Micropile

A micropile is a small-diameter drilled pile, grouted and reinforced with steel, used to support or strengthen a building's foundation.

What is a micropile?

A micropile is a small-diameter pile that is drilled into the ground, filled with grout and reinforced with a steel element in the centre. The Federal Highway Administration (FHWA) describes micropiles as small-diameter, drilled piles of placed or injected grout. Steel reinforcement in the centre resists most of the design load. The Slovak term is mikropilóta.

The STU textbook Konštrukcie spodnej stavby sets the size limit. A micropile is a slender element with a diameter up to 300 mm. An element wider than 300 mm is an ordinary pile.

FHWA records that micropile technology was conceived in Italy in the early 1950s. It served as a flexible foundation system to underpin, repair or retrofit damaged structures. That origin explains why people often discuss micropiles as a remedy for an existing foundation.

How does a micropile carry the load?

The STU textbook describes three parts. The head takes the load from the building. The shaft passes through layers that cannot carry load. The root is grouted into the surrounding ground and passes the load on to it.

The textbook names three types.

TypeLoad-bearing partUse today, per the textbook
Pipe micropileThick-walled steel pipes 70 to 150 mm in diameter, joined by threaded connectionsMost used
Solid bar micropileSolid steel bar 50 mm in diameterUsed in recent years
Reinforcement cage micropileCage of steel bars, for example 3 to 5 bars of 32 mmLess used. The textbook says this type is no longer used

The textbook describes the pipe micropile in detail. Thick-walled steel pipes 70 to 150 mm in diameter carry the load. Designers often place them in drilled holes of 118, 137 or 150 mm. A solid steel bar 50 mm in diameter can serve as the load-bearing element instead. The sequence of work has five steps.

  • Drill the hole, usually with a temporary steel casing.
  • Fill the hole with cement grout and pull out the casing.
  • Place the steel pipe or bar in the hole before the grout sets.
  • Inject the root after the grout sets, at a pressure of at least 0.5 MPa.
  • Repeat the injection if the pressure is not reached, to raise the skin friction.

The textbook gives one capacity figure. It applies if the root is embedded at least 3 m in a bearing layer. Then the micropile reaches 400 to 500 kN. The design, the ground and the connection to the building set the real capacity.

How is a micropile different from traditional underpinning?

Underpinning is the general name for securing or strengthening a foundation. The STU textbook describes the traditional method of gradual deepening. Crews dig short work pits, undercut part of the old foundation and cast the new part. They fill the pit back before they move to the next stage.

AspectGradual deepeningMicropile underpinning
Main workShort pits, undercutting of the old foundation, new concrete or brickworkDrilling, placing the steel element and injecting grout
Limits in the textbookSimple static conditions, buildings up to five storeys, pit depth up to 5 m. Otherwise prove stability by calculation at every stageThe textbook states no such limits. Assess the effect of a local repair on the old foundation
Pit sizeWork pits up to 1.35 m wide with gaps of at least 4 mMobile drilling rigs work in cramped spaces close to walls and columns
Direction of the elementVertical work pitsVertical or inclined

The textbook says that micropiles now replace the traditional methods of underpinning in many cases. Their production is fairly simple and needs little space. The choice is a design decision for a structural engineer with geotechnical input.

When is micropile underpinning used on an existing building?

The STU textbook says underpinning is necessary in three cases. A building pit that reaches below the foundation base is dug next to the building. Part of a basement is deepened inside the building. The properties of the foundation soil have got worse. If the bearing ground lies deep, the textbook describes the use of deep foundation elements such as drilled piles.

Micropiles also suit new buildings. The textbook says designers now often prefer them for new deep foundations where space is limited and access to the site is poor.

How does a micropile connect to the old foundation?

The textbook warns that the connection detail needs attention. The load must pass reliably into the bearing layers. It describes two ways:

  • Drill an inclined hole through the brick foundation masonry and insert the micropile. The load passes through the bond of the grout to the masonry, or through a steel plate on the micropile head.
  • Embed the micropiles in reinforced concrete ring beams on both sides of the old foundation. Horizontal steel ties can strengthen the link.

Another reason to check the old foundation first comes from a case in Dallas. GEI Consultants describes a seven-story building that needed support. The owners planned a nine-story expansion with a three-level basement, and a new 22-story residential tower stood next to it. The designers first planned to reuse the existing footings. A field investigation then showed that the concrete of the footings was much weaker than anticipated, and several footings were thinner than expected. The team connected the micropiles to the grade beams and bypassed the old footings. The connection used a load transfer frame with tensioned tie rods, clamped onto the existing structure.

The case is a large commercial building, not a family house. It shows one lesson for any house. Test the old foundation before you choose the method, because the assumed strength can differ from the real one. See tie rod.

What problems with a foundation lead to underpinning?

The STU textbook lists causes of excessive or uneven settlement of a building:

  • a faulty foundation design because the ground was not known,
  • wrong building procedures during construction,
  • a change of soil bearing capacity during use, for example from a changing groundwater level or faulty drainage,
  • a higher load after a change of use,
  • frost, where the foundation is not deep enough.

The textbook says that the choice of repair depends on a detailed analysis of all causes. See building settlement and differential settlement. If cracks appear, a structural engineer should find the cause first.

Can repairing only part of a foundation cause new settlement?

Yes. The STU textbook says designers must assess the effect of a local repair, for example micropiles under part of the foundations. The risk is differential settlement between the original and the repaired foundations. Plan a partial repair with the whole foundation in mind.

How is a micropile different from a pile foundation?

A pile foundation is a whole foundation system. The STU textbook divides deep foundation elements by size. Piles have a diameter larger than 300 mm. Micropiles have a diameter smaller than 300 mm. Designers use deep foundations when the ground that can carry the building lies far below the surface.

Does a micropile repair the cracks by itself?

No. A micropile changes how the foundation is supported. It does not repair the cracks in the walls. The textbook says that a foundation repair must lead to reliable removal of the cause of settlement. The structural crack needs its own assessment before you choose a repair.

If a crack keeps moving after the foundation is supported, look for another cause. Monitoring over time shows whether the movement stops.

Frequently asked questions

What is a micropile in plain words?
It is a narrow pile drilled into the ground and filled with cement grout, with a steel element in the centre. The steel carries most of the design load. The STU textbook gives the diameter as up to 300 mm. Larger elements are ordinary piles.
How strong is a micropile?
It depends on the design. The STU textbook gives 400 to 500 kN for a micropile with its root embedded at least 3 m in a bearing layer. That is a textbook figure, not a design value. A structural engineer sets the real capacity for the ground and the building.
Is a micropile the same as underpinning?
No. Underpinning is the goal of securing a foundation, for example while a deep pit is dug next to it. Micropiles are one way to do it. The traditional way is to deepen the foundation in short sections. The right method depends on access, ground and load.
Can micropiles be installed inside a house?
Often yes. The STU textbook says mobile drilling rigs can work close to bearing walls and columns in cramped basement spaces. A structural engineer should check the access route and the ceiling height before the method is chosen.
Does a micropile repair the cracks in the walls?
No. A micropile changes how the foundation is supported. The STU textbook says a foundation repair must reliably remove the cause of the settlement. Wall cracks are a separate repair, done after the movement stops.
How do I compare offers for micropile underpinning?
Ask each contractor to price the same design from the same structural engineer. Then compare the access plan, the amount of excavation and the monitoring of movement during the work. Offers for different scopes are not comparable.

Sources

  1. Chapter 2: Foundation Engineering Project, A Quarter Century of Geotechnical Research (section 2.6.7 Micropiles) · Federal Highway Administration (FHWA) · 2.6.7 Micropiles
  2. Micropile Underpinning at Hines Maple Terrace · GEI Consultants · Project description
  3. Micropile Design and Construction Guidelines: Implementation Manual (FHWA-SA-97-070) · U.S. Federal Highway Administration
  4. Konštrukcie pozemných stavieb: Konštrukcie spodnej stavby · Slovenská technická univerzita v Bratislave, Stavebná fakulta (Juraj Žilinský a kol.) · 20 Hĺbkové základy; 20.2 Mikropilóty; 22 Sanácie základov; 22.1; 22.2 Podchytávanie základov mikropilótami