 degrees (subsection 6). That rule concerns the covering, not the insulation.

What mistakes are common with between-rafter insulation?

The points below follow from the guidance cited on this page.

  • Choosing the insulation by thickness alone, without checking how much depth remains for a ventilation gap and the vapour layer.
  • Expecting the between-rafter layer alone to reach the performance of a layout with a second layer below the rafters.
  • Combining a vapour-resistant board over the rafters with low-resistance mineral wool between them, without a vapour control layer on the underside of the rafters.
  • Leaving out the continuous gap above the insulation in a ventilated roof.
  • Leaving punctures in the air tightness layer where services run through it.

A between-rafter build-up is a design of depth and layers. The right choice depends on the rafters that the roof actually has.

Frequently asked questions

What is the difference between between-rafter and above-rafter insulation?
Between-rafter insulation sits in the space between the rafters, so the rafter depth limits its thickness. Above-rafter insulation lies on top of the rafters, so the rafter depth does not cap it. Greenspec notes that insulation over the rafters needs a higher roof line.
Does between-rafter insulation need a vapour control layer?
In most cases, yes. Greenspec places a combined air tightness and vapour control layer on the warm side of the insulation, which is the room side of the roof. Dörken puts an air and vapour barrier directly on the insulation, on the underside of the rafters.
How much does a second layer under the rafters change the U-value?
In Greenspec's typical UK values, 150 mm of mineral wool between the rafters gives 0.26 W/m²K. Adding a second 100 mm layer below the rafters to 100 mm between them gives 0.18 W/m²K. These are UK figures for one set of products.
Is a ventilation gap needed above between-rafter insulation?
It depends on the roof type. Greenspec's ventilated roof needs a continuous 50 mm gap above the insulation, vented to the eaves and the ridge. Its unventilated roof uses a vapour-permeable breather membrane, so the insulation can fill the full rafter depth.
Can foam board over the rafters go with mineral wool between them?
Greenspec does not advise it, unless an effective vapour control layer sits on the underside of the rafters. A vapour-resistant board over the rafters combined with low-resistance mineral wool between them Check the combination with the manufacturers.
Does Slovak regulation allow a roof where vapour condenses?
Yes, in one case. Section 26 subsection 4 of Decree 532/2002 Z. z. says the roof must be designed so that vapour does not condense in it. It accepts a roof where vapour does condense if the function and service life of the external wall are not endangered.

Sources

  1. Vyhláška Ministerstva životného prostredia Slovenskej republiky č. 532/2002 Z. z., ktorou sa ustanovujú podrobnosti o všeobecných technických požiadavkách na výstavbu · Ministerstvo životného prostredia SR, via Slov-Lex · § 26 ods. 3, 4 a 6
  2. Zákon č. 25/2025 Z. z. o výstavbe a o zmene a doplnení niektorých zákonov (stavebný zákon) · Národná rada SR, via Slov-Lex · § 84 ods. 23 písm. b
  3. Housing Retrofit: Unventilated pitched roof insulation · Greenspec (UK independent guidance) · Insulation positions: between the rafters only, between and below, between and above; Air tightness
  4. Housing Retrofit: Ventilated pitched roof insulation · Greenspec (UK independent guidance) · The converted / refurbished roof; U-value target; Ventilation; Air tightness
  5. Roof systems for new buildings · Dörken GmbH & Co. KG · Pure between-rafter insulation